DEPARTMENT OF POWER<br />

ANNUAL REPORT<br />

<strong>1991</strong>-<strong>92</strong><br />

lR;eso t;rs<br />

MINISTRY OF POWER AND<br />

NON-CONVENTIONAL ENERGY SOURCES<br />

GOVERNMENT OF INDIA, NEW DELHI


HVDC Transmission Tower<br />

Cover Photo - Rihand Super Thermal <strong>Power</strong> Project <strong>of</strong> NTPC


CONTENTS<br />

Department <strong>of</strong> <strong>Power</strong> 2<br />

The Year Under Review 3<br />

Central Electricity Authority 26<br />

Assistance to the State Electricity Boards 28<br />

Private Sector Participation 28<br />

Public Sector Undertakings and other Organisations 32<br />

CHARTS AND MAP<br />

Growth <strong>of</strong> Electricity Generation (Utilities) 3<br />

All India Sector-wise PLF 4<br />

Growth <strong>of</strong> Installed Generating Capacity (Utilities) 8<br />

Growth <strong>of</strong> Capacity Additions 14<br />

All India Installed Generating Capacity Mix (Percentage) 16<br />

Villages Electrified 17<br />

Pumpsets/Tubewells Energise 18<br />

Electricity Statistics at a glance 54<br />

New Tehri Town


1. DEPARTMENT OF POWER<br />

1.1 ORGANISATION<br />

The <strong>Ministry</strong> <strong>of</strong> Energy, comprising the Department <strong>of</strong><br />

<strong>Power</strong>, Department <strong>of</strong> Coal and Department <strong>of</strong> Nonconventional<br />

Energy Sources, was reconstituted in June,<br />

<strong>1991</strong>, and a new <strong>Ministry</strong> <strong>of</strong> <strong>Power</strong> and Nonconventional<br />

Energy Sources was formed comprising the<br />

Department <strong>of</strong> <strong>Power</strong> and the Department <strong>of</strong> Nonconventional<br />

Energy Sources. Shri Kalyan Singh Kalvi,<br />

Minister for Energy and Shri Babanrao Dhakne, Minister<br />

<strong>of</strong> State <strong>of</strong> Energy, demitted the charge <strong>of</strong> their <strong>of</strong>fices,<br />

on the 20th June, <strong>1991</strong>. Shri Kalp Nath Rai took over as<br />

Minister <strong>of</strong> State for <strong>Power</strong> and Non-conventional Energy<br />

Sources (Independent Charge) on the 24th June, <strong>1991</strong>.<br />

Shri S. Rajgopal is Secretary in the Department <strong>of</strong> <strong>Power</strong>.<br />

He is assisted by a Special Secretary and six Joint<br />

Secretaries, including the Financial Adviser.<br />

There are six Wings in the Department <strong>of</strong> <strong>Power</strong>, each<br />

headed by a Joint Secretary. These are :<br />

I) Energy Management & Administration Wings:<br />

II) Planning & Coordination Wing:<br />

III) Thermal Wing:<br />

IV) Hydel Wing:<br />

V) Systems & Operation Wing: and<br />

VI) Finance Wing.<br />

The Central Electricity Authority (CEA), constituted<br />

under the Electricity (Supply) Act, 1948, advises the<br />

Department <strong>of</strong> <strong>Power</strong> on technical and economic matters.<br />

The construction and operation <strong>of</strong> generation and<br />

transmission projects in the Central Sector are entrusted<br />

to Central Sector <strong>Power</strong> Corporations, namely, the<br />

National Thermal <strong>Power</strong> Corporation (NTPC), the<br />

National Hydro-electric <strong>Power</strong> Corporation (NHPC), the<br />

North-Eastern Electric <strong>Power</strong> Corporation (NEEPCO),<br />

and the National <strong>Power</strong> Transmission Corporation<br />

(NPTC). The NTPC, which was incorporated on the 23rd<br />

October, 1989, will henceforth be responsible for all the<br />

existing and future transmission projects in the Central<br />

Sector and also for the formation <strong>of</strong> the National <strong>Power</strong><br />

Grid. Apart from the above organisations, there are two<br />

joint venture <strong>Power</strong> Corporations under the administrative<br />

control <strong>of</strong> the Department <strong>of</strong> <strong>Power</strong>, namely: Nathpa<br />

Jhakri <strong>Power</strong> Corporation and Tehri Hydro Development<br />

Corporation, which are responsible for the execution <strong>of</strong><br />

the Nathpa Jhakri <strong>Power</strong> Project and projects <strong>of</strong> the Tehri<br />

Hydro <strong>Power</strong> Complex, respectively. The Damodar<br />

Valley Corporation (DVC), constituted under the DVC<br />

Act, 1948, and the Bhakra Beas Managment Board<br />

(BBMB), constituted under the Punjab Reorganisation<br />

Act, 1966, are also under the administrative control <strong>of</strong> the<br />

Department <strong>of</strong> <strong>Power</strong>. The Department <strong>of</strong> <strong>Power</strong> also<br />

administers the Beas Construction Board (BCB), which is<br />

2<br />

a construction agency. Further, the Central <strong>Power</strong><br />

Research Institute (CPRI), the <strong>Power</strong> Engineers Training<br />

Society (PETS), and the Energy Management Centre<br />

(EMC) are under the administrative control <strong>of</strong> the<br />

Department <strong>of</strong> <strong>Power</strong>. Programmes <strong>of</strong> rural electrification<br />

are within the purview <strong>of</strong> the Rural Electrification<br />

Corporation (REC). The <strong>Power</strong> Finance Corporation<br />

(PFC) provides term-finance to projects in the <strong>power</strong><br />

sector.<br />

1.2 FUNCTIONS<br />

The primary responsibility <strong>of</strong> the Department <strong>of</strong> <strong>Power</strong><br />

pertains to the development <strong>of</strong> electrical energy in the<br />

country. The Department is concerned with perspective<br />

planning, policy formulation, processing <strong>of</strong> projects for<br />

investment decision, monitoring <strong>of</strong> the projects, training<br />

and man<strong>power</strong> development and the administration and<br />

enactment <strong>of</strong> legislation in regard to <strong>power</strong> generation,<br />

transmission and distribution. The Department <strong>of</strong> <strong>Power</strong> is<br />

also responsible for the administration <strong>of</strong> the Electricity<br />

(Supply) Act, 1948 and the Indian Electricity Act, 1910<br />

and to undertake such amendments to these Acts, as may<br />

be necessary from time to time, in conformity with the<br />

Government's policy objectives.<br />

To deal with the matters relating to private sector<br />

participation in <strong>power</strong> generation, supply and distribution,<br />

an Investment Promotion Cell has been set up in the<br />

Department <strong>of</strong> <strong>Power</strong>.<br />

1.3 ENERGY POLICY<br />

The Energy Policy <strong>of</strong> the Government <strong>of</strong> India aims at<br />

ensuring adequate energy supplies at a minimum cost,<br />

achieving self-sufficiency in energy supplies and<br />

protecting the environment from the adverse impact <strong>of</strong><br />

utilising energy resources in an injudicious manner. The<br />

main elements <strong>of</strong> Energy Policy are:<br />

— Accelerated exploitation <strong>of</strong> conventional energy<br />

sources, viz coal hydel, oil and nuclear <strong>power</strong>.<br />

— Management <strong>of</strong> demand for oil and other forms <strong>of</strong><br />

energy.<br />

— Energy Conservation and Management, with a view to<br />

increase energy productivity.<br />

— Optimising the utilisation <strong>of</strong> existing capacity in the<br />

country.<br />

— Development and exploitation <strong>of</strong> renewable sources <strong>of</strong><br />

energy to meet the energy requirement <strong>of</strong> rural<br />

communities.<br />

— Intensification <strong>of</strong> research and development activities<br />

in the field <strong>of</strong> new and renewable energy sources.<br />

— Organisation <strong>of</strong> training for the personnel engaged at<br />

various levels in the energy sector.


2.0 THE YEAR UNDER REVIEW<br />

During the year <strong>1991</strong>-<strong>92</strong> (upto December, <strong>1991</strong>) the<br />

National Thermal <strong>Power</strong> Corporation (NTPC)<br />

commissioned a total generating capacity <strong>of</strong> 210 MW,<br />

raising its total installed capacity to 10335 MW. The<br />

generation from the NTPC <strong>power</strong> stations during <strong>1991</strong>-<strong>92</strong><br />

(upto Dec, 91) has been 44190 million units as against the<br />

target <strong>of</strong> generation <strong>of</strong> 54847 million units for the entire<br />

year. As against the target <strong>of</strong> 860 Ckt Kms <strong>of</strong><br />

transmission lines, the NTPC completed 775 Ckt Kms <strong>of</strong><br />

transmission lines (upto Dec, 91). A Memorandum <strong>of</strong><br />

Understanding (MOU) for the year <strong>1991</strong>-<strong>92</strong> was signed<br />

between the NTPC and the Department <strong>of</strong> <strong>Power</strong>. The<br />

MOU clearly identifies the performance targets to be<br />

achieved by the NTPC during the year with respect to<br />

<strong>power</strong> generation, additional new capacity and<br />

construction <strong>of</strong> transmission lines, apart from laying down<br />

the actions to be taken by the Government to enable to the<br />

achievement <strong>of</strong> these targets.<br />

The NTPC qualified for the meritorious productivity<br />

award for the year <strong>1991</strong> for achieving high standards <strong>of</strong><br />

3<br />

performance. Four employees <strong>of</strong> the Vindhyachal STPP<br />

were awarded the Prime Minister Shram Bhushan Award<br />

in <strong>1991</strong> for their outstanding and meritorious work<br />

performance. The NTPC has also won the Company<br />

Standardisation Council Award in <strong>1991</strong>.<br />

As per the provisional estimates the NTPC earned a net<br />

pr<strong>of</strong>it <strong>of</strong> Rs. 700.95 crores during <strong>1991</strong>-<strong>92</strong>.<br />

The performance <strong>of</strong> the National Hydro-electric <strong>Power</strong><br />

Corporation was also commendable during <strong>1991</strong>-<strong>92</strong>.<br />

The Corporation which is responsible for the operation<br />

and maintenance <strong>of</strong> Baira Suil, Loktak and Salal Stage-I<br />

projects, generated 2785.44 million units in <strong>1991</strong>-<strong>92</strong><br />

(upto Dec, 91) as against the target generation <strong>of</strong> 2770<br />

million units. The performance <strong>of</strong> the NHPC's<br />

transmission system also exceeded the target during the<br />

year under review. Its Jeypore-Talcher transmission<br />

system transmitted 404.56 million units <strong>of</strong> <strong>power</strong> upto<br />

December, <strong>1991</strong> as compared to the target <strong>of</strong> 304.68<br />

million units during the year <strong>1991</strong>-<strong>92</strong>.


2.1 POWER GENERATION<br />

2.2 HIGHLIGHTS<br />

As a result <strong>of</strong> favourable monsoon, the generation targets<br />

fixed for <strong>1991</strong>-<strong>92</strong> (upto December, 91) for Hydro, have<br />

been exceeded during the period April, <strong>1991</strong> to<br />

December, <strong>1991</strong>. The Thermal generation was 2.7% less<br />

than the programme. However, it was 11.8% more than<br />

that <strong>of</strong> the corresponding period <strong>of</strong> last year. The Hydro<br />

generation during this period was 11.5% more than the<br />

programme and 4.4% more than that <strong>of</strong> last year.<br />

The total energy generation in the country during 1990-91<br />

was 264.231 BUs, showing an increase <strong>of</strong> 7.8% over the<br />

generation in 1989-90. The increase in Thermal<br />

generation during 1990-91 over the previous year was<br />

4.4%. The Hydro generation registered an increase <strong>of</strong><br />

15.4% during 1990-91 over the last year because <strong>of</strong><br />

favourable monsoon.<br />

For the year <strong>1991</strong>-<strong>92</strong>, the generation target <strong>of</strong> 283.450<br />

BUs has been fixed, comprising 211.700 BUs Thermal,<br />

6.850 BUs. Nuclear and 64.900 BUs Hydro <strong>Power</strong>. This<br />

envisaged an increase <strong>of</strong> about 7.2% over the generation<br />

achieved during 1990-91.<br />

During the period April, <strong>1991</strong> to December, <strong>1991</strong> the<br />

Hydro generation was about 4.4% more than that <strong>of</strong> last<br />

year. This was mainly due to favourable monsoon. The<br />

Thermal generation was however 2.7% less than the<br />

programme because <strong>of</strong> backing down due to low system<br />

demand, delay in commissioning and stabilisation <strong>of</strong><br />

certain units and non availability <strong>of</strong> requisite quantity and<br />

quality <strong>of</strong> coal. The total generation during this period<br />

was 211.381 BUs which is 9.01% more than the<br />

generation during the corresponding period <strong>of</strong> the<br />

previous year. The actual generation during the period,<br />

April <strong>1991</strong> to December, <strong>1991</strong>, as compared with the<br />

target is given below :-<br />

(Figures in MU)<br />

APRIL TO DECEMBER, <strong>1991</strong><br />

Type <strong>of</strong> Programme Actual %age %age <strong>of</strong> the<br />

Generation <strong>1991</strong> <strong>1991</strong> <strong>of</strong> the Corresponding<br />

programme period/<br />

last year<br />

Thermal 154738 150597 97.3 111.6<br />

Nuclear 4593 3943 85.8 82.0<br />

Hydro 50965 56841 111.5 104.4<br />

Total 210296 211381 100.6 109.0<br />

4<br />

2.3 PLANT LOAD FACTOR OF THERMAL<br />

STATIONS<br />

Thermal capacity, at present consitutes abot 69% <strong>of</strong> the<br />

total installed capacity, in the country, and contributes<br />

about 72% <strong>of</strong> the total <strong>power</strong> generation. At the beginning<br />

<strong>of</strong> the 6th Five Year Plan, the performance <strong>of</strong> the thermal<br />

<strong>power</strong> stations was unsatisfactory with the plant load<br />

factor <strong>of</strong> 44.3% only. To improve their performance, a<br />

number <strong>of</strong> measures were taken to achieve the optimum<br />

utilisation <strong>of</strong> the existing thermal units. At the beginning<br />

<strong>of</strong> 7th Five Year Plan i.e., 1985-86, the PLF improved to<br />

52.4% and further increased to 53.2% in 1986-87. During<br />

1987-88, the PLF increased to 56.5% which was the<br />

highest achieved in any year. During 1990-91 the PLF<br />

was 53.80%. The decrease in PLF during 1990-91 over<br />

the previous year was mainly due to favourable monsoon<br />

and consequent reduction in demand, particularly in<br />

agricultural sector, resulting in low thermal generation.<br />

During the period April, <strong>1991</strong> to December, <strong>1991</strong> the PLF<br />

has been 53.4%.<br />

During the period April, <strong>1991</strong> to December, <strong>1991</strong>, the<br />

following State Electricity Board/Corporations achieved<br />

PLF higher than the All-India average <strong>of</strong> 53.4%.


Sl. No. State Electricty Boards/<br />

Corporations<br />

PLF (%)<br />

1. Rajasthan 61.0<br />

2. Punjab 54.9<br />

3. Gujarat 55.0<br />

4. Maharashtra 59.6<br />

5. Andhra Pradesh 57.0<br />

6. Karnataka <strong>Power</strong> Corporation 55.1<br />

7. West Bengal <strong>Power</strong> Development<br />

Corporation 64.1<br />

8. N.T.P.C. 66.2<br />

9. Neyveli 63.6<br />

10. A.E.Co. 68.3<br />

11. Trombay 54.7<br />

12. C.E.S.C. 59.7<br />

In the State Sector Anpara Thermal <strong>Power</strong> Station <strong>of</strong><br />

UPSEB achieved the highest Plant Load Factor <strong>of</strong> 69.0%<br />

during April, <strong>1991</strong> to December, <strong>1991</strong>. In the private<br />

sector, Ahmadabad Electric Co, achieved the highest<br />

Plant Load Factor <strong>of</strong> 68.3 during the period. In the central<br />

sector Singrauli Super Thermal <strong>Power</strong> Station <strong>of</strong> NTPC<br />

achieved the highest PLF <strong>of</strong> 75.6% during this period.<br />

2.4 MERITORIOUS PRODUCTIVITY<br />

AWARD SCHEME<br />

The meritorious Productivity Award Scheme for better<br />

performance <strong>of</strong> Thermal <strong>Power</strong> Stations is being<br />

implemented by the Department <strong>of</strong> <strong>Power</strong> since 1983-84.<br />

The objective <strong>of</strong> this Scheme is to maximise Thermal<br />

Generation by motivating employees working in various<br />

Thermal <strong>Power</strong> Stations by providing cash awards to<br />

them for significant increase in Thermal Generation in<br />

their respective stations. For the year 1990 the following<br />

<strong>power</strong> stations received awards under this scheme:-<br />

1. Raichur TPS 2. Vijayawada TPS<br />

3. Tuticorin TPS 4. Bhusawal TPS<br />

5. Gandhi Nagar TPS 6. Anpara TPS<br />

7. Chandrapur (Mah) TPS 8. Korba West TPS<br />

9. Kolaghat TPS 10. Parli TPS<br />

11. Korba East TPS 12. Obra TPS<br />

13. Koradi TPS 14. Singrauli TPS<br />

15. Neyveli-I TPS 16. Neyveli-II TPS<br />

17. Ropar TPS 18. Farakka TPS<br />

19. Bokaro 'B' TPS 20. Badarpur TPS<br />

21. Ukai TPS 22. Ennore TPS<br />

23. Faridabad TPS<br />

5<br />

The scheme has been continued in <strong>1991</strong>-<strong>92</strong> also. A<br />

provision <strong>of</strong> Rs. 250.00 lakhs has been provided in the<br />

Revised Estimate. A similar provision <strong>of</strong> Rs. 350 lakhs<br />

has been proposed in the Budget Estimates 19<strong>92</strong>-93.<br />

During the VIII Five Year Plan 19<strong>92</strong>-93 to 1996-97, a<br />

total <strong>of</strong> Rs. 12.50 crores is likely to be spent on this<br />

scheme assuming an average expenditure <strong>of</strong> Rs. 2.50<br />

crores during the each year <strong>of</strong> the Plan.<br />

Another scheme for incentive award for efficient and<br />

economic operation <strong>of</strong> Thermal <strong>Power</strong> Stations in the<br />

country has also been approved. Under this scheme also,<br />

during the VIII Five Year Plan 19<strong>92</strong>-93 to 1996-97, a total<br />

amount <strong>of</strong> Rs. 12.50 crores is estimated to be incurred<br />

assuming an expenditure <strong>of</strong> Rs. 2.50 crores during each<br />

year <strong>of</strong> the Plan.<br />

2.5 RENOVATION AND<br />

MODERNISATION OF<br />

THERMAL POWER STATIONS<br />

2.6 R&M PROGRAMME PHASE-I<br />

With a view to improve the performance <strong>of</strong> the existing<br />

thermal <strong>power</strong> stations, a massive renovation and<br />

modernisation (R&M) programme has been launched all<br />

over the country.<br />

The scheme covers 34 selected thermal <strong>power</strong> stations<br />

comprising 164 thermal units (including 2 units <strong>of</strong> 55 MW<br />

each damaged in fire at Durgapur TPS) aggregating to a<br />

total capacity <strong>of</strong> 13585.5 MW. The total sanctioned cost<br />

<strong>of</strong> various renovation schemes is Rs. l083 crores. Of this,<br />

Rs. 455 crores is being provided under Central Loan<br />

Assistance and Rs. 628 crores will have to be financed by<br />

the States under State Plan/Own Resources. In so far as<br />

the Central Assistance is concerned, the Government <strong>of</strong><br />

India had approved an amount <strong>of</strong> Rs. 500 crores in 1984,<br />

for providing Central Loan Assistance (CLA) to various<br />

State Elecy. Boards/Organisations to supplement their<br />

efforts.<br />

The <strong>Power</strong> Finance Corproation have taken over from<br />

CEA, the function <strong>of</strong> releasing CLA fund from 1988-89<br />

onwards. A total amount <strong>of</strong> Rs. 344.22 crores has been<br />

released to various State Electricity Boards/Organisations<br />

under Central Loan Assistance upto December, <strong>1991</strong><br />

against a total budgetted outlay <strong>of</strong> Rs. 435.48 crores. In<br />

addition, various State Electricity Board/Organisations


have incurred a total expenditure <strong>of</strong> Rs. 499.99 crores<br />

against total Budgetted allocation <strong>of</strong> Rs. 971.68 crores<br />

under State Plan/Own Resources upto December, <strong>1991</strong>.<br />

CEA continues to supervise and monitor the<br />

implementation <strong>of</strong> R&M Programme. The status <strong>of</strong><br />

implementation <strong>of</strong> R&M activities is shown in the Exhibit<br />

enclosed. Some <strong>of</strong> the thermal units where substantial<br />

R&M works have been carried out, have shown marked<br />

improvement in their performances as shown in Table-I.<br />

2.7 R&M PROGRAMME PHASE-II<br />

Keeping in view the benefits being accrued out <strong>of</strong> the<br />

Phase-I R&M Programme during the VII Plan period, its<br />

second phase has been launched for completion during<br />

8th Plan period with the objective to achieve optimum<br />

per<strong>of</strong>ormance results from the old thermal units. The total<br />

tentative cost <strong>of</strong> the R&M programme (Phase-II) covering<br />

46 old thermal <strong>power</strong> stations comprising 201 generating<br />

units aggregating to a total capacity <strong>of</strong> 19980.9 MW, is<br />

Rs. 1328 crores (Includes Rs. 68 crores <strong>of</strong> World Bank<br />

Loan Assistance). Of the total 46 schemes <strong>of</strong> the TPS, 40<br />

schemes covering 174 units aggregating to a capacity <strong>of</strong><br />

18706 MW at a total estimated cost <strong>of</strong> Rs. 1201 crores<br />

(includes Rs. 68 crores <strong>of</strong> World Bank Loan Assistance)<br />

have been cleared by CEA and the balance 6 schemes<br />

covering 27 units aggregating a capacity <strong>of</strong> 1274.9 MW at<br />

a total tentative cost <strong>of</strong> Rs. 127 crores are under<br />

examination.<br />

The implementation <strong>of</strong> the schemes has already<br />

commenced and a total expenditure <strong>of</strong> Rs. 5.98 crores has<br />

been incurred upto December, <strong>1991</strong>.<br />

TABLE-I<br />

STATEMENT SHOWING IMPROVEMENT IN PLF OF THERMAL UNITS WHERE<br />

SUBSTANTIAL R&M WORKS HAVE BEEN CARRIED OUT.<br />

(From 1.4.91 to 31.12.91)<br />

Sl. Name <strong>of</strong> Unit Particulars PLF based on present Remarks/<br />

No. TPS (NO.) Capacity (%) Original<br />

Present PLF/Before PLF after rated<br />

Capacity Renovation carrying out capacity<br />

(MW) substantial<br />

renovation works<br />

(MW)<br />

1 2 3 4 5 6 7<br />

1. Badarpur 1 95 48.1 75.1 100<br />

2 95 55.7 53.1 100<br />

3 95 60.2 68.3 100<br />

4 210 44.2 62.8 –<br />

5 210 37.0 54.4 –<br />

2. I.P. 3 62.5 53.5 72.0 –<br />

4 62.5 49.7 58.2 –<br />

5 60.0 50.3 69.2 –<br />

3. Faridabad 1 55 31.4 33.6 60<br />

2 55 39.8 53.7 60<br />

3 55 23.0 62.8 60<br />

4. Bhatinda 2 110 53.0 66.0 –<br />

3 110 45.7 55.5 –<br />

5. Obra 2 40 57.1 60.6 50<br />

6 94 40.3 41.3 100<br />

8 94 45.9 54.8 100<br />

9 200 33.3 56.1 –<br />

10 200 31.4 65.8 –<br />

6


1 2 3 4 5 6 7<br />

11 200 28.4 64.3 –<br />

12 200 40.2 49.9 –<br />

13 200 35.1 56.4 –<br />

6. Amarkantak 3 120 39.2 54.2 –<br />

7. Satpura 1 62.5 51.5 53.6 –<br />

8. Gandhinagar 1 120 50.1 63.9 –<br />

2 120 48.2 62.5 –<br />

9. Dhuvaran 1 63.5 73.6 75.4 –<br />

3 63.5 71.7 72.2 –<br />

6 140 64.7 76.3 –<br />

10. Ukai 1 120 47.0 53.5 –<br />

2 120 38.7 55.8 –<br />

11. Koradi 1 115 65.9 74.6 120<br />

4 115 40.6 74.0 120<br />

12. Nasik 1 140 55.9 56.6 –<br />

2 140 51.9 56.7 –<br />

13. Paras 2 58 58.7 69.5 62.5<br />

14. Kothagudam 2 60 57.8 78.2 –<br />

3 60 53.8 62.4 –<br />

5 105 28.9 56.8 110<br />

6 105 24.3 50.2 110<br />

7 110 17.3 36.4 –<br />

15. Ennore 1 60 51.0 72.0 –<br />

2 60 48.1 76.5 –<br />

3 110 33.8 47.8 –<br />

4 110 25.2 60.5 –<br />

16. Tuticorin 1 210 46.0 69.8 –<br />

2 210 47.0 48.5 –<br />

3 210 40.4 78.5 –<br />

17. Neyveli 2 50 67.0 83.0 –<br />

3 50 71.1 81.3 –<br />

6 50 78.3 80.0 –<br />

7 100 70.6 76.1 –<br />

8 100 63.2 65.8 –<br />

9 95 69.8 87.1 100<br />

18. Durgapur (DVC) 3 140 39.4 39.7 –<br />

19. Talcher 1 60 35.1 40.2 62.5<br />

20. Patratu 1 40 41.0 42.0 50<br />

2 40 31.5 35.6 50<br />

21. Santaldih 3 120 26.7 44.3 –<br />

22. Bandel 2 80 33.8 44.3 –<br />

23. DPL 3 70 0.0 24.2 –<br />

7


2.8 GENERATING<br />

CAPACITY ADDITION<br />

2.9 PROGRAMME, ANTICIPATED<br />

ACHIVEMENT AND SLIPPAGE<br />

DURING/FROM <strong>1991</strong>-<strong>92</strong>:<br />

In all 61 major, medium and small units with<br />

aggregate capacity <strong>of</strong> 3810.8 MW are programmed<br />

8<br />

for commissioning during the year <strong>1991</strong>-<strong>92</strong>. This<br />

capacity comprises 35 hydel, 24 thermal and 2<br />

nuclear units with capacity aggregating to 754.3,<br />

2586.5 and 470 MW respectively. In view <strong>of</strong> the<br />

present status <strong>of</strong> the execution <strong>of</strong> the programme<br />

8 hydel and 4 thermal units aggregating to 245.3<br />

MW capacity are anticipated to slip from <strong>1991</strong>-<strong>92</strong>.


Table-II<br />

(All figures in MW)<br />

Capacity Details <strong>of</strong> Central State Private Total<br />

Type item Sector Sector Sector<br />

Hydel i) Prog. 120 634.3 – 754.3<br />

ii) Ant. Ach. 120 475.0 – 595.0<br />

iii) Slippage – 159.3 – 159.3<br />

Thermal i) Prog. 998 1455 133.5 2586.5<br />

ii) Ant. Ach. 998 1369 133.5 2500.5<br />

iii) Slippage – 86 – 86<br />

Nuclear i) Prog. 470 – – 470<br />

ii) Ant. Ach. 470 – – 470<br />

iii) Slippage – – – –<br />

Total i) Prog. 1588 2089.3 133.5 3810.5<br />

ii) Ant. Ach. 1588 1844 133.5 3565.5<br />

iii) Slippage – 245.3 – 245.3<br />

Pogramme & Achievement during April, <strong>1991</strong> to December <strong>1991</strong>.<br />

The sectoral break up <strong>of</strong> the programme and achievement<br />

during <strong>1991</strong>-<strong>92</strong> by type <strong>of</strong> generation is as under:-<br />

Programme during <strong>1991</strong>-<strong>92</strong><br />

Figures in MW<br />

Achievement during <strong>1991</strong>-<strong>92</strong> (Upto 12/91)<br />

Central State Total All Central State Total All<br />

sector sector India sector sector India<br />

Hydro 120 634.3 754.3 – 91.5 91.5<br />

Thermal 998 1588.5 2586.5 420 343.5 763.5<br />

Nuclear 470 – 470 235 – 235.0<br />

Total 1588 2222.8 3810.8 655 435.0 1090<br />

Table III and Table IV give details <strong>of</strong> the capacity addition programme for 91-<strong>92</strong> and the achievement during<br />

April-December <strong>1991</strong>.<br />

9


ELECTRIC POWER GENERATION CAPACITY ADDITION PROGRAMME<br />

FOR THE YEAR <strong>1991</strong>-<strong>92</strong><br />

Sl. Name <strong>of</strong> the Project H/T/N State Capacity Expected date<br />

No. and Unit No.<br />

NORTHERN REGION<br />

Organisation (MW) <strong>of</strong> commissioning<br />

1. Upper Sindh-II-1 H J&K 35 11/91<br />

2. Upper Sindh-II-2 H J&K 35 12/91<br />

3. Pampore GT St. II-1 T J&K/PDC 25 2/<strong>92</strong><br />

4. Pampore GT St. II-2 T J&K/PDC 25 3/<strong>92</strong><br />

5. UBDC-II-2 H Punjab 15 6/91<br />

6. UBDC-II-3 H Punjab 15 8/91<br />

7. Ropar-5 T Punjab 210 2/<strong>92</strong><br />

8. Mangrol-I H Rajasthan 2 6/91<br />

9. Mangrol-2 H Rajasthan 2 7/91<br />

10. Mangrol-3 H Rajasthan 2 8/91<br />

11. Ramgarh GT T Rajasthan 3 12/91<br />

12. Tanakpur-1 H UP/NHPC 40 1/<strong>92</strong><br />

13. Tanakpur-2 H UP/NHPC 40 2/<strong>92</strong><br />

14. Tanakpur-3 H UP/NHPC 40 2/<strong>92</strong><br />

15. Khara-1 H UP 24 10/91<br />

16. Khara-2 H UP 24 11/91<br />

17. Khara-3 H UP 24 12/91<br />

18. National Capital TPP-1 T UP/NTPC 210 8/91<br />

19. CCGT Project at Dadri GT-1 T UP/NTPC 131 11/91<br />

20. CCGT Project at Dadri GT-2 T UP/NTPC 121 1/91<br />

21. Tanda-4 T UP 110 9/91<br />

22. Narora-2 N UP/NPCL 235 7/91<br />

CENTRAL STATE TOTAL<br />

HYDRO 120 178 298<br />

THERMAL 472 373 845<br />

NUCLEAR 235 – 235<br />

TOTAL (NR) 827 551 1378<br />

WESTERN REGION<br />

23. Kawas CCGT GT-1 T Guj/NTPC 106 3/<strong>92</strong><br />

24. Gandhinagar-4 T Gujarat 210 10/91<br />

25. Vatwa CCGT-2 T Gujarat 33 7/91<br />

26. Vatwa CCGT ST-1 T Gujarat 33 10/91<br />

27. Utran CCGT GT-1 T Gujarat 33 9/91<br />

28. Utran CCGT GT-2 T Gujarat 33 11/91<br />

29. Utran CCGT GT-3 T Gujarat 33 1/<strong>92</strong><br />

30. Bansagar Tons-3 H MP 105 9/91<br />

31. Birsinghpur-1 H MP 20 8/91<br />

32. Chandrapur-6 T Maharashtra 500 2/<strong>92</strong><br />

33. Kakrapara-1 N Guj/NPCL 235 12/91<br />

10<br />

Table-III


Sl. Name <strong>of</strong> the Project H/T/N State Capacity Expected date<br />

No. and Unit No. Organisation (MW) <strong>of</strong> commissioning<br />

CENTRAL STATE TOTAL<br />

HYDRO – 125 125<br />

THERMAL 106 875 981<br />

NUCLEAR 235 – 235<br />

TOTAL (WR) 341 1000 1341<br />

34.<br />

SOUTHERN REGION<br />

Penna Ahobilam-1 H AP 10 12/91<br />

35. Penna Ahobilam-2 H AP 10 1/<strong>92</strong><br />

36. Nagarjunasagar LBC-1 H AP 30 9/91<br />

37. Nagarjunasagar LBC-2 H AP 30 11/91<br />

38. Vijjeswaram ST-1 T AP/APGPCL 33 12/91<br />

39. Ghatprabha-1 H Karnataka 16 1/<strong>92</strong><br />

40. Ghatprabha-2 H Karnataka 16 2/<strong>92</strong><br />

41. Kallada-1 H Kerala 7.5 12/91<br />

42. Kallada-2 H Kerala 7.5 1/<strong>92</strong><br />

43. Neyveli 2nd Mine cut-5 T TN/NLC 210 12/91<br />

44. Tuticorin-4 T Tamil Nadu 210 12/91<br />

45. Narimanam GT-1 T Tamil Nadu 5 7/91<br />

46. Narimanam GT-2 T Tamil Nadu 5 9/91<br />

CENTRAL STATE TOTAL<br />

HYDRO – 127 127<br />

THERMAL 210 253 463<br />

NUCLEAR - – –<br />

TOTAL (SR) 210 380 590<br />

47.<br />

EASTERN REGION<br />

Sone Western Canal-1 H Bihar 1.65 1/<strong>92</strong><br />

48. Sone Western Canal-2 H Bihar 1.65 2/<strong>92</strong><br />

49. Kahalgaon-1 T Bihar/NTPC 210 2/<strong>92</strong><br />

50. Rengali-3 H Orissa 50 2/<strong>92</strong><br />

51. Upper Kolab-4 H Orissa 80 2/<strong>92</strong><br />

52. CESC Replacement T WB 67.5 4/91<br />

53. Myangchu-1 H Sikkim 2 1/<strong>92</strong><br />

54. Myangchu-2 H Sikkim 2 2/<strong>92</strong><br />

55. Upper Rongnichu-1 H Sikkim 2 1/<strong>92</strong><br />

56. Upper Rongnichu-2 H Sikkim 2 2/<strong>92</strong><br />

CENTRAL STATE TOTAL<br />

HYDRO – 141.3 141.3<br />

THERMAL 210 67.5 277.5<br />

NUCLEAR – – –<br />

TOTAL (ER) 210 208.8 418.8<br />

11


Sl. Name <strong>of</strong> the Project H/T/N State Capacity Expected date<br />

No. and Unit No.<br />

NORTH-EASTERN REGION<br />

Organisation (MW) <strong>of</strong> commissioning<br />

57. Tago-2 H Ar. Pradesh 1.5 7/91<br />

58. Tago-3 H Ar. Pradesh 1.5 9/91<br />

59. Lakwa GT PH-II-5 T Assam 20 3/<strong>92</strong><br />

60. Umiam Umtru IV-2 H Meghalaya 30 1/<strong>92</strong><br />

61. Umiam Umtru IV-1 H Meghalaya 30 2/<strong>92</strong><br />

CENTRAL STATE TOTAL<br />

HYDRO – 63 63<br />

THERMAL – 20 20<br />

NUCLEAR – – –<br />

TOTAL (NER) – 83 83<br />

CENTRAL STATE TOTAL<br />

HYDRO 120 634.3 754.3<br />

THERMAL 998 1588.5 2586.5<br />

NUCLEAR 470 – 470<br />

ALL INDIA 1588 2222.8 3810.8<br />

Note : The programme excludes mini/micro hydel capacity.<br />

12<br />

A dusk view <strong>of</strong> Singrauli


CAPACITY ADDITION DURING APRIL-DECEMBER <strong>1991</strong><br />

Table-IV<br />

Sl. Name <strong>of</strong> the Unit Capacity State/ Remarks<br />

No. Project<br />

HYDRO<br />

No. (MW) Executing<br />

Agency<br />

1. UBDC-II 2 15 Punjab/PSEB Rolled on 10.6.91<br />

2. UBDC-II 3 15 Punjab/PSEB Rolled on 12.12.91<br />

3. Suratgarh 1* 2 Raj/RSEB Rolled on 28.6.91<br />

4. Suratgarh 2* 2 Raj/RSEB Rolled on 28.6.91<br />

5. Mangrol 1 2 Raj/RSEB Rolled on 25.7.91<br />

6. Mangrol 2 2 Raj/RSEB Rolled on 23.7.91<br />

7. Mangrol 3 2 Raj/RSEB Rolled on 27.7.91<br />

8. Birsinghpur 1 20 MP/MPEB Rolled on 14.8.91<br />

9. Nil Sagar LBC 1 30 AP/APSEB Rolled on 11.9.91<br />

10. Tago 2 1.5 Ar. Pradesh Commissioned on 7.8.91<br />

TOTAL (H)<br />

THERMAL<br />

91.5<br />

1. National<br />

Capital TPP<br />

1 210 UP/NTPC Commissioned on 24.10.91<br />

2. Vetwa CCGT 2 33 Guj/AE Co. Commissioned on 26.6.91<br />

3. Vetwa CCGT St. 1 33 Guj/GEB Commissioned on 18.10.91<br />

4. Gandhinagar 4 210 Guj/GEB Commisioned on 20.7.91<br />

5. CESC Rept. 2 67.5 WB/CESC Commissioned on 10.4.91<br />

6. Neyveli M. Cut 5 210 TN/NLC Commissioned on 30.12.91<br />

TOTAL (T)<br />

NUCLEAR<br />

763.5<br />

1. Narora 2 235 UP/DAE Critical on 24.10.<strong>1991</strong><br />

Total (N) 235<br />

Total (H+T+N) 1090<br />

*Outside the Programme for <strong>1991</strong>-<strong>92</strong><br />

2.10 TRANSMISSION<br />

Transmission line projects continue to be accorded<br />

high priority in the context <strong>of</strong> the need to evacuate<br />

<strong>power</strong> from the Central Generating Stations to the<br />

beneficiary states. The programmes for <strong>1991</strong>-<strong>92</strong><br />

included construction <strong>of</strong> 2878 Ckt. Km. <strong>of</strong> 400 KV<br />

lines and 3252 Ckt. km. <strong>of</strong> 220 KV lines alongwith<br />

the associated sub-stations.<br />

13<br />

The progress achieved during the year <strong>1991</strong>-<strong>92</strong><br />

(upto December, 91) in the construction <strong>of</strong><br />

transmission lines and sub-stations is summarised<br />

below :-<br />

400 KV 1614 Ckt. km.<br />

220 KV 2266 Ckt. km.<br />

400 Kv Sub-station 2520 KVA<br />

220 KV Sub-station 2150 KVA


2.11 CENTRAL SECTOR<br />

TRANSMISSION SYSTEMS<br />

Central Sector Transmission lines and sub-stations<br />

completed during the year <strong>1991</strong>-<strong>92</strong> (upto December, 91)<br />

are listed in the following table :<br />

Transmission Lines Executing Length Total<br />

400 KV<br />

Agency Ckt.km.<br />

1. Gooty-Banglore S/C NPTC 382<br />

2. Vijaywada-Gazuwaka S/C NPTC 332<br />

3. Maithen-Jamshedpur D/C NPTC 306<br />

4. Agra-Ballabgrah S/C NPTC 182<br />

5. Ramagundam-Khammam S/C NPTC<br />

220 KV<br />

189 1311<br />

1. LILO <strong>of</strong> Ukai-Valtaan lines<br />

at Kakarpara APP D/C<br />

NPC 8<br />

2. Parulia-DSP 3 Ckts. DVC 45 53<br />

Sub-stations<br />

400 KVA<br />

Executing<br />

Agency<br />

KVA Total<br />

1. Gooty NPTC 315<br />

2. Vijayawada NPTC 315<br />

3. Gazuwaka NPTC 315<br />

4. Biharshariff NPTC 315<br />

5. Mandaula NPTC 630 1890<br />

The National <strong>Power</strong> Transmission Corporation (NPTC) is<br />

now executing the transmission projects associated with<br />

the generation projects <strong>of</strong> NTPC, NHPC and NEEPCO.<br />

An HVDC back-to-back link between Vindhyachal and<br />

Singrauli Super Thermal <strong>Power</strong> Stations as well as the<br />

first ±500 KV HVDC bi-pole line from Rihand to Dadri<br />

have already been put into operation by NTPC. The<br />

schemes for providing a 1000 MW HVDC back-to-back<br />

tie between Chandrapur (in Western Region) and<br />

Ramagundam (in Southern Region) has been accorded<br />

approval <strong>of</strong> the PIB, and preliminary work has been taken<br />

up. Besides this, a scheme for providing a 500 MW<br />

HVDC back-to-back tie between Jeypore (in Eastern<br />

Region) and Gazuwaka (in Southern Region) is under<br />

process for investment approval. Both these projects will<br />

be taken up for execution by NPTC.<br />

To facilitate the exchange <strong>of</strong> <strong>power</strong> between the States<br />

and Regions, Inter-state and Inter-regional transmission<br />

lines are being constructed under a Centrally sponsored<br />

Scheme which are introduced in 1969.<br />

14<br />

CAPACITY ADDITIONS PROGRAMME &<br />

ACHIEVEMENTS DURING <strong>1991</strong>-<strong>92</strong><br />

LEGEND<br />

PROGRAMME<br />

COMMISSIONED<br />

During the year <strong>1991</strong>-<strong>92</strong> (upto December, 91) the 400 KV<br />

Kolaghat - Rengali inter-state link was completed.<br />

2.12 TRANSMISSION & DISTRIBUTION<br />

LOSSES<br />

The average All-India transmission & distribution losses<br />

for the year 1990-91 have been estimated at about 22.90%<br />

(provisional).<br />

The Government <strong>of</strong> India have launched a scheme for<br />

incentive payments for the reduction <strong>of</strong> transmission and<br />

distribution (T&D) losses. Under the schemes, the SEBs/<br />

Elecy. Deptts. and their Distribution Divisions which<br />

achieve a prescribed minimum reduction in T&D losses<br />

are given awards. In addition, they are given shields on<br />

the basis <strong>of</strong> their performance in reduction in energy<br />

losses and Chairmen/Heads <strong>of</strong> the concerned Elecy.<br />

Boards/Deptts. are given Gold Medals. Individuals as well<br />

as institutions or organisations, who develop scientific<br />

devices or put forward practical suggestions for reduction<br />

<strong>of</strong> T&D losses also qualify for cash awards.<br />

During the year <strong>1991</strong>-<strong>92</strong> Gold Medals and Shields for the<br />

year 1989-90 were awarded to State Elecy. Board/Elecy.<br />

Deptt. <strong>of</strong> Karnataka and Chandigarh. In addition, cash<br />

awards were given to Chandigarh, Indore distribution<br />

division <strong>of</strong> MPEB and 13 distribution divisions <strong>of</strong> Gujarat<br />

Elecy. Board. Also Shields were awarded to Valsad City<br />

distribution division <strong>of</strong> GEB and Indore distribution<br />

division <strong>of</strong> MPEB.<br />

2.13 INTERGRATED OPERATION<br />

The Regional <strong>Power</strong> Grids in the Northern, Western,<br />

Southern and Eastern Regions facilitate flow <strong>of</strong> <strong>power</strong><br />

from surplus areas to deficit areas and assist in the<br />

optimum utilisation <strong>of</strong> the <strong>power</strong> available in the country.


The Inter-State/Inter-Regional Assistance <strong>of</strong> Energy<br />

effected during the period April, <strong>1991</strong> to December, <strong>1991</strong><br />

are listed below :<br />

INTER-STATE/INTER-REGIONAL<br />

ASSISTANCE OF ENERGY<br />

STATE Assistance<br />

(All Figures in MU)<br />

ASSISTANCE<br />

from Dec.<strong>1991</strong> Apr.91-<br />

Dec.91<br />

Northern Region<br />

CHANDIGARH Punjab 0.0 0.0<br />

H.P. 0.0 0.0<br />

S.S.T.P.S. 7.9 68.2<br />

DELHI B.B.M.B. 0.3 23.1<br />

Punjab 0.0 36.2<br />

H.P. 0.0 356.5<br />

HARYANA H.P. 0.0 42.8<br />

H.P. Punjab 1.2 45.0<br />

U.P. 19.7 <strong>92</strong>.9<br />

S.S.T.P.S. 10.8 20.4<br />

J&K S.S.T.P.S. 35.4 214.1<br />

B.B.M.B. 3.1 7.1<br />

PUNJAB H.P. 0.0 0.0<br />

RAJASTHAN H.P. 0.0 41.4<br />

Punjab 48.4 217.3<br />

M.P. 8.7 47.1<br />

U.P. B.B.M.B. 14.3 77.6<br />

H.P. 0.0 2.4<br />

S.S.T.P.S. Vindhyachal STPS 27.7 211.6<br />

B.B.M.B. S.S.T.P.S. 0.0 49.6<br />

Rihand 0.0 24.1<br />

Western Region<br />

Gujarat Maharashtra 87.6 698.6<br />

N.R. 4.5 95.2<br />

S.R. 0.0 20.7<br />

M.P. Rajasthan 0.0 62.5<br />

A.P. 4.9 43.3<br />

N.R. 32.6 323.8<br />

S.R. 0.0 27.2<br />

Maharashtra<br />

Gujarat 0.3 55.0<br />

Karnataka 0.0 0.0<br />

N.R. 0.0 10.2<br />

S.R. 0.0 8.1<br />

15<br />

Goa<br />

Daman DIU &<br />

Dadar Nagar<br />

Maharashtra 17.0 143.2<br />

Haveli<br />

Southern Region<br />

Gujarat 23.8 177.4<br />

A.P. Karnataka 0.0 1.4<br />

Maharashtra 0.0 142.1<br />

M.P. 4.3 29.0<br />

Orissa 0.0 24.1<br />

Karnataka A.P. 0.0 0.0<br />

Kerala 0.0 0.0<br />

T.N. 0.0 0.0<br />

Maharashtra 0.0 0.4<br />

Kerala Karnataka 0.0 0.0<br />

TN 0.0 10.05<br />

Tamil Nadu<br />

Eastern Region<br />

Kerala 0.0 0.0<br />

Bihar West Bengal 0.0 0.0<br />

Orissa 0.0 0.0<br />

NTPC (SSTPS) 0.0 2.2<br />

NTPC (ANTA) 20.7 254.5<br />

NTPC (AURAIYA) 43.2 435.7<br />

D.V.C. Bihar 0.0 0.0<br />

Orissa 0.0 0.0<br />

West Bengal 0.0 0.0<br />

Orissa Bihar 0.0 0.0<br />

West Bengal 0.0 0.0<br />

NALCO 66.9 327.0<br />

ICCL 49.8 109.5<br />

R.S.P. 0.0 1.2<br />

A.P. 0.0 0.0<br />

M.P. 0.0 24.9<br />

West Bengal Orissa 0.0 0.0<br />

Bihar 0.0 0.0<br />

N.E. Region<br />

NER (Assam) 6.2 21.9<br />

Assam Eastern Region 11.0 30.7<br />

2.14 DEVELOPMENT OF A NATIONAL<br />

POWER GRID<br />

The setting up <strong>of</strong> a National <strong>Power</strong> Grid is an evolutionary<br />

Process. To achieve this objective, the strengthening and<br />

the improvement <strong>of</strong> the Regional <strong>Power</strong> Grids and their<br />

progressive integration through the setting up <strong>of</strong> inter-<br />

State transmission lines and Central Sector transmission<br />

projects which cut across State boundaries was continued


during the year. These projects, alongwith the 400 KV<br />

and 220 KV transmission systems being constructed in the<br />

Central sector are expected to constitute the basic<br />

structure <strong>of</strong> the National <strong>Power</strong> Grid. In order to<br />

accelerate the process <strong>of</strong> the formation <strong>of</strong> the Grid, the<br />

National <strong>Power</strong> Transmission Corporation set up under<br />

Department <strong>of</strong> <strong>Power</strong> in October, 1989 has started taking<br />

over the construction, ownership, operation and<br />

maintenance <strong>of</strong> the works relating to transmission and<br />

associated sub-stations from various Central <strong>power</strong><br />

generating public undertakings in a phased manner to<br />

ensure a better integrated grid-operation and delivery <strong>of</strong><br />

<strong>power</strong> from the central generating stations to the<br />

respective beneficiary States.<br />

2.15 REGIONAL ELECTRICITY BOARDS AND<br />

REGIONAL LOAD DESSPATCH CENTRES.<br />

In order to promote the integrated operation <strong>of</strong> the <strong>power</strong><br />

systems, the country has been divided into five regions<br />

namely North, West, South, East and North-East.<br />

Regional Electricity Boards have been set up in each <strong>of</strong><br />

these regions.<br />

16<br />

To coordinate the operations <strong>of</strong> the grids <strong>of</strong> the constituent<br />

<strong>power</strong> systems and to optimise utilisation <strong>of</strong> the existing<br />

generation capacity, Regional Load Despatch Centres<br />

have been set up in each region which function under the<br />

respective Regional Electricity Boards. The Central<br />

Electricity Authority exercises overall supervisions over<br />

the Regional Load Despatch Centres (RLDCs).<br />

In the Northern, Western and Eastern regions, permanent<br />

Regional Load Despatch Centres equipped with computer<br />

based telemetry and data acquisition systems have already<br />

been established. The existing facilities in the Southern<br />

Region are proposed to be modernised based on the study<br />

and recommendations made by the Consultant M/s EdF,<br />

International. The consultants have submitted a detailed<br />

project <strong>report</strong> and technical specifications to modernise<br />

Southern Regional Load Despatch Centre. A scheme<br />

based on the above Project Report is being processed for<br />

techno-economic clearance <strong>of</strong> Central Electricity<br />

Authority. In the North-Eastern Region, an interim load<br />

despatch centre is operating. A proposal to set up a<br />

permanent RLDC with modern facilities in the North-<br />

Eastern Region is already


In an advanced stage and is expected to be<br />

implemented during the VIII Plan. It is proposed to<br />

take up a similar unified scheme for the establishment<br />

<strong>of</strong> long term RLDC and augmentation <strong>of</strong> existing<br />

system in the Northern Region.<br />

2.16 MASTER TELECOM PLAN<br />

FOR INDIAN POWER SECTOR<br />

The work <strong>of</strong> preparing a Master Telecom Plan for<br />

Indian <strong>Power</strong> Sector covering all <strong>power</strong> utilities, and<br />

Regional Electricity Boards, was awarded to M/s.<br />

Merz & Maclellan, U.K. in association with M/s.<br />

Bharat Electronics Limited, India in November, 1987.<br />

The <strong>report</strong> <strong>of</strong> the consultants has been made available<br />

to CEA in three phases and the same has been sent to<br />

concerned utilities to initiate the process <strong>of</strong><br />

VILLAGES ELECTRIFIED AS ON<br />

30-11-91<br />

(AS PER 1981 CENSUS)<br />

17<br />

implementation. The project <strong>report</strong>s for the<br />

independent dedicated telecom system for the State<br />

Electricity Boards <strong>of</strong> Punjab (Phase I), Kerala, Gujarat,<br />

Madhya Pradesh, Maharashtra (Phase I and Phase II),<br />

Orissa, Uttar Pradesh, Himachal Pradesh and North-<br />

Eastern Region have already been appraised by CEA.<br />

Department <strong>of</strong> Telecommunications (DOT) has been<br />

requested by CEA on behalf <strong>of</strong> the <strong>power</strong> utilities to<br />

accord their clearance for the dedicated multi-channel<br />

links by the <strong>power</strong> utilities. They have already<br />

approved the multi-channel links (Optical Fibre/<br />

Digital Microwave) for Punjab State Electricity Board,<br />

Gujarat Electricity Board & North-Eastern Region.<br />

Towards implementation <strong>of</strong> the schemes, <strong>Power</strong><br />

utilities have already started undertaking Radio/Site<br />

surveys.


2.17 UPGRADING OF TECHNOLOGY<br />

2.18 NEXT HIGHER AC<br />

TRANSMISSION VOLTAGE<br />

The adoption <strong>of</strong> 800 KV class as the next higher AC<br />

transmission voltage in the country had been accepted<br />

by the Govt. <strong>of</strong> India in October, 1988. The decision<br />

had been conveyed to all State Electricity Boards/<br />

<strong>Power</strong> Utilities etc. With a view to bring uniformity in<br />

the development <strong>of</strong> future 800 KV systems in the<br />

country, the Standing EHV Committee had constituted<br />

10 Working Groups with representatives from<br />

Electricity Boards/Undertakings, CPRI, Industry and<br />

CEA to take up the work <strong>of</strong> standardisation <strong>of</strong> 800 KV<br />

class equipment/transmission line material. Based on<br />

the studies carried out by the Working Group and<br />

detailed discussions held by them, a <strong>report</strong> on<br />

Standard Parameters <strong>of</strong> 800 KV transmission system<br />

in India had been brought out by CEA in September,<br />

1990. This <strong>report</strong> has been circulated to all the<br />

Electricity Boards and <strong>Power</strong> Utilities etc. for their<br />

guidance and adoption <strong>of</strong> recommended parameters.<br />

2.19 NATIONAL HVDC PROJECT<br />

Under the National HVDC project, one circuit <strong>of</strong> the<br />

existing D/C 220 kv AC line between Lower Sileru<br />

(A.P.) and Bearoor (M.P.) is being taken up for<br />

18<br />

conversion from AC to DC link. The project is being<br />

implemented in two phases. The first phase envisaged<br />

the conversion <strong>of</strong> one circuit to 100 KV, 100 MW DC<br />

link. In the second phase, this link is to be uprated to<br />

200 KV, 200 MW. The first phase has been completed<br />

and there is continuous flow <strong>of</strong> 100 MW <strong>power</strong> on this<br />

link since 20th October, <strong>1991</strong>. The second phase has<br />

already been approved by the HVDC Hardware<br />

Development Committee and the revised cost<br />

estimates <strong>of</strong> the same are under finalisation.<br />

Rihand-Delhi HVDC Transmission line 500 KV 1500<br />

MW Bipole: This HVDC Bipole transmission project<br />

envisages transmission <strong>of</strong> 1500 MW <strong>of</strong> <strong>power</strong> from<br />

Rihand complex to Dadri (near Delhi) over a distance<br />

<strong>of</strong> about 820 kms. The project is being executed by<br />

M/s BHEL in collaboration with M/s ASRA, Sweden.<br />

The complete equipment for the first pole has been<br />

supplied by M/s. ABB, Sweden and for second pole,<br />

the equipment has been jointly supplied by M/s ABB<br />

& BHEL.<br />

One pole <strong>of</strong> the Rihand-Delhi HVDC transmission<br />

system was commissioned in December, 1990 and is<br />

now under commercial operation. The restoration<br />

work on the other pole damaged in a fire incident, was<br />

completed and the pole has been in operation since<br />

December, <strong>1991</strong>.


2.20 POWER & TELECOMMUNI-<br />

CATION CO-ORDINATION<br />

(PTCC)<br />

During the year <strong>1991</strong>-<strong>92</strong>, CEA have recommended 74<br />

cases to DOT for issue <strong>of</strong> necessary clearance by them so<br />

that the transmission lines could be energised. CEA<br />

engineers were associated in the Low Frequency<br />

Induction tests carried out on Gooty-Banglaroe and<br />

Talaguppa-Shimaga 400 KV transmission lines. CEA<br />

have also provided consultancy services to Bihar State<br />

Electricity Board in processing on computer PTCC cases.<br />

During the year three meetings were organised at Delhi,<br />

Bangalore & Patna for sorting out outstanding issues<br />

related to PTCC clearance. These meetings were attended<br />

by higher level <strong>of</strong>ficers from CEA, DOT and SEBs/<strong>Power</strong><br />

Utilities.<br />

2.21 RURAL ELECTRIFICATION<br />

PROGRAMME<br />

During the year <strong>1991</strong>-<strong>92</strong>, 2022 inhabited villages were<br />

declared as electrified and 194482 pumpsets energised as<br />

on 30.11.<strong>1991</strong>, against the target <strong>of</strong> 5787 villages<br />

electrification and 234530 pumpsets energisation<br />

respectively, for the year as a whole. Cumulatively,<br />

483146 villages have been electrified and 91035<strong>92</strong><br />

pumpsets have been energised as on 30.11.<strong>1991</strong>.<br />

Cumulative progress <strong>of</strong> rural electrification both in terms<br />

<strong>of</strong> villages electrified and pumpsets energised as at the<br />

end <strong>of</strong> Five Year/Annual Plan is reflected in the charts at<br />

pages 18 & 19.<br />

As regards to the electrification <strong>of</strong> tribal villages, out <strong>of</strong> a<br />

total <strong>of</strong> 111886 tribal villages in the country, 73532<br />

villages constituting 65.7% have been electrified as on<br />

30.11.<strong>1991</strong>. Similarly, 245583 Harijan Bastis have been<br />

electrified.<br />

2.22 SEVENTH FIVE YEAR PALN<br />

The salient features <strong>of</strong> the approved <strong>power</strong> programme<br />

during the Seventh Plan (1985-90) were:<br />

a. Induction <strong>of</strong> an additional generating capacity <strong>of</strong><br />

22,245 MW as follows:-<br />

Thermal 15,999 MW<br />

Hydro 5,541 MW<br />

Nuclear 705 MW<br />

22,245 MW<br />

b. Construction <strong>of</strong> associated transmission and<br />

distribution facilities corresponding to the addition <strong>of</strong><br />

22,245 MW generating capacity.<br />

19<br />

c. Electrification <strong>of</strong> 1.18 lakh villages and energisation<br />

<strong>of</strong> 23.9 lakhs pump-sets.<br />

d. Implementation <strong>of</strong> programmes <strong>of</strong> renovation and<br />

modernisation, research and development, energy<br />

conservation etc.<br />

The achievement <strong>of</strong> the Seventh plan <strong>power</strong> programme<br />

has been impressive. An additional generating capacity <strong>of</strong><br />

21,401 MW comprising 17,104 MW <strong>of</strong> thermal, 3827<br />

MW <strong>of</strong> hydro and 470 MW nuclear, has been installed,<br />

achievement being 96.2% <strong>of</strong> the target <strong>of</strong> the Seventh<br />

Plan. A 250 MW back-to-back HVDC line has been<br />

established at Vindhyachal. About 13,800 Ckt. Kms <strong>of</strong><br />

400 KV and 13600 Ckt Kms <strong>of</strong> 220 KV lines have been<br />

added to the transmission and distribution network in the<br />

country. Electrification <strong>of</strong> 100494 villages and<br />

energisation <strong>of</strong> 26.41 lakhs <strong>of</strong> pumpsets was completed in<br />

the Seventh Plan.<br />

A total allocation <strong>of</strong> Rs. 34273.<strong>92</strong> crores was made in the<br />

seventh plan for the <strong>power</strong> sector against which the<br />

expenditure was Rs. 37404.19 crores (tentative), the<br />

details <strong>of</strong> which are given below :-<br />

(Rs. in crores)<br />

Approved outlay Actual Expenditure<br />

(Anticipated)<br />

States 22784.18 20757.04<br />

UTs 437.74 <strong>92</strong>9.15<br />

Centre 11052.00 15718.00*<br />

34273.<strong>92</strong> 37404.19<br />

(This includes Rs. 430.00 crores for PFC also)<br />

2.23 PROGRAMME FOR ADDITIONS<br />

TO GENERATING CAPACITY<br />

DURING 1990-91:<br />

A target <strong>of</strong> 4212 MW was fixed for addition <strong>of</strong> installed<br />

generating capacity during the year 1990-91. The details<br />

are given below :<br />

(All Figures in MW)<br />

Type Central State Total<br />

Sector Sector All India<br />

Hydro – 1006.5 1006.5<br />

Thermal 732 2238.5 2970.5<br />

Nuclear 235 – 235.0<br />

Total: 967 3245.0 4212.0


Achievement during 1990-91:<br />

Against the programme <strong>of</strong> 4212 MW a capacity <strong>of</strong> 2776.5<br />

MW was commissioned/rolled during the year 1990-91.<br />

The details are given below :<br />

Type Central Sector State Sector Total<br />

Hydro – 445.5 445.5<br />

Thermal 732 1599 2331<br />

Nuclear – – –<br />

Total : 732 2044.5 2776.5<br />

2.24 FOURTEENTH ELECTRIC<br />

POWER SURVEY COMMITTEE<br />

The Fourteenth <strong>Power</strong> Survey Committee was set up in<br />

February, 1989, under the chairmanship <strong>of</strong> Chairman,<br />

CEA to review demand projections in details keeping in<br />

view the Eighth Plan proposals and to project the<br />

perspective demand in the country upto 2009-10. The<br />

committee submitted its <strong>report</strong> in March <strong>1991</strong>.<br />

2.25 INDO-SOVIET WORKING GROUP<br />

ON POWER<br />

The Fourteenth meeting <strong>of</strong> the Indo-Soviet Working<br />

Group on <strong>Power</strong> was held in New Delhi from April 1-5,<br />

<strong>1991</strong>. The Soviet side was led by Mr. A.P. Poddubsky,<br />

Deputy Minister for <strong>Power</strong> & Electrification, USSR, and<br />

the Indian side was led by Shri S. Rajgopal, Secretary,<br />

Department <strong>of</strong> <strong>Power</strong>.<br />

The Working Group reviewed the progress <strong>of</strong> the Soviet<br />

assisted thermal <strong>power</strong> projects in India viz.,<br />

Vindhyachal, Kahalgaon, Kayamkulam, Maithon Right<br />

Bank, Mangalore, Bakreswar and hydro projects viz.,<br />

Tehri and Kol Dam. The Working Group also reviewed<br />

the progress <strong>of</strong> transmission lines such as Dulhasti-<br />

Kishenpur-Srinagar, Vindhayachal-Bina-Nagda and<br />

Vindhyacahl-Jabalpur-Itarsi. Both the sides identified<br />

measures to remove the bottle-necks and difficulties,<br />

which are encountered in project implementation, within<br />

the stipulated time schedules.<br />

The other areas in the field <strong>of</strong> Indo-Soviet co-operation<br />

considered by the Working Group included maintenance,<br />

repair and modernisation <strong>of</strong> the Soviet made equipement<br />

installed at <strong>power</strong> stations in India, scientific and technical<br />

co-operation, training programmes, supply <strong>of</strong> BHEL<br />

equipment/services to Soviet assited projects in India/third<br />

countries, consultancy in tidal <strong>power</strong> development and<br />

energy management.<br />

20<br />

2.26 PARTICIPATION IN<br />

PROJECTS OUTSIDE INDIA<br />

CHUKHA HYDEL PROJECT, BHUTAN<br />

From the Chukha Hydel Project, the Royal Government <strong>of</strong><br />

Bhutan earned a revenue <strong>of</strong> over Rs. 160 crores by<br />

December, <strong>1991</strong> by way <strong>of</strong> sale <strong>of</strong> <strong>power</strong> to India, besides<br />

supplying <strong>power</strong> for internal consumption <strong>of</strong> Bhutan. The<br />

project has recovered more than 60% <strong>of</strong> the Project cost<br />

by sale <strong>of</strong> <strong>power</strong> to India. Encouraged by the successful<br />

operation <strong>of</strong> the Project, a Memorandum <strong>of</strong> Understanding<br />

was signed between Government <strong>of</strong> India and the Royal<br />

Government <strong>of</strong> Bhutan for investigations and preparation<br />

<strong>of</strong> a detailed Project Reports for Chukha Stage-II (Tala<br />

Hydroelectric Project-1000 MW) and Chukha Stage-III<br />

(Wangchu Reservior Scheme - 175 MW) downstream <strong>of</strong><br />

the existing Chukha Project, in Febrauary, <strong>1991</strong>. The<br />

Project, when taken up, would benefit the two countries.<br />

While India would get peaking <strong>power</strong> for the Eastern<br />

Region, Bhutan, on the other hand would be able to earn<br />

substantial revenue by sale <strong>of</strong> <strong>power</strong> to India.<br />

2.27 FOREIGN EXCHANGE<br />

The Department <strong>of</strong> <strong>Power</strong> is responsible for the release <strong>of</strong><br />

foreign exchange for import <strong>of</strong> equipment and spare parts<br />

required for the operation and maintenance <strong>of</strong> <strong>power</strong><br />

stations in the country. It also asesses the need to engage<br />

foreign experts for <strong>power</strong> utilities, both in the public and<br />

private sector. Foreign Exchange <strong>of</strong> Rs. 63.65 crores<br />

under free resources was released upto January, 31, 19<strong>92</strong><br />

for import <strong>of</strong> equipment and spares and also for engaging<br />

foreign experts. Foreign exchange equivalent to Rs. 2.28<br />

Crores was also released to <strong>power</strong> utilities for the import<br />

<strong>of</strong> emergency spares.<br />

Under various lines <strong>of</strong> credit, foreign exchange equivalent<br />

to Rs. 158.<strong>92</strong> crores, as detailed below, was released for<br />

import <strong>of</strong> equipment during the year, upto Janaury 31,<br />

19<strong>92</strong>.<br />

Sl. Project Foreign Exchange Line <strong>of</strong><br />

No. released<br />

(Rs. in crores)<br />

Credit<br />

1. Shravati H.E. Project<br />

(Epoxy Coil winding) 0.89 World Bank<br />

Loan IBRD<br />

2. Bhakra Right Bank <strong>Power</strong><br />

Plant, (BBMB) (Material 56.62 Indo Soviet<br />

for renovation/replacement) Trade Plan


Sl. Project Foreign Exchange Line<br />

No. released<br />

(Rs. in crores)<br />

<strong>of</strong> Credit<br />

3. Thermal <strong>Power</strong> Generation<br />

Station, Trombay (TATA) 0.48 IBRD Loan<br />

(Import <strong>of</strong> Electrode Cell<br />

for electrochlorination Plant).<br />

4. Kathal Guri Mariani Project<br />

No. 2452 IN.<br />

(NEEPCO) Assam (Import <strong>of</strong> 1.40 OECF Loan<br />

structural Steel for<br />

Transmission Towers)<br />

5. Srisallam HEP, APSEB<br />

No. IDP-46<br />

(Import <strong>of</strong> 6x150 MW 50.37 OECF Loan<br />

Generating equipment).<br />

6. Ujjaini HEP. Govt. <strong>of</strong><br />

No. IDP-46<br />

Maharashtra, Irrigation 0.43 OECF Loan<br />

Department (Import <strong>of</strong><br />

additional spares <strong>of</strong><br />

reversible plant).<br />

7. NEEPCO, Import <strong>of</strong><br />

structural steel for<br />

400 KV O/C Mariani Malda<br />

No. IDP-34<br />

Line and Kathal Guri Mariani OECF Loan<br />

section, associated with 20.14 No. IDP-42/<br />

Assam Gas based combined<br />

Cycle <strong>Power</strong> Project.<br />

46<br />

8. Farakka Super Thermal Loan No.<br />

<strong>Power</strong> Project 1.68 2442-IN.<br />

9. Vindhyachal Super Thermal 0.37 Soviet<br />

<strong>Power</strong> Project<br />

10. Rihand Super Thermal<br />

Credit.<br />

<strong>Power</strong> Project 2.94 KFW Loan<br />

11. Rihand Super Thermal IBRD Loan<br />

<strong>Power</strong> Project 0.04 No. 2555-IN<br />

12. Talcher Super Thermal 1.64 IBRD Loan<br />

<strong>Power</strong> Project No. 2845-IN<br />

13. Talcher Super Thermal 2.19 IBRD Loan<br />

<strong>Power</strong> Project No. 2845-IN<br />

14. Gas Based Combined 1.84 IBRD Loan<br />

<strong>Power</strong> Project, Anta No. 2674-IN<br />

15. Kayamkulam and 17.89 Soviet<br />

Mangalore Credit.<br />

Total: 158.<strong>92</strong><br />

Sanctions for engaging a total <strong>of</strong> 62 foreign experts for<br />

various <strong>power</strong> projects were also issued during this<br />

period.<br />

21<br />

2.28 ENERGY<br />

CONSERVATION<br />

Confronted as we are with the increasing energy shortages<br />

on the one hand and scarcity <strong>of</strong> investible resources on the<br />

other, the most cost effective option available to the<br />

country for bridging the gap between the demand and<br />

supply for energy is Energy Demand Management and<br />

Conservation. Energy Conservation has accordingly been<br />

identified by the Department <strong>of</strong> <strong>Power</strong> as one <strong>of</strong> the thrust<br />

areas for the Eighth Five Year Plan. It is aimed to improve<br />

the efficiency <strong>of</strong> existing supply base and reduce the<br />

energy consumption in the energy intensive units through<br />

various measures. The Department <strong>of</strong> <strong>Power</strong> functions as<br />

the nodal point for facilitating the implementation <strong>of</strong> a<br />

coordinated strategy on Energy Conservation. The Energy<br />

Management Centre (EMC) acts as its executive agency.<br />

The strategy being followed is the promotion <strong>of</strong> energy<br />

conservation in energy intensive sectors by assessing the<br />

efficiency <strong>of</strong> energy use through energy audits, evolving<br />

action plan for reducing the level <strong>of</strong> energy consumption<br />

per unit <strong>of</strong> prodcution, and monitoring the targets.<br />

Measures taken in the industrial and other core sectors <strong>of</strong><br />

the economy include the promotion <strong>of</strong> energy savings<br />

through introduction <strong>of</strong> efficient technologies &<br />

demonstration projects, fiscal incentives and<br />

standardisation <strong>of</strong> electrical equipment. Studies have been<br />

undertaken to evaluate specific technical and policy<br />

options, training <strong>of</strong> pr<strong>of</strong>essionals to create a cadre <strong>of</strong><br />

energy managers and auditors, and education <strong>of</strong><br />

consumers through publicity campaign.<br />

During the Eighth Plan, the strategy proposed is to make<br />

energy conservation a mass movement, encourage<br />

consumers to undertake energy audits and to start<br />

demonstration projects, besides intensifying the other<br />

connected activities.<br />

2. AWARNESS PROGRAMME<br />

As a part <strong>of</strong> awareness programme, 14th December every<br />

year has been dedicated as the National Energy<br />

Conservation Day with a view to make Energy<br />

Conservation a people's movement, a part <strong>of</strong> their daily<br />

discipline and as a way <strong>of</strong> life. On 14th December, <strong>1991</strong>,<br />

a function presided over by the President <strong>of</strong> India was<br />

organised. National Energy Conservation week was also<br />

organised all over the country from 14th December to<br />

20th December, <strong>1991</strong>. Simultaneously, an intensive<br />

awareness campaign was undertaken.


Phase II <strong>of</strong> the Awareness Programme at a cost <strong>of</strong><br />

Rs. 1.26 crores was approved. The programme is being<br />

implemented by the Energy Management Centre. Under<br />

this programme, Radio and T.V. spots, press<br />

advertisements, hoardings etc. on the theme <strong>of</strong> Energy<br />

Conservation are being organised.<br />

The Department <strong>of</strong> <strong>Power</strong> also sponsored a number <strong>of</strong><br />

seminars, essay and drawing & poster competitions etc. in<br />

various organisations on the theme <strong>of</strong> Energy<br />

Conservation.<br />

3. NATIONAL AWARD TO INDUSTRIAL<br />

UNITS<br />

With a view to motivate competitiveness, improved<br />

energy efficiency and performance in the various<br />

industries, the Department <strong>of</strong> <strong>Power</strong> has instituted a<br />

National Award Scheme for the Industrial Units showing<br />

excellent performance in efficient utilisation and<br />

conservation <strong>of</strong> energy. The scheme is open to the<br />

Industrial units in various Industrial sub-sectors. On the<br />

Energy Conservation Day on 14th December, <strong>1991</strong><br />

awards for the year 1990 were distributed to 15 Industrial<br />

units.<br />

4. ENERGY AUDITS<br />

Follow up actions on the recommendations <strong>of</strong> the energy<br />

audits completed in about 200 industrial units with the<br />

help <strong>of</strong> various consultancy organisations were taken. The<br />

<strong>report</strong>s received from some <strong>of</strong> the units revealed that they<br />

have achieved substantial savings due to the<br />

implementation <strong>of</strong> the recommendations <strong>of</strong> energy audits.<br />

The Energy Audit scheme in Industrial and Commercial<br />

sectors sanctioned to some <strong>of</strong> the organisations were<br />

progressing satisfactorily. Energy Audit manuals for 10<br />

selected energy sectors, like steel, foundry, vanaspati,<br />

chlor-alkali, automobiles, glass, ceramics, distilleries and<br />

breweries, dairies, re-rolling and galvanized wiredrawings<br />

were prepared through National Productivity<br />

Council.<br />

5. DEMONSTRATION PROJECTS<br />

The agricultural sector continued to be one <strong>of</strong> the major<br />

target sectors for demonstration projects for taking up<br />

rectification <strong>of</strong> agricultural pump sets on a large scale<br />

with Grant-in-aid from the Department <strong>of</strong> <strong>Power</strong>. Out <strong>of</strong><br />

the funds made available by the Department <strong>of</strong> <strong>Power</strong>,<br />

complete rectification <strong>of</strong> 345 agricultural pumpsets were<br />

undertaken in Gujarat. Another scheme <strong>of</strong> partial<br />

rectification <strong>of</strong> 20,000 agricultural pumpsets in Gujarat<br />

was also sanctioned. About 9000 pump sets have already<br />

been rectified. Partial rectification <strong>of</strong> 1350 pump sets in<br />

22<br />

Punjab was also approved during the current financial<br />

year. 10,000 pump sets were rectified by replacement <strong>of</strong><br />

foot-valves in Tamil Nadu.<br />

The system improvement schemes in electrical network in<br />

Meerut Distt. sanctioned to the Rural Electrification<br />

Corporation in 1989 were completed during this financial<br />

year.<br />

A three year project relating to design, installation and<br />

evaluation <strong>of</strong> energy efficient and conservation devices<br />

(viz. 50 KW Vapour Compressor heat pump, sterling<br />

engine run by wood gasifier, development <strong>of</strong> 10 KW<br />

Wind Turbine and high efficiency inverter) was<br />

sanctioned to Central <strong>Power</strong> Research Institute (CPRI),<br />

Bangalore in March, 1990.<br />

A testing and evaluation laboratory for energy efficent<br />

renewable energy devices has also been sanctioned to<br />

CPRI, Bangalore in the year <strong>1991</strong>. The project is expected<br />

to be completed in the year 19<strong>92</strong>-93.<br />

6. TRAINING<br />

The Department <strong>of</strong> <strong>Power</strong> in <strong>1991</strong>-<strong>92</strong> entrusted a training<br />

programme on energy conservation in agricultural<br />

pumping system to Rural Electrification Corporation<br />

(REC) for training 600 <strong>of</strong>ficers from various<br />

organisations. The programme has been completed. The<br />

proposal regarding extension <strong>of</strong> this programme is being<br />

processed.<br />

7. WORKING GROUP ON FLY-ASH<br />

UTILISATION<br />

Based on the recommendations <strong>of</strong> the Working Group on<br />

Fly-Ash Utilisation and on the basis <strong>of</strong> views expressed at<br />

different fora, policy guidelines for promotion <strong>of</strong> use <strong>of</strong><br />

fly-ash were formulated and are being processed for<br />

Government approval.<br />

8. INTERNATIONAL COOPERATION<br />

IN ENERGY CONSERVATION<br />

The Department <strong>of</strong> <strong>Power</strong> have taken up energy<br />

conservation projects with multilateral and bilateral<br />

external assistance. Four Energy Buses have been<br />

acquired under the UNDP Programme. The EEC also<br />

assisted in the acquisition <strong>of</strong> three Energy buses under the<br />

Energy Audit Programme. These Energy Buses are being<br />

used for conducting on the spot Energy Audits <strong>of</strong><br />

Industrial Manufacturing, Commercial and Transport<br />

sub-sectors. Phase-II <strong>of</strong> the SIDA (Swedish International<br />

Development Agency) assisted project in the energy<br />

conservation field, has been undertaken & is in its final<br />

stages.


an Industrial Energy Efficiency Project is proposed to be<br />

implemented with the assistance <strong>of</strong> the World Bank. The<br />

World Bank Team has completed the appraisal <strong>of</strong> the<br />

project and the project is under advanced stage <strong>of</strong><br />

approval.<br />

9. ENERGY MANAGEMENT CENTRE<br />

The Energy Management Centre was established with<br />

EEC cooperation on 10.4.89 under the <strong>department</strong> <strong>of</strong><br />

<strong>Power</strong> and is registered as an autonomous body under the<br />

Societies Registration Act 1860. It is established with the<br />

objectives <strong>of</strong> providing a core group <strong>of</strong> energy sector<br />

pr<strong>of</strong>essionals to carry out/organise training in energy<br />

management/establish and manage a database on energy<br />

efficiency performance, in the country, and assist the<br />

Government in coordinating energy conservation<br />

activities throughout the country.<br />

Since its inception, the EMC has organised useful<br />

activities and has been identified as a focal point for<br />

implementing a number <strong>of</strong> international cooperation<br />

programmes viz. the UNDP Energy Project, the EEC-<br />

India Energy Bus project, the Regional UNDP/ESCAP<br />

TCDC Working Group on Energy Conservation and the<br />

proposed World Bank assisted Energy Efficiency<br />

Technical Assistance Programme.<br />

During the year <strong>1991</strong>-<strong>92</strong>, the EMC took up various<br />

studies on energy demand management aspects. It<br />

organised energy audits, demonstration projects, and<br />

launched awareness campaign on a national level.<br />

2.29 CONSULTATIVE COMMITTEE OF<br />

MEMBERS OF PARLIAMENT<br />

The Consultative Committee <strong>of</strong> Members <strong>of</strong> Parliament<br />

for the <strong>Ministry</strong> <strong>of</strong> <strong>Power</strong> & N.E.S. relates to both the<br />

Departments <strong>of</strong> the <strong>Ministry</strong> viz., the Department <strong>of</strong><br />

<strong>Power</strong> and the Department on Non-Conventional Energy<br />

Sources.<br />

The Department <strong>of</strong> <strong>Power</strong> Coordinated and organised<br />

three meetings <strong>of</strong> the Consultative Committee during the<br />

year (<strong>1991</strong>-<strong>92</strong>). At these meetings, the committee<br />

discussed matters relating to "Introduction to <strong>Power</strong><br />

sector" and "Introduction about Department <strong>of</strong> Non-<br />

Conventional Energy Sources", "General Discussion on<br />

Department on Non-Conventional Energy Sources", and<br />

"Review <strong>of</strong> <strong>Power</strong> Finance Corporation (PFC) and Rural<br />

Electrification Corporation (REC)".<br />

23<br />

2.30 AUDIT OBSERVATIONS<br />

The organisation-wise break-up <strong>of</strong> Audit observations<br />

and Inspection Report/Audit Paras pending as on 31st<br />

December, <strong>1991</strong> are as under.<br />

AUDIT OBJECTIONS AS ON 31.12.<strong>1991</strong><br />

Sl. Organisations No. <strong>of</strong> No. <strong>of</strong> Paras/<br />

No. Inspection Reports<br />

1. C.E.A. 13 32<br />

2. B.T.P.P. 6 51<br />

B.T.P.S. 8 130<br />

3. C.W.C. 27 126<br />

4. B.B.M.B. 69 182<br />

5. N.H.P.C. 100 363<br />

6. Beas Project 109 265<br />

7. P.E.T.S. 11 49<br />

8. Department <strong>of</strong> <strong>Power</strong> 7 48<br />

9. Pay & Accounts Office<br />

i) P.A.O.<br />

C.E.A.<br />

4 7<br />

ii) P.A.O.<br />

B.M.C.C.<br />

2 2<br />

iii) P.A.O.<br />

Sectt.<br />

5 21<br />

iv) P.A.O.<br />

Hydel<br />

2 2<br />

v) C.E.A.<br />

Bangalore<br />

2 2<br />

Total : 365 1280<br />

INTERNAL INSPECTIONS<br />

The Internal Audit Wing <strong>of</strong> the <strong>of</strong>fice <strong>of</strong> the Controller <strong>of</strong><br />

Accounts, Department <strong>of</strong> <strong>Power</strong> ensures the adoption <strong>of</strong><br />

sound procedures, regularity and propriety <strong>of</strong> final<br />

transactions and accuracy <strong>of</strong> accounts. This wing also<br />

advises the DDOs and their staff in correct<br />

implementation <strong>of</strong> rules and maintenance <strong>of</strong> proper<br />

accounts records. Internal Audit Wing also pursues the<br />

settlement <strong>of</strong> objections raised by the Statutory Audit.<br />

During the year performance <strong>of</strong> the Internal Audit Wing<br />

is seen in the table given below :-<br />

No. <strong>of</strong> Units No. <strong>of</strong> Paras No. <strong>of</strong> Paras No. <strong>of</strong> Paras<br />

Year Due & raised settled outstanding<br />

Inspected Upto Dec. 91<br />

1990-91 24/24 322 104 218


2.31 IMPLEMENTATION OF OFFICIAL<br />

LANGUAGE POLICY<br />

During the year, the Department <strong>of</strong> <strong>Power</strong> continued to<br />

follow the Government's instructions relating to the<br />

implementation <strong>of</strong> progressive use <strong>of</strong> Hindi in the<br />

Department as well as in its attatched/subordinate <strong>of</strong>fices<br />

and Public Sector Undertakings.<br />

During the year under review, a Committee <strong>of</strong> Parliament<br />

on Official Language visited the Department on 9.4.<strong>1991</strong><br />

to assess the progress achieved in the use <strong>of</strong> Hindi in the<br />

Department. The Second Sub-Committee <strong>of</strong> the<br />

Committee <strong>of</strong> Parliament on Official Language visited on<br />

27.9.<strong>1991</strong>, the Loktak Hydroelectric Project, Manipur,<br />

which is one <strong>of</strong> the <strong>power</strong> projects <strong>of</strong> the National<br />

Hydroelectric <strong>Power</strong> Corporation, a Public Sector<br />

Undertaking under the administrative control <strong>of</strong> the<br />

Department.<br />

Seven Corporate Offices <strong>of</strong> the Public Sector<br />

Undertakings under the administrative control <strong>of</strong> the<br />

Department <strong>of</strong> <strong>Power</strong>, were also inspected by <strong>of</strong>ficers <strong>of</strong><br />

the Department during the year under review. The<br />

Corporate Offices, wherever neceasery, were advised to<br />

bring improvement in their functioning with regard to the<br />

progressive use <strong>of</strong> Hindi in their <strong>of</strong>ficial work.<br />

To acquaint the <strong>of</strong>ficers/staff with the Official Language<br />

Policy and encourage them to do their maximum work in<br />

Hindi, six Hindi Workshops were organised and fifty nine<br />

<strong>of</strong>ficers/members <strong>of</strong> staff <strong>of</strong> the Department were given<br />

training through Hindi Workshops. A Hindi week was<br />

also organised during the year under review. To motivate<br />

and encourage the <strong>of</strong>ficials, Essay and Typing<br />

Competitions were also organised and prizes awarded to<br />

the successful participants. Meetings <strong>of</strong> the <strong>of</strong>ficial<br />

Language Implementation Committee <strong>of</strong> the Department<br />

were also held during the year.<br />

In order to popularise the use <strong>of</strong> Hindi, the Cash Awards<br />

Scheme, formulated by Department <strong>of</strong> Official Language<br />

was implemented in the Department <strong>of</strong> <strong>Power</strong> and in its<br />

attached and subordinate <strong>of</strong>fices as well as in the Public<br />

Sector Undertakings under the administrative control <strong>of</strong><br />

the Department. These schemes are yielding fruitful<br />

results and have been widely accepted by the <strong>of</strong>ficers/<br />

employees <strong>of</strong> the <strong>department</strong> and other organisations.<br />

The incentive scheme <strong>of</strong> the Department <strong>of</strong> Official<br />

Language for originating notes/dratfs in Hindi was also<br />

24<br />

introduced during the year and the employees who took<br />

part in this Scheme were suitably awarded.<br />

For the promotion <strong>of</strong> original books in Hindi on <strong>power</strong><br />

subjects, a new Scheme under the title "VIDYUT<br />

SAHITYA PURASKAR" is being introduced in the<br />

Department. The scope <strong>of</strong> the Scheme is being extended<br />

to all the members <strong>of</strong> the staff and <strong>of</strong>ficers working in the<br />

Department or in the attached/ subordinate <strong>of</strong>fices and<br />

Public Sector Undertakings. The Scheme is likely to<br />

encourage a large number <strong>of</strong> people associated with<br />

<strong>Power</strong> Sector all over the country to write original books<br />

on the subject in Hindi.<br />

To encourage the employees to acquire pr<strong>of</strong>iciency in<br />

Hindi, the Department has been nominating its staff for<br />

Prabodh, Praveen and Pragya Classes conducted by the<br />

Department <strong>of</strong> Official Language under the auspices <strong>of</strong><br />

Hindi Teaching Scheme. The training in Hindi-typing and<br />

Hindi-stenography has also been arranged to the untrained<br />

members <strong>of</strong> the staff <strong>of</strong> the Department so as to achieve<br />

better results.<br />

2.32 VIGILANCE / DISCIPLINARY<br />

CASES<br />

At the beginning <strong>of</strong> the year <strong>1991</strong>, there were five<br />

vigilance / disciplinary cases. Subsequently, one more<br />

disciplinary case, has been added. One case is pending in<br />

the Court, and the <strong>department</strong>al proceedings are being<br />

taken in the remaining five cases.<br />

2.33 INTERNAL WORK STUDY UNIT<br />

26 Complaints/Petitions/Grievances were received in<br />

Internal Work Study Unit through the Deptt. <strong>of</strong><br />

Administrative Reforms & Public Grievances, Deptt. <strong>of</strong><br />

Pension & Pensioners Welfare, Cabinet Secretariat (Public<br />

Grievance) etc. Action was to be taken on 47 cases<br />

including the 21 pending cases. All these grievances relate<br />

to the service matters and non-settlement <strong>of</strong> pension cases<br />

<strong>of</strong> the employees/ex-employees <strong>of</strong> the Public Sector<br />

Undertakings under the control <strong>of</strong> the Department <strong>of</strong><br />

<strong>Power</strong>.<br />

Out <strong>of</strong> 47 grievances, 30 have been settled. Action on the<br />

rest 17 is in hand with the respective organisations under<br />

this Department.


2.34 PRIME MINISTER'S 15<br />

POINT PROGRAMME ON<br />

WELFARE OF THE<br />

MINORITIES<br />

The Prime Minister's 15-point programme on welfare <strong>of</strong><br />

Minorities is being implemented in the Department <strong>of</strong><br />

<strong>Power</strong>. It has been ensured that in case <strong>of</strong> Direct<br />

recruitment to Group 'C' and 'D' posts, a memebr <strong>of</strong> a<br />

minority community is included in the Selection<br />

Committee. Quartely returns in respect <strong>of</strong> scheduled<br />

castes and scheduled tribes and minorities from Public<br />

Sector Undertakings are being regularly monitored in<br />

accordance with the guidelines on the subject.<br />

A statement incorporating the total number <strong>of</strong><br />

Government Servants employed in the <strong>Ministry</strong> <strong>of</strong> <strong>Power</strong><br />

and Non-Conventional Energy Sources (Department <strong>of</strong><br />

<strong>Power</strong>) including the number <strong>of</strong> schedule castes and<br />

schedule tribes is given below :-<br />

Sl. Name <strong>of</strong> Office Group A Group B Group C Group D<br />

Total SC ST Total SC ST Total SC ST Total SC ST<br />

1. Department<br />

<strong>of</strong> <strong>Power</strong><br />

35 5 1 84 8 – 115 17 3 69 35 4<br />

2. C.E.A. 652 71 8 374 47 1 1043 165 17 399 127 5<br />

3. Controller <strong>of</strong><br />

Accounts<br />

(Deptt. <strong>of</strong> <strong>Power</strong>)<br />

2 1 – 16 3 – 66 4 1 10 4 –<br />

Tehri Project - Rehabilitation <strong>of</strong> Oustees.<br />

25


3.0 CENTRAL ELECTRICITY AUTHORITY<br />

3.1 FUNCTIONS<br />

The Central Electricity Authority is a statutory<br />

organisation constituted under the Electricity (Supply) Act<br />

1948. The main functions <strong>of</strong> the Authority are:<br />

1. to formulate short-term and perspective plans for <strong>Power</strong><br />

Devlopment.<br />

2. to collect data concerning generation, distribution and<br />

utilisation <strong>of</strong> <strong>power</strong>, study <strong>of</strong> cost efficiency, losses,<br />

benefits, publication <strong>of</strong> <strong>report</strong>s and investigations.<br />

3. to advise the State Governments, Electricity Boards,<br />

generation companies or any other agency engaged in the<br />

generation or supply <strong>of</strong> electricity on such matters as<br />

would improve the operation and maintenance <strong>of</strong> their<br />

system in an efficient and coordinated manner.<br />

4. to promote and assist in the timely completion <strong>of</strong><br />

projects sanctioned in the <strong>power</strong> sector and to constantly<br />

monitor their implementation.<br />

5. to make arrangements for advancing the skills <strong>of</strong><br />

persons in the generation and distribution <strong>of</strong> electricity.<br />

6. to promote research in matters affecting the generation,<br />

transmission and distribution <strong>of</strong> electricity.<br />

7. to advise the Central Government on any matter on<br />

which its advice is sought or to make recommendations<br />

which would help in improving the generation,<br />

distribution and utilisation <strong>of</strong> electricity.<br />

In addition, the Electricity Rules 1977 make it incumbent<br />

on the Central Electricity Authority to: formulate the<br />

financial performance <strong>of</strong> the State Electricity Boards and<br />

undertake studies concerning the economic and<br />

commercial aspects <strong>of</strong> the <strong>power</strong> industry as well as<br />

analysis <strong>of</strong> the tariff structure and promote inter-State and<br />

joint sector <strong>power</strong> projects.<br />

3.2 POWER PROGRAMME FOR THE<br />

EIGHTH PLAN : (19<strong>92</strong>-97)<br />

The Planning Commission had set up a Working Group<br />

on <strong>Power</strong> for formulation <strong>of</strong> a programme for <strong>power</strong><br />

development in the 8th Five Year Plan (1990-95). The<br />

Working Group submitted its <strong>report</strong> in December, 1989.<br />

Taking into account the constraints <strong>of</strong> availability <strong>of</strong> funds<br />

and the physical preparedness <strong>of</strong> the 8th Plan starts, which<br />

were taken up in the 7th Plan period and the projects<br />

which could be taken up in the 8th Plan, the Working<br />

Group recommended and incremental capacity addition<br />

programme <strong>of</strong> 38,369 MW for the 8th Plan. Due to<br />

26<br />

various reasons the 8th Plan programme could not be<br />

finalised. In the meantime the plan programme for<br />

<strong>1991</strong>-<strong>92</strong> has already been finalised and is under<br />

implementation. In view <strong>of</strong> this and other major factors<br />

such as changes in priorities etc. the Government decided<br />

to treat the Annual plans for the years 1990-91 and<br />

<strong>1991</strong>-<strong>92</strong> as separate Annual Plans and that the earlier<br />

proposals submitted to the Planning Commission by the<br />

Working Group on <strong>Power</strong> for the period 1990-95,<br />

therefore, needed review to cover the period 19<strong>92</strong>-97.<br />

Accordingly a Group was constituted by Department <strong>of</strong><br />

<strong>Power</strong> for forumulation <strong>of</strong> proposals for the Eight Five<br />

Year Plan (19<strong>92</strong>-97). The Group submitted its <strong>report</strong> in<br />

October, <strong>1991</strong>.<br />

The overall peak <strong>power</strong> and energy shortages at the end<br />

<strong>of</strong> 7th Plan period was about 17% and 8% respectively<br />

even though we succeeded in achieving over 96% <strong>of</strong> the<br />

targeted capacity addition <strong>of</strong> 22245 MW during the plan<br />

period. The total installed <strong>power</strong> generation capacity, in<br />

utilities, at the end <strong>of</strong> the 7th Plan in the country was<br />

63289 MW. Out <strong>of</strong> this, hydro was 18308.8 MW (29%),<br />

thermal 43417 MW (69%) and nuclear 1565 MW (2%).<br />

Thermal capacity includes gas and diesel generation<br />

cpacity. The Working Group had recommended an<br />

addition <strong>of</strong> 38369 MW <strong>of</strong> <strong>Power</strong> generation capacity<br />

during the period 1990-95. Capacity addition <strong>of</strong> 3532<br />

MW during 1990-91 and 6358.3 MW during <strong>1991</strong>-<strong>92</strong><br />

was recommended by the Working Group. Against this<br />

the targets for 1990-91 and <strong>1991</strong>-<strong>92</strong> were fixed at 4212<br />

MW & 3810 MW respectively. However, during 1990-<br />

91, generating units aggregating to 2776.5 MW <strong>of</strong><br />

capacity were synchronised/rolled. There are various<br />

factors which have resulted in the low capacity addition<br />

e.g. constraints <strong>of</strong> resources, and tying up <strong>of</strong> other inputs<br />

etc. The Group on <strong>Power</strong>, which was set up by Deptt. <strong>of</strong><br />

<strong>Power</strong> has recommended a capacity addition programme<br />

<strong>of</strong> 36646 MW in the Eight Plan. The source wise and<br />

sector wise break up <strong>of</strong> capacity addition <strong>of</strong> 36646 MW<br />

in the Eighth Plan period is given below :-<br />

Sector Hydro Thermal Nuclear Total<br />

State Sector 6218.9 13566.8 — 19785.7<br />

Private Sector 168.0 1180.0 — 1348.0<br />

Central Sector3010.0 11327.0 1175.0 15512.0<br />

Total 9396.9 26073.8 1175.0 36645.7


With proposed capacity commissioning <strong>of</strong> 36645.7 MW<br />

during the 8th plan period, the <strong>power</strong> generation capacity<br />

at the end <strong>of</strong> the 8th Plan period, would be 106263.4 MW<br />

comprising 74288.7 MW in thermal, 28764.7 in hydro<br />

and 3210 MW in Nuclear.<br />

3.3 TECHNO-ECONOMIC APPRAISAL<br />

The Central Electricity Authority is responsible for the<br />

identification <strong>of</strong> schemes for thermal as well as hydro<br />

<strong>power</strong> stations for benefits during the plan periods. The<br />

CEA is associated with the inspection <strong>of</strong> sites proposed<br />

for <strong>power</strong> projects, tying up <strong>of</strong> necessary inputs like coal,<br />

water, transport facilities, environmental clearance and<br />

civil aviation clearance. The CEA is also responsible for<br />

establishing the need for captive <strong>power</strong> projects and to<br />

recommend the same whenever required.<br />

During the current financial year i.e. <strong>1991</strong>-<strong>92</strong>, Central<br />

Electricity Authority accorded techno-economic approval<br />

to 35 New Schemes and 9 Revised Cost Estimates from<br />

1.4.91 to 31.1.<strong>92</strong> as per following details :i)<br />

NEW SCHEMES<br />

As on 31.1.<strong>92</strong><br />

Type <strong>of</strong> Schemes IC(MW)/ No. <strong>of</strong> Estimated Cost<br />

Ckt.Kms. Schemes Rs. in Crores<br />

A. Schemes <strong>of</strong> SEB's Generating Companies etc.<br />

Hydro 846.25/280<br />

Ckt.Kms.<br />

7 1260.10<br />

Thermal 900 4 1696.69<br />

T&D` 9122<br />

Ckt.Kms.<br />

14 11<strong>92</strong>.86<br />

R&D Gen: – 5 395.28<br />

T&D 1 60.06<br />

Sub-total (A) 1746.25 MW/<br />

9402 Ckt.Kms.<br />

31 4604.99<br />

B. Schemes <strong>of</strong> Licensees/Captive Schemes<br />

Hydro 90 1 71.20<br />

Thermal 240 1 5<strong>92</strong>.87<br />

T&D 406 Ckt.Kms. 2 118.02<br />

Sub-total (B) 330 MW/406<br />

Ckt.Km.<br />

4 782.09<br />

GRAND TOTAL 2076.25 MW/<br />

98008 Ckt. Kms.<br />

35 5387.08<br />

27<br />

ii) REVISED COST ESTIMATES<br />

Type <strong>of</strong> No. <strong>of</strong> I.C. (MW)/<br />

(Upto 31.1.<strong>92</strong>)<br />

Estimated Cost<br />

Scheme revised Ckt. Kms. Original Revised<br />

estimates (Rs. in Crores)<br />

Hydro 5 1967 MW/<br />

35 Ckt. Kms.<br />

886.93 2363.33<br />

Thermal 1 840 MW 1174.40 22<strong>92</strong>.26<br />

T&D 2 825 Ckt. Kms. 103.29 87.22<br />

R&D 1 – 39.85 43.13<br />

TOTAL 9 2807 MW/<br />

860 Ckt. Kms.<br />

2204.47 4785.94<br />

3.4 TRAINING ORGANISATIONS OF<br />

THE CEA<br />

3.5 POWER SYSTEM TRAINING<br />

INSTITUTE (PSTI)<br />

The <strong>Power</strong> System Training Institute, Bangalore imparts<br />

training in various disciplines, including <strong>power</strong> systems<br />

planning, operation, protection, communication in <strong>power</strong><br />

systems, computer application and <strong>power</strong> telecommunication<br />

co-ordination. Since the inception <strong>of</strong> the Institute in<br />

1972, 3252 engineers had been trained upto the end <strong>of</strong><br />

90-91. During the year 91-<strong>92</strong>, 143 more engineers were<br />

trained at the Institute.<br />

A scheme <strong>of</strong> augmentation <strong>of</strong> training facilities <strong>of</strong> PSTI<br />

which was approved by the Government in February,<br />

1989 at an estimated cost <strong>of</strong> Rs. 323,38 lakhs has been<br />

taken up for implementation. Civil works have been<br />

entrusted to the CPWD. Orders have been placed for the<br />

supply <strong>of</strong> Static Protective Relay cubicle.<br />

The Institute has acquired a Despatcher Training<br />

Simulator (DTS) and a set <strong>of</strong> educational Video-tapes<br />

along with a Video Projection System as part <strong>of</strong> UNDP<br />

aided project IND/86/005. These facilities have also been<br />

integrated into the training programmes being conducted<br />

by PSTI.<br />

3.6 HOT LINE TRAINING CENTRE<br />

(HLTC)<br />

In order to reduce to the barest minimum the outages <strong>of</strong><br />

transmission lines during maintenance, Hot Line


Maintenance Techniques are being introduced. A Hot<br />

Line Training Centre to train personnel in Hot Line<br />

Maintenance Techniques upto 220 KV was set up at<br />

Bangalore in 1975. 659 personnel were trained by the<br />

Centre upto the end <strong>of</strong> 1990-91. During the year <strong>1991</strong>-<strong>92</strong>,<br />

31 personnel in 220 KV level (Hot-stick method) and 30<br />

personnel in 400 KV level (Bare-Hand method) have been<br />

trained at the centre.<br />

A scheme for augmentation <strong>of</strong> the training facilities at an<br />

approved cost <strong>of</strong> Rs. 479.48 lakhs is under implementation.<br />

Under this scheme, tools and equipment required for<br />

training using hot-stick and bare-hand techniques upto<br />

400 KV voltage level have been procured and also about<br />

57 acres <strong>of</strong> land have been acquired at Somanahalli near<br />

Bangalore for setting up a permanent Training Centre<br />

along with hostel, staff quarters, etc. Civil works have<br />

been entrusted to CPWD. The construction <strong>of</strong> 400 KV/<br />

220 KV experimental lines end the construction <strong>of</strong> 11 to<br />

110 KV experimental lines along with <strong>power</strong> supply have<br />

been completd.<br />

3.7 UNDP - AIDED PROJECT<br />

The Central Electricity Authority completed<br />

implementation <strong>of</strong> UNDP-aided project relating to<br />

modernisation <strong>of</strong> training facilities at PSTI, Bangalore and<br />

the development <strong>of</strong> expertise in system/operation and<br />

started in April 1987 and all the activities have been<br />

completed now. Installation and commissioning <strong>of</strong> a<br />

Depatcher Training Simulator (DTS) which constituted<br />

the main component <strong>of</strong> the project was completed in<br />

February, 1990, and the equipment was accepted in May,<br />

1990 after a 60 days working availability test run. The<br />

system has also been integrated into different training<br />

programmes being conducted in PSTI, Bangalore. As per<br />

UNDP guidelines, the project was evaluated by UNDP<br />

designed independent consultant.<br />

4.0 ASSISTANCE TO THE<br />

STATE ELECTRICITY BOARDS:<br />

UTTAR PRADESH:<br />

ANPARA 'B' THERMAL POWER PROJECT<br />

The Government <strong>of</strong> India have agreed to provide to the<br />

State <strong>of</strong> U.P. a special loan assistance <strong>of</strong> Rs. 127 Crores<br />

representing 50% <strong>of</strong> the resource gap to be mobilised by<br />

the Govt. <strong>of</strong> U.P. to meet its commitment for the year<br />

<strong>1991</strong>-<strong>92</strong> in respect <strong>of</strong> Anpara 'B' Thermal <strong>Power</strong> Project<br />

(2x500 MW) as the State Government had expressed its<br />

inability to continue the implementation <strong>of</strong> the project on<br />

account <strong>of</strong> resource constraint.<br />

28<br />

FEROZ GANDHI UNCHAHAR THERMAL<br />

POWER PROEJCT<br />

A Memorandum <strong>of</strong> Understanding was signed on 8th<br />

December, <strong>1991</strong>, between the Minister <strong>of</strong> State for <strong>Power</strong><br />

and Non-conventional Energy Sources and the U.P. Chief<br />

Minister to provide for the transfer <strong>of</strong> ownership <strong>of</strong> the<br />

Feroz Gandhi Unchahar Thermal <strong>Power</strong> Project (existing<br />

capacity 2x210 MW and approved extension capacity <strong>of</strong><br />

2x210 MW) <strong>of</strong> Uttar Pradesh Rajya Vidyut Utpadan<br />

Nigam to the National Thermal <strong>Power</strong> Corporation at a<br />

value <strong>of</strong> Rs. <strong>92</strong>5 crores to ensure operation <strong>of</strong> the existing<br />

Unchahar Project at its optimum capacity, commencement<br />

<strong>of</strong> work on the extension project, held up on account <strong>of</strong><br />

resource constraints, and to liquidate its outstanding dues<br />

and future dues to the Central Agencies viz. NTPC.<br />

ANDHRA PRADESH<br />

A Technical Assistance Agreement has been signed with<br />

the Asian Development Bank loan assistance <strong>of</strong> 1 million<br />

US Dollars to assist the Andhra Pradeh State Electricity<br />

Board in its efforts to improve its operations in the areas<br />

<strong>of</strong> electricity demand management <strong>power</strong> system<br />

management and loss reduction in a generation,<br />

transmission and distribution; integrated data processing<br />

including computerised management information system<br />

and provision <strong>of</strong> related training.<br />

5.0 PRIVATE SECTOR<br />

PARTICIAPTION IN POWER<br />

GENERATION<br />

5.1 POST-POLICY ENVIRONMENT<br />

FOR PRIVATE SECTOR INVESTMENT<br />

To bring in additionality <strong>of</strong> resources for the capacity<br />

addition programme in the Electricity sector, Government<br />

has formulated a scheme to encourage greater partcipation<br />

by private enterprises in electricity generation, supply and<br />

distribution. The scheme widens the scope <strong>of</strong> private<br />

investment in the sector and has modified the financial,<br />

administrative and legal environment for the private<br />

enterprises to make investments in the Electricity sector<br />

attractive. The new environment is based on the<br />

amendments to the electricity legislation, namely, the<br />

Indian Electricity Act, 1910, Electricity (Supply) Act 1948<br />

on which the electricity sector in India is based.


- Private sector units can set up coal/lignite or gasbased<br />

thermal, hydel, wind and solar energy projects <strong>of</strong> any<br />

size.<br />

- Private enterprises can set up units, either as Licensees<br />

distributing <strong>power</strong> in a licenced area from own<br />

generation or purchased <strong>power</strong> or as Generating<br />

Compaines, generating <strong>power</strong> for supply to the grid.<br />

- Licensee companies holding license to supply and<br />

distribute energy in a specified area under a license<br />

issued by the State Government will function under a<br />

liberalised economic and legal environment.<br />

- New licenses can be issued by the State Governments<br />

to private units, willing to enter the Electricity sector.<br />

- Captive <strong>Power</strong> Plants set up to serve an industrial or<br />

other units by the private enterprises will be permitted<br />

to sell or supply surplus <strong>power</strong> to SEBs.<br />

Investment Promotion Cell (IPC) in the Department <strong>of</strong><br />

<strong>Power</strong> will directly interface with prospective private<br />

enterprise entrants to the Electricity sector and help them<br />

in getting clearances. The High <strong>Power</strong>ed Board under the<br />

Chairmanship <strong>of</strong> Cabinet Secretary comprising<br />

Secretaries <strong>of</strong> concerned Ministries <strong>of</strong> the Government <strong>of</strong><br />

India to which senior <strong>of</strong>ficials <strong>of</strong> the State Government<br />

concerned can be coopted, would monitor issue <strong>of</strong><br />

clearances, and resolve all outstanding issues pertaining to<br />

clearances. The Board would decide on all other matters<br />

concerning investment from non-resident Indians and<br />

foreign sources within a scheduled time-frame.<br />

5.2 INCENTIVES UNDER THE<br />

SCHEME IN THE NEW POLICY<br />

The scheme forumulated under the policy throws the<br />

electricity generation, supply and distribution field wide<br />

open to private enterpreneurs, opening up pr<strong>of</strong>itable<br />

investment opportunities. That <strong>of</strong>fers a package <strong>of</strong><br />

incentives which investors, both from India and overseas,<br />

will find really attractive.<br />

All private companies entering the Electricity Sector<br />

hereafter will be allowed a debt-equity ratio <strong>of</strong> 4:1. They<br />

will be permitted to raise upto a minimum <strong>of</strong> 20 percent<br />

<strong>of</strong> the total outlay through public issues.<br />

Promoters contribution should be at least 11% <strong>of</strong> the total<br />

outlay. Not more than 40% <strong>of</strong> the total outlay can come<br />

29<br />

from Indian Public Financial Institutions. To ensure that<br />

private enterpreneurs bring in additionality <strong>of</strong> resources to<br />

the sector, they must find 60 per cent <strong>of</strong> the resources<br />

from sources other than public financial institutions.<br />

For both Licensee and Generating Companies, the<br />

following is permitted :<br />

• Upto Hundred percent (100%) foreign equity<br />

participation can be permitted for projects set up by<br />

foreign private investors.<br />

• With the approval <strong>of</strong> the Government, import <strong>of</strong><br />

equipment for <strong>power</strong> projects will also be permitted in<br />

cases where foreign supplier(s) or agency(ies) extend<br />

concessional credit.<br />

Generating companies can be set up by Private<br />

enterpreneures. For safeguarding return on investment<br />

against possible under-demand <strong>of</strong> <strong>power</strong> arising from<br />

variations in demand, generating companies can now sell<br />

<strong>power</strong> on the basis <strong>of</strong> a suitably structured two-part tariff.<br />

This will be based on operational norms and optimal PLF<br />

(Plant Load Factor) prescribed by the CEA/Government,<br />

as also on a rate <strong>of</strong> depreciation notified by the Central<br />

Government, from time to time.<br />

The Indian Electricity Act and the Electricity (Supply) Act<br />

have been amended to bring about this new legal and<br />

financial environment for private enterprises in the<br />

Electricity Sector. As a step towards liberalisation,<br />

schemes where the total outlay does not exceed Rs. 25<br />

crores need not be submitted to CEA for concurrence.<br />

The specific incentives for Licenses are:<br />

a: Licenses <strong>of</strong> a longer duration <strong>of</strong> 30 years in the first<br />

instance and subsequent renewals <strong>of</strong> 20 years, instead<br />

<strong>of</strong> 20 and 10 years respectively as at present.<br />

b: Higher rate <strong>of</strong> return <strong>of</strong> 5% in place <strong>of</strong> the previous 2%<br />

above the RBI rate.<br />

c: Capitalisation <strong>of</strong> Interset During Construction (IDC) at<br />

actual cost (for expansion project also) as agaisnt 1%<br />

over RBI rate as at present.<br />

d: Special appropriations to meet debt redemption<br />

obligations.<br />

The details <strong>of</strong> private sector projects are given in the<br />

enclosed Tables (V-XI).


Table-V<br />

Existing Private Sector units<br />

Corporation Capacity<br />

1. Tata Electric Co. 1606 MW<br />

2. C.E.S.C. 615 MW<br />

3. A.E. Co. 509 MW<br />

4. Gujarat Industrial <strong>Power</strong><br />

Corpn. Ltd. (GIPCL)<br />

66 MW<br />

5. Andhra Pradesh Gas<br />

<strong>Power</strong> Corpn.<br />

66 MW<br />

TOTAL 2862 MW<br />

Project advertised by State Governments<br />

for implementation in private sector<br />

Table-VII<br />

Thermal Coal 14,225 MW<br />

Thermal Gas 5,260 MW<br />

Hydel 1,885 MW<br />

Others (Wind, solar, DG sets etc) 158 MW<br />

TOTAL 21,558 MW<br />

Projects to be implemented with foreign investment<br />

Table-VI<br />

Details <strong>of</strong> on-going private sector <strong>power</strong> projects<br />

Name <strong>of</strong> the Capacity Type State<br />

Project (MW)<br />

1. Bhira Pumped<br />

Storage Scheme<br />

150 Hydel Maharashtra<br />

2. Gujarat Industrial 78 Thermal Gujarat<br />

<strong>Power</strong> Corporation Ltd. (Gas)<br />

3. Vijjeshwaram 33 Thermal Andhra<br />

(Gas) Pradesh<br />

4. Trombay 180 CCGT Maharashtra<br />

5. Dahanu - BSES 500 Thermal Maharashtra<br />

(Western Maharashtra) (Coal)<br />

6. Maniyar 12 Hydel Kerala<br />

TOTAL 953<br />

Name <strong>of</strong> the Project/<br />

State<br />

Capacity Type Agency<br />

1. Barsingsar TPS/ 240 MW Lignite Lignite M/s Coleman &<br />

Rajasthan [2x120 MW] Associates Pvt. Ltd.<br />

(Australian Consortium)<br />

2. 'Zero unit' TPS <strong>of</strong> 210 MW Lignite M/s ST <strong>Power</strong><br />

NLC/Tamil Nadu Systems Inc., USA<br />

3. Ib Valley TPS/ 2340 MW Thermal M/s Southern Electric<br />

Orissa (Coal) International Inc., USA<br />

4. Dubri TPS <strong>of</strong> Kalinga 500 MW Thermal M/s North East<br />

<strong>Power</strong> Corpn. Ltd/<br />

Orissa<br />

[2x250 MW] (Coal) Services Inc., USA<br />

5. Gas based 800 MW Gas M/s NTPC & M/s ABB<br />

Total 4,090 MW<br />

30<br />

Table-VIII


Out <strong>of</strong> Project Advertised - Decision taken by State Govts. to entrust implementation to private firms<br />

Name <strong>of</strong> Project/<br />

State<br />

Capacity Type Agency Remarks<br />

1. Pench TPS Stg.I/M.P. 420 MW Thermal M/s Centuary Textiles<br />

(Coal) and Industries Ltd.,<br />

Bombay<br />

2. Baspa-II H.E./H.P. 300 MW Hydel M/s Jaiprakash<br />

Industries Ltd., Delhi<br />

3. Ghanvi H.E./H.P. 22.5 MW Hydel M/s Punjab <strong>Power</strong><br />

Generation Machines Ltd<br />

4. TIDCO with 1500 MW Lignite M/s Jayamkondam<br />

McNally Bharat/<br />

Tamil Nadu<br />

[3x500 MW] Lignite Corpn. Ltd<br />

5. Uhl-III/<br />

Himachal Pradesh<br />

70 MW Hydel M/s Ballarpur Industries<br />

6. Chandil TPS/ 500 MW Thermal M/s RPG Enterprises<br />

Bihar (Coal)<br />

7. Godavari CCGT 400 MW Thermal<br />

Gas<br />

M/s GVK Industries ltd.<br />

3212.5 MW<br />

Projects with evinced interest under examination in CEA<br />

1. Barge mounted/ 110 MW Thermal M/s Confidence<br />

Maharashtra Shipping Co. Pvt. Ltd.<br />

2. TICAPCO/<br />

Tamil Nadu<br />

250 MW<br />

360 MW<br />

Lignite M/s GM Swamy Associates<br />

Project approved after Policy Amendment<br />

1. Budge-Budge TPS/ 500 MW M/s C.E.S.C<br />

West Bengal [2x250 MW]<br />

31<br />

Table-IX<br />

Table-X<br />

Table-XI


6.0 PUBLIC SECTOR UNDERTAKINGS & OTHER<br />

ORGANISATIONS<br />

6.1 NATIONAL THERMAL POWER<br />

CORPORATION LTD (NTPC).<br />

The NTPC is presently engaged in the execution <strong>of</strong> nine<br />

Super Thermal <strong>Power</strong> Project with an aggregate approved<br />

capacity <strong>of</strong> 13240 MW and four gas based combined<br />

cycle projects with an aggregate approved capacity <strong>of</strong><br />

2527 MW. The NTPC has also undertaken the<br />

construction <strong>of</strong> transmission lines with a total length<br />

<strong>of</strong> about 20200 ckt.kms. <strong>of</strong> high voltage lines including<br />

about 813 ckt. kms. <strong>of</strong> HVDC transmission line and 85<br />

sub-stations/sub-station extensions. The total approved<br />

cost <strong>of</strong> the NTPC projects including associated<br />

transmission system and other schemes is Rs. 18624.12<br />

crores. The above includes Rs. 103.5 crores for<br />

Vindhyachal-II.<br />

6.2 Projects under Implementation<br />

The details <strong>of</strong> the projects <strong>of</strong> the NTPC under<br />

implementation are given below :<br />

DETAILS OF NTPC PROJECTS<br />

Name <strong>of</strong> the Region/State Capacity in MW Actual/Expected Approved Cost<br />

Project date <strong>of</strong> incl. associated TL<br />

Ultimate Approved commissioning System<br />

(Rs. in Crs.)<br />

Singrauli STPP Northern 2000 2000 1374.93<br />

Uttar Pradesh Stage-I Unit-1(200) Feb.82<br />

(3x200) Unit-2(200) Nov. 82<br />

Unit-3(200) Mar. 83<br />

Stage-II Unit-4(200) Nov. 83<br />

(2x200+2x500) Unit-5(200) Feb. 84<br />

Unit-6(500) Dec. 86<br />

Unit-7(500) Nov. 87<br />

Korba STPP Western 2100 2100 1873.79<br />

Madhya Stage-I Unit-1(200) Mar. 83<br />

Pradesh (3x200+1x500) Unit-2(200) Oct.83<br />

Unit-3(200) Mar. 84<br />

Unit-4(500) May. 87<br />

Stage-II Unit-5(500) Mar. 88<br />

(2x500) Unit-6(500) Mar. 89<br />

Ramagundam STPP Southern 2100 2100 1985.12<br />

Andhra Stage-I Unit-1(200) Oct. 83<br />

Pradesh (3x200+1x500) Unit-2(200) May. 84<br />

Unit-3(200) Dec. 84<br />

Unit-4(500) Jun. 88<br />

Stage-II Unit-5(500) Mar. 89<br />

(2x500) Unit-6(500) Oct. 89<br />

Farakka STPP Eastern 2100 2100 2366.69<br />

West Bengal Stage-I Unit-1(200) Jan. 86<br />

(3x200) Unit-2(200) Dec. 86<br />

Unit-3(200) Aug. 87<br />

Stage-II Unit-4(500) Jun. <strong>92</strong><br />

(2x 500) Unit-5(500) Jun. 93<br />

Stage-III (1x500) Unit-6(500)#<br />

32


Name <strong>of</strong> the Region/State Capacity in MW Actual/Expected Approved Cost<br />

Project date <strong>of</strong> incl. associated TL<br />

Ultimate Approved commissioning System<br />

(Rs. in Crs.)<br />

Vindhyachal STPP Western 2260 1260 1773.29<br />

Madhya Pradesh Stage-I Unit-1(210) Oct. 87<br />

(6x210) Unit-2(210) Jul. 88<br />

Unit-3(210) Feb.89<br />

Unit-4(210) Dec. 89<br />

Unit-5(210) Mar. 90<br />

Unit-6(210) Feb. 91<br />

Rihand STPP Northern 3000 1000 1688.17<br />

Uttar Pradesh Stage-I Unit-I(500) Mar.88<br />

(2x500) Unit-2(500) Jul. 89<br />

Kahalgaon STPP Eastern 2840 840 1058.64<br />

Bihar Stage-I Unit-1(210) Mar. <strong>92</strong><br />

(4x210) Unit-2(210) Mar. 93<br />

Unit-3(210) Nov. 93<br />

Unit-4(210) Jun. 94<br />

National Northern 840 840 1063.60<br />

Capital Thermal Uttar Pradesh Stage-I Unit-1(210) Oct. 91<br />

<strong>Power</strong> Project (4x210) Unit-2(210) Sept. <strong>92</strong><br />

(Dadri) Unit-3(210) Mar. 93<br />

Unit-4(210) Sept. 93<br />

Talcher STPP Eastern 3000 1000 1480.85<br />

Orissa Stage-I Unit-1(500) Apr. 94<br />

(2x500) Unit-2(500) Apr. 95<br />

Kawas GBPP Western 1295 600-Nominal Gas Turbine 410.84<br />

Gujarat Stage-I 645-Actual Unit-1(106) Mar. <strong>92</strong><br />

(4x106+2x110) Unit-2 (106) July, <strong>92</strong><br />

Unit-3(106) Sept. <strong>92</strong><br />

Unit-4(106) Nov. <strong>92</strong><br />

Steam Turbine<br />

Unit-5(110) May, 93<br />

Unit-6(110) Sept. 93<br />

Auraiya GBPP Northern 1302 600-Nominal Gas Turbine 472.28<br />

Uttar Pradesh Stage-I 652-Actual Unit-1(112) Mar. 89<br />

(4x112+2x102) Unit-2(112) Jul. 89<br />

Unit-3(112) Aug. 89<br />

Unit-4(112) Sept. 89<br />

Steam Turbine<br />

Unit-5(102) Dec. 89<br />

Unit-6(102) Jun. 90<br />

33


Name <strong>of</strong> the Region/State Capacity in MW Actual/Expected Approved Cost<br />

Project date <strong>of</strong> incl. associated<br />

Ultimate Approved commissioning TL System<br />

(Rs. in Crs.)<br />

Anta GBPP Northern 843 430-Nominal Gas Turbine 316.74<br />

Rajasthan Stage-I 413-Actual Unit-1 (88) Jan. 89<br />

(3x88 + 1x149) Unit-2 (88) Mar. 89<br />

Unit-3 (88) May. 89<br />

Steam Turbine<br />

Unit-4 (149) Mar. 90<br />

Dadri GBPP Northern 1225 817 Gas Turbine 783.44<br />

Uttar Pradesh Stage-I Unit-1 (131) Jan. <strong>92</strong><br />

(4x131+2x146.5) Unit-2 (131) Mar. <strong>92</strong><br />

Unit-3 (131) Jun. <strong>92</strong><br />

Unit-4 (131) Sept. <strong>92</strong><br />

Steam Turbine<br />

Unit-5 (146.5) May, 93<br />

Unit-6 (146.5) Aug. 93<br />

Central 1655 Ckt. Kms. 400 KV 388.05<br />

Transmission<br />

Project-I<br />

Rihand <strong>Power</strong> 1691 Km 400 KV A/C 1063.00<br />

Transmission 814.5 Km 1± 500 KV HVDC<br />

Project<br />

Vindhyachal 1930 Km 400 KV 339.69<br />

Additional TL<br />

Total Approved 15767 MW 18439.12<br />

# Unit to be commissioned in 5 years from the date <strong>of</strong> Main Plant Award. The process <strong>of</strong> tendering and award <strong>of</strong><br />

main plant contract will be taken up after the World Bank funding envisaged for the project becomes effective.<br />

NB: 1. In addition Govt. approval to incur Rs. 103.5 Crs. by way <strong>of</strong> advance action/Stage-I clearance accorded in<br />

March, 90 for Vindhyachal Stage-II Project.<br />

2. Approved Cost <strong>of</strong> Other Schemes is Rs. 81. 50 Crs.<br />

34


6.3 Capacity Additons<br />

By end March, 91 NTPC had commissioned 10, 125 MW<br />

at its various Stations. Details <strong>of</strong> capacity commissioned<br />

are given below :<br />

Project Capacity commissioned<br />

Singrauli 2000 MW<br />

Korba 2100 MW<br />

Ramagundam 2100 MW<br />

Farakka 500 MW<br />

Rihand 1000 MW<br />

Vindhyachal 1260 MW<br />

Anta 413 MW<br />

Auraiya 652 MW<br />

TOTAL 10125 MW<br />

During the year <strong>1991</strong>-<strong>92</strong>, the NTPC has programmed to<br />

commission 788 MW comprising 210 MW from NCTPP,<br />

210 MW from Kahalgaon, 262 MW from Dadri Gas<br />

Project and 106 MW from Kawas Gas Project. Of this,<br />

the 210 MW Unit at National Capital Thermal <strong>Power</strong><br />

Project; Dadri has already been commissioned. With this<br />

the total installed capacity <strong>of</strong> NTPC stands increased to<br />

10335 MW. The other Units programmed for<br />

commissioning this year are progressing satisfactorily.<br />

6.4 Transmission Lines<br />

NTPC - Kahalgaon Super Thermal <strong>Power</strong> Project<br />

35<br />

By end March, 91 NTPC had completed 153.89 ckt. Kms<br />

<strong>of</strong> transmission lines. During 91-<strong>92</strong>, NTPC has<br />

programmed to add 860 Ckt. Kms. NTPC has already<br />

completed 775 ckt. kms. <strong>of</strong> transmission lines thereby<br />

raising the total length <strong>of</strong> high voltage lines laid by NTPC<br />

to 16511 Ckt. Kms.<br />

The following transmission lines have been fully<br />

completed during the year <strong>1991</strong>-<strong>92</strong>.<br />

1. Agra-Chatta 400 KV S/C<br />

2. Chatta-Ballabgarh 400 KV S/C<br />

3. Vijayawada-Gazuwaka 400 KV S/C<br />

4. Gooty-Bangalore 400 KV S/C<br />

5. Maithon-Jamshedpur 400 KV D/C<br />

6.5 Generation<br />

As on end December, <strong>1991</strong> a total capacity <strong>of</strong> 10335 MW<br />

is under operation at various NTPC Stations. This<br />

comprised 22 Units <strong>of</strong> 200/210 MW at Singrauli, Korba,<br />

Ramagundam, Farakka, Vindhyachal and NCTPP, 10<br />

Units <strong>of</strong> 500 MW at Singrauli, Korba, Ramagundam and<br />

Rihand and 10 Gas/Steam Units at Anta and Auraiya.<br />

The generation from NTPC stations has been at a


consistently high level. Till end December, <strong>1991</strong> the gross<br />

generation from NTPC stations is 44190 MUs against the<br />

target <strong>of</strong> 54847 MUs for the year. The generation during<br />

the previous year (1990-91) was 46,879 MUs compared to<br />

the target <strong>of</strong> 46,475 MUs.<br />

The units under commercial operation generated 44164<br />

MUs at a plant load factor <strong>of</strong> 67.49% during <strong>1991</strong>-<strong>92</strong>, till<br />

the end <strong>of</strong> December, <strong>1991</strong>. During the same period, the<br />

units under commercial operation at Singrauli, Korba,<br />

Ramagundam, Farakka, Vindhyachal, Rihand, Anta (Gas)<br />

and Auraiya (Gas) operated at a PLF <strong>of</strong> 77.47%, 68.33%,<br />

56.22%, 59.76%, 68.21%, 72.98%, 66.11% and 68.85%<br />

respectively.<br />

Units that achieved plant load factor in excess <strong>of</strong> 70%<br />

during their operation upto December, 91 are detailed<br />

below :<br />

Sl. No. Station Capacity Unit No. PLF (%)<br />

1. Singrauli 200 1 87.54<br />

2. Singrauli 200 3 82.74<br />

3. Singrauli 200 4 88.41<br />

4. Singrauli 500 5 88.83<br />

5. Singrauli 500 6 78.67<br />

6. Korba 200 1 78.18<br />

7. Korba 200 3 87.46<br />

8. Korba 500 4 75.71<br />

9. Farakka 200 2 73.35<br />

10. Vindhyachal 210 1 78.48<br />

11. Vindhyachal 210 6 70.60<br />

12. Rihand 500 1 78.14<br />

13. Anta 88 1 70.65<br />

14. Anta 88 2 75.97<br />

15. Auraiya 112 1 73.97<br />

16. Auraiya 102 2 79.52<br />

6.6 Awards<br />

The NTPC's Ramagundam project qualified for the<br />

Meritorious productivity award for 1990 for achieving<br />

high standards <strong>of</strong> performance.<br />

Four employees <strong>of</strong> the Vindhyachal STPP have been<br />

awarded the Prime Minister's Sharm Bhushan Award in<br />

<strong>1991</strong> for their outstanding and meritorious work<br />

performance.<br />

NTPC was awarded the Company Standardisation<br />

Commendation Award for the year <strong>1991</strong> by the Institute<br />

36<br />

<strong>of</strong> Standards Engineers. Till <strong>1991</strong> the Quality Assurance<br />

Deptt. has introduced about 500 company standards many<br />

<strong>of</strong> which are being considered as inputs for National<br />

Standards.<br />

6.7 Agreement for Construction,<br />

Operation and Management<br />

<strong>of</strong> Transmission System<br />

In pursuance <strong>of</strong> the decision <strong>of</strong> Department <strong>of</strong> <strong>Power</strong>,<br />

NTPC and National <strong>Power</strong> Transmission Corporation<br />

(NPTC) entered into a management agreement dated 13th<br />

August, <strong>1991</strong> vide which NPTC has transferred various<br />

transmission systems to NTPC for the purpose <strong>of</strong><br />

Construction, Operation and Maintenance on behalf <strong>of</strong><br />

NTPC. NTPC, however, still retains the ownership <strong>of</strong> the<br />

above transmission assets.<br />

In pursuance <strong>of</strong> this agreement, various NTPC executives<br />

and Non-executives connected with transmission lines and<br />

associated functions also stood transferred to NPTC with<br />

effect from 16.8.<strong>1991</strong>. Completion <strong>of</strong> legal and other<br />

formalities for transfer <strong>of</strong> ownership <strong>of</strong> transmission assets<br />

to NPTC has been taken up in line with Govt. decision in<br />

this regard.<br />

6.8 Budget Utilisation And Financial<br />

Aspects<br />

The authorised share capital <strong>of</strong> the Corporation is<br />

Rs. 8000 crores. As <strong>of</strong> Dec. <strong>1991</strong> the paid up capital <strong>of</strong><br />

NTPC was Rs. 6954.78 crores, which is wholly subscribed<br />

by the Government <strong>of</strong> India.<br />

During the financial year 1990-91, the NTPC earned a net<br />

pr<strong>of</strong>it <strong>of</strong> Rs. 700.95 crores. The return on capital<br />

employed and return on net worth were 10.02% and<br />

10.58% respectively (excluding prior period income).<br />

The total amount raised upto 31st December, <strong>1991</strong> from<br />

the three public issues and three private placements <strong>of</strong> the<br />

NTPC <strong>power</strong> bond was Rs. 2083.04 crores.<br />

Outlay For <strong>1991</strong>-<strong>92</strong>.<br />

Despite phenomenal expansion in construction activities,<br />

NTPC has been relying more and more on internal and<br />

extra budgetary resources for meeting its requirement <strong>of</strong><br />

funds thereby reducing its dependence on Government <strong>of</strong><br />

India for net budgetary support. The requirement <strong>of</strong> funds,<br />

especially for the new projects, is envisaged to by way <strong>of</strong><br />

international assistance and commercial borrowings.


The plan outlay for <strong>1991</strong>-<strong>92</strong> has been proposed at<br />

Rs. 2755.77 Crs. in the revised estimate. This outlay is<br />

proposed to be financed as under :<br />

(Rs. Crores)<br />

1. International assistance routed 1003.00<br />

through Govt. budget<br />

2. Extenal commercial borrowings 396.00<br />

3. Internal resources 556.76<br />

4. <strong>Power</strong> Bonds 800.00<br />

5. Net Budgetary Support NIL<br />

TOTAL 2,755.77<br />

(includes Rs. 271.75 Crs. for T/L)<br />

6.9 Consultancy Services<br />

Within a year <strong>of</strong> its setting up, Consultancy Wing has<br />

made significant break through in the export market by<br />

obtaining the US$ 17.726 million contract for turunkey<br />

execution <strong>of</strong> 400 KV transmission line project from<br />

Dubai Electricity Company against stiff international<br />

competition. NTPC has opened a Site Office at Dubai<br />

and the project is under progress. Another export<br />

assignment has been obtained from Hydroelectric<br />

Commission, Tasmania for inspection <strong>of</strong> instrument<br />

transformers for their King and Anthony <strong>Power</strong> Station.<br />

The total foreign exchange earnings for the<br />

Consultancy Wing during the year 1990-91 have been<br />

Rs. 3.46 crores.<br />

In the domestic front also, the company has obtained<br />

several prestigious Consultancy Assignments in the<br />

year 1990-91 <strong>of</strong> a total estimated value <strong>of</strong> Rs. 635.50<br />

lakhs. Of these, the major assignments are from<br />

Damodar Valley Corporation for Maithon Right Bank<br />

Project, GVK Industries for 400 MW gas plant at<br />

Godavari, SAIL for 60 MW Captive <strong>Power</strong> Plant,<br />

MPEB for vendor assessment and OPGC for Cooling<br />

Water Studies for Ib Thermal <strong>Power</strong> Station. In the<br />

<strong>Power</strong> Systems area also several consultancy<br />

assignments have been received. Of these the major<br />

assignments are system studies for NHPC and<br />

Karnataka <strong>Power</strong> Corporation, Tower design/review for<br />

APSEB and BSES, Sub-station engineering for<br />

Karnataka Electricity Board. The work on DESU ring<br />

main and MSEB's Chandrapur-Padghe HVDC system<br />

have been taken up in full swing. The Mandaula 220<br />

KV sub-station which was executed on behalf <strong>of</strong> DESU<br />

has been commissioned.<br />

37<br />

NTPC - Vindhyachal<br />

Super Thermal <strong>Power</strong> Project<br />

The wing is registered with International financial<br />

institutions such as the Wold Bank, Asian Development<br />

Bank, African Development Bank as Consultants and<br />

also with export oriented Indian organisations such as<br />

EEPC and FIEO.<br />

MOUs have been signed with reputed international<br />

consultants such as Hydro Quebec International <strong>of</strong><br />

Canada, EPDC <strong>of</strong> Japan and EDF <strong>of</strong> France for joint<br />

execution <strong>of</strong> projects in third countries.<br />

With a total Consultancy order booking <strong>of</strong> over Rs. 50<br />

crores as on 31st March, <strong>1991</strong> and a turn over <strong>of</strong> Rs.<br />

1<strong>92</strong>.88 lakhs, NTPC is now well established as a<br />

consultant in the international <strong>power</strong> sector and hopes<br />

to expand this area <strong>of</strong> business considerably in future.<br />

6.10 Ash Utilisation<br />

With the objective <strong>of</strong> ensuring useful utilisation <strong>of</strong> the<br />

ash generated by the NTPC's <strong>power</strong> stations, an Ash<br />

utilisation division has been created with the<br />

responsibilities <strong>of</strong> identification <strong>of</strong> appropriate<br />

technologies and their adaptation for Indian conditions,<br />

setting up <strong>of</strong> pilot cum demonstration plants and<br />

participation in joint venture for manufacture <strong>of</strong> fly ash<br />

based products.


6.11 Solar Thermal Wing<br />

NTPC is planning to enter the solar thermal era and had<br />

recently established a solar thermal <strong>power</strong> wing, which<br />

is presently working on a solar thermal plant to be<br />

located in Rajasthan as an R&D Project. This is<br />

expected to open up a new chapter in exploiting the<br />

non-conventional energy sources in the country.<br />

6.12 MOU<br />

A Memorandum <strong>of</strong> Understanding (MOU) for the year<br />

<strong>1991</strong>-<strong>92</strong> was signed between the NTPC and the<br />

Department <strong>of</strong> <strong>Power</strong>. The MOU clearly identifies the<br />

performance targets to be achieved by the NTPC during<br />

the year with respect to <strong>Power</strong> generation, addition <strong>of</strong><br />

new capacity, construction <strong>of</strong> transmission lines, apart<br />

from laying down the actions to be taken by the<br />

Government to enable achievement <strong>of</strong> these targets.<br />

The details <strong>of</strong> targets for the year <strong>1991</strong>-<strong>92</strong> are given<br />

below :<br />

MOU Performance <strong>1991</strong>-<strong>92</strong><br />

MOU Target<br />

1. Capacity Addition (MW) 788<br />

2. Generation (MUs) 54847<br />

3. Transmission (EHV) lines 860<br />

construction (ckt. kms.)<br />

4. Turnover (Rs. Crores) 3164<br />

5. Pr<strong>of</strong>its (Rs. Crores) 468<br />

Against the above targets, NTPC, till Dec. <strong>1991</strong>, has<br />

added 210 MW Capacity, constructed 775 ckt. kms. <strong>of</strong><br />

transmission lines and has generated 44164 MUs <strong>of</strong><br />

electricity.<br />

6.13 BADARPUR THERMAL<br />

POWER STATION<br />

Badarpur Thermal <strong>Power</strong> Station comprises 3 x 100<br />

MW and 2 x 210 MW Units under the management <strong>of</strong><br />

NTPC Ltd. During the period April, <strong>1991</strong> to December,<br />

<strong>1991</strong> the Station has generated a total <strong>of</strong> 2842 MUs at a<br />

PLF <strong>of</strong> 61.08%<br />

The Generation Target and PLF for the year <strong>1991</strong>-<strong>92</strong><br />

are 3900 MUs and 63.15% respectively. The Station<br />

generated 3843 MUs in the Calender Year <strong>1991</strong> at a<br />

PLF <strong>of</strong> 62.23%. Specific Oil Consumption is 6.1 ml/<br />

Kwh in the year <strong>1991</strong>. Auxiliary <strong>Power</strong> consumption in<br />

the last three months has reduced by about 3% which is<br />

38<br />

Badarpur Thermal <strong>Power</strong> Project –<br />

A view <strong>of</strong> the demineralisation plant<br />

expected to save about 120 MUs per annum. BTPS has<br />

made a pr<strong>of</strong>it <strong>of</strong> Rs. 4.05 Crores in the current financial<br />

year (uptill Nov., 91). Energy conservation day was<br />

organised at BTPS on 14.12.91 and BTPS has been<br />

selected as the Pilot Project for implementation <strong>of</strong><br />

Energy Conservation by NTPC for the year 19<strong>92</strong>-93 as<br />

part <strong>of</strong> the National Energy Conservation Campaign.<br />

Under Renovation & Modernisation Phase-II<br />

Programme <strong>of</strong> BTPS, 32 packages have been identified<br />

for implementation and the proposal for the same has<br />

been submitted to Central Electricity Authority for<br />

according their Techno-economic clearance.<br />

6.14 NATIONAL HYDROELECTRIC<br />

POWER CORPORATION<br />

LIMITED<br />

The National Hydroelectric <strong>Power</strong> Corporation (NHPC)<br />

was incorporated in 1975 under the Companies Act,<br />

1956. The main objectives <strong>of</strong> the Corporation are to<br />

plan, promote and organise an integrated development<br />

<strong>of</strong> hydro-electric <strong>power</strong> in the country. The authorised<br />

share capital <strong>of</strong> the Corporation stands at Rs. 2500<br />

crores. The paid-up capital which was Rs. 1619.30<br />

crores as on 31.03.<strong>1991</strong> has increased to Rs. 1<strong>92</strong>2.41<br />

crores as at the end <strong>of</strong> December, 91. The pr<strong>of</strong>it during<br />

the year 1990-91 was Rs. 52.76 crores (before tax) as<br />

against Rs. 52.50 crores in the previous year. The<br />

turnover <strong>of</strong> the Corporation during the year<br />

1990-91. was Rs. 223.95 crores as against Rs. 209.87


crores in the previous year. The estimated pr<strong>of</strong>it for<br />

<strong>1991</strong>-<strong>92</strong> is Rs. 46 crores.<br />

NHPC is responsible for the operation and maintenance <strong>of</strong><br />

Baira Siul, Loktak and Salal (Stage-I) <strong>Power</strong> Stations<br />

located in Himachal Pradesh, Manipur and J&K<br />

respectively. The generation achieved during the year<br />

1990-91 in the above <strong>power</strong> stations was 3617.46 MU<br />

which is 113.12% <strong>of</strong> the targeted generation <strong>of</strong> 3198 M.U.<br />

The total generation during the year <strong>1991</strong>-<strong>92</strong> (upto<br />

December, '91) has been 2785.44 MUs against the target<br />

<strong>of</strong> 2770 MUs for the period.<br />

In addition to the generation in its own <strong>power</strong> stations,<br />

NHPC improted during 1990-91, 1389.29 MUs against a<br />

target <strong>of</strong> 1374 MUs <strong>of</strong> <strong>power</strong> from the Chukha Hydel<br />

Project, Bhutan. In <strong>1991</strong>-<strong>92</strong>, upto December, <strong>1991</strong> the<br />

Corporation imported 1331 MUs against the target <strong>of</strong><br />

1190 MUs. It also transmitted 304.52 MUs <strong>of</strong> <strong>power</strong><br />

during 1990-91 through its Jaypore-Talcher Transmission<br />

System in Orissa. During <strong>1991</strong>-<strong>92</strong>, upto December, 91,<br />

404.56 MUs <strong>of</strong> <strong>power</strong> were transmitted through the<br />

Jaypore Talcher Transmission System.<br />

In November, <strong>1991</strong>, all the transmission Lines under<br />

construction, operation and maintenance have been<br />

transferred to the newly set up National <strong>Power</strong><br />

Transmission Corporation Ltd. (NPTC) for construction,<br />

operation and maintenance on management basis for<br />

which necessary agreement was signed on 18th<br />

November, <strong>1991</strong>. These Transmission Lines will be<br />

transferred to NPTC on ownership basis in due course<br />

after obtaining necessary clearances.<br />

During the year, NHPC has been engaged in the<br />

costruction <strong>of</strong> the following H.E. Projects :-<br />

Sl. No. Name <strong>of</strong> the Project State (Installed<br />

capacity in<br />

MWs)<br />

(1) Chamera H.E. Project H.P. (3x180 MW)<br />

(Stage-I)<br />

(2) Tanakpur H.E. Project U.P. (3x40 MW)<br />

(3) Dulhasti H.E. Project J & K (3x130 MW)<br />

(4) Uri H.E. Project J & K (4x120 MW)<br />

(5) Salal H.E. Project J & K (3x115 MW)<br />

(Stage-II)<br />

(6) Rangit H.E. Project Sikkim(3x20 MW)<br />

While the Chamera Stage-I Project is being executed with<br />

financial and technical assistance from Canada, execution<br />

<strong>of</strong> the Dulhasti Project and the Uri Project with bilateral<br />

financial assistance have been awarded on turn-key basis<br />

to French and Swedish-British Consortia respectively.<br />

The status <strong>of</strong> progress <strong>of</strong> work on these Projects is as<br />

follows :-<br />

39<br />

(1) Chamera H.E. Project (Stage-I)<br />

Works on the various components <strong>of</strong> the Project like Main<br />

Dam, <strong>Power</strong> Tunnel, Tail Race Tunnel etc. were in<br />

progress during the year.<br />

Upto December, <strong>1991</strong> against a total quantity <strong>of</strong> 13.50<br />

lakhs M3 , 13.31 lakhs M3 <strong>of</strong> concrete placement was<br />

achieved in the Main Dam. Of the 6.4 KM long <strong>Power</strong><br />

Tunnel while heading has been completd, work on<br />

benching and overt lining was affected due to poor<br />

geological strata. In the squeezed portion <strong>of</strong> the Tunnel<br />

220 nos. <strong>of</strong> old ribs out <strong>of</strong> total <strong>of</strong> 370 nos. have been<br />

replaced and the work is in progress. As regards Tail Race<br />

Tunnel at the end <strong>of</strong> December, '91, overt lining was in<br />

progress and 1546 M, out <strong>of</strong> the total <strong>of</strong> 2414 M have<br />

been completed. In the <strong>Power</strong> House civil works for Unit-<br />

III are completd upto EL 553.5 M (Service Bay level). In<br />

UnitUnit-II, concreting <strong>of</strong> spiral casing and generator<br />

barrel has also been completed. On the Surge Shaft 52.4<br />

M concreting has been completed against the total height<br />

<strong>of</strong> 61 M. Erection <strong>of</strong> penstock liners and the work in<br />

switchyard area were in progress as at the end <strong>of</strong><br />

December, <strong>1991</strong>.<br />

On the Chamera-Moga Transmission Line associated with<br />

the Project, out <strong>of</strong> a total <strong>of</strong> 647 nos. towers, 645 nos. have<br />

been erected and stringing completed in 233 KM out <strong>of</strong><br />

total length <strong>of</strong> 236 KMs. The Project is scheduled for<br />

completion by December, 19<strong>92</strong>.<br />

(2) Tanakpur H.E. Project<br />

Most <strong>of</strong> the civil works are in final stages <strong>of</strong> completion.<br />

Initially the work on around 800 m <strong>of</strong> the left afflux bund<br />

lying in Nepal Area was not allowed to be carried out by<br />

Nepal Govt. authorities. This issue has now been resolved<br />

during the Prime Ministers meeting <strong>of</strong> India and Nepal<br />

during the Prime Minister's meeting <strong>of</strong> India and Nepal<br />

during December '91 and work has been taken up with<br />

effect from 15th December'91 and is now in full swing. As<br />

regards the <strong>Power</strong> House Installation works, Units I & III<br />

have been completed and work on Unit II is in advanced<br />

stage <strong>of</strong> completion. The work on silt ejector is<br />

progressing satisfactorily. Transmission Line work, for<br />

evacuation <strong>of</strong> <strong>power</strong>, is also progressing satisfactorily and<br />

stringing is expected to be completed by January'<strong>92</strong>. The<br />

Project is scheduled for completion by March'<strong>92</strong>.<br />

(3) Dulhasti H.E. Project<br />

Construction <strong>of</strong> C<strong>of</strong>fer Dam has been completed and<br />

concreting <strong>of</strong> Intake Portal has been taken up. Head Race<br />

Tunnel has been excavated upto 747 M by the Tunnel<br />

Boring Machine from upstream and 232 M by<br />

conventional methods, silt flushing tunnel has been


excavated upto 571 M. 15543 M3 excavation has been<br />

completed in <strong>Power</strong> House and crane Beam concreting<br />

has been completed. The Project is scheduled for<br />

completion in July, 1994.<br />

(4) Uri H.E. Project<br />

Following the abduction <strong>of</strong> two Swedish Engineers, the<br />

civil works contractor stopped the work w.e.f. April,<br />

<strong>1991</strong>. However, work on designs and drawings and<br />

manufacture <strong>of</strong> Gates, Electrical and Mechanical<br />

Equipment are progressing as per schedule. The civil<br />

works contractor has since resumed the work in the first<br />

week <strong>of</strong> December, <strong>1991</strong> after additional security<br />

arrangements and transportation facility, unrestricted<br />

access to relevant areas <strong>of</strong> work etc. have been ensured.<br />

The Project is scheduled for completion in Nov., 1995.<br />

(5) Salal H.E. Project (STAGE-II)<br />

During the year, work on <strong>Power</strong> House and Tail Race<br />

Tunnel <strong>of</strong> this Project were in progress. However, the<br />

work on the Tail Race Tunnel (inlet package) is behind<br />

schedule due to the slow progress made by the Contractor.<br />

The matter is being looked into far taking remedial action.<br />

The Project as per the present schedule is due for<br />

completion in Sept.'93 however this schedule may<br />

undergo revision on account <strong>of</strong> slow progress in the Tail<br />

Race Tunnel.<br />

(6) Rangit H.E. Project<br />

Infrastructure works and work on construction <strong>of</strong><br />

diversion tunnel and Head Race Tunnel are in progress.<br />

The construction <strong>of</strong> <strong>92</strong> temporary residential units was<br />

completed and the diversion tunnel 345 M tunnel boring<br />

was also completed upto December, <strong>1991</strong>. 88 M<br />

excavation <strong>of</strong> Adit <strong>of</strong> HRT from downstream side has<br />

been completed. Open excavation <strong>of</strong> Surge Shaft is also<br />

in progress. The contract for the construction <strong>of</strong> dam has<br />

been awarded and contract for <strong>power</strong> house civil works is<br />

under finalisation.<br />

The Project is scheduled for completion is Sept., 1995.<br />

6.15 NEW SCHEMES / PROJECTS<br />

(1) Dhauliganga H.E. Project :<br />

In April <strong>1991</strong>, investment approval was accorded by the<br />

Govt. for the execution <strong>of</strong> the Project at a cost <strong>of</strong><br />

Rs. 601.98 crores (Net including Rs. 84.53 crores as IDC<br />

for the generation portion <strong>of</strong> the Project). The land<br />

required for the Project is being identified with the help <strong>of</strong><br />

the State Government. The infrastructure activity <strong>of</strong> land<br />

acquisition and preparation <strong>of</strong> contract packages and other<br />

relevant works etc. were in progress.<br />

Tanakpur Barrage <strong>of</strong> NHPC.<br />

40


However, no project works could be taken up so far on<br />

account <strong>of</strong> paucity <strong>of</strong> funds.<br />

(2) Koel Karo H.E. Project :<br />

The Koel Karo H.E. Project in Bihar has been accorded<br />

investment approval in November, <strong>1991</strong> for execution<br />

at an estimated revised cost <strong>of</strong> Rs. 1338.81 crores<br />

including IDC <strong>of</strong> Rs. 202.38 crores. However, work on<br />

the Project structures could not be commenced so far on<br />

account <strong>of</strong> resource constraints.<br />

(3) Baglihar H.E. Project<br />

(3 x 150 MW) :<br />

The environmental and forest clearance for the Project<br />

have been accorded by the <strong>Ministry</strong> <strong>of</strong> Environment<br />

and Forests. The techno-economic clearance for the<br />

Project has also been accorded by CEA in April, '91<br />

and the Investment approval is being processed.<br />

(4) Sawalkot H.E. Project<br />

(3 x 200 MW) :<br />

The Pre-PIB Meeting was held on 14.6.91 and it was<br />

decided to update the estimates. Updating <strong>of</strong> estimates<br />

and firming up <strong>of</strong> technical parameters are in progress.<br />

NHPC also proposes to take up, in the future, the<br />

execution <strong>of</strong> the following Hydroelectric Projects which<br />

are under various stages <strong>of</strong> clearance:<br />

i) Chamera H.E. Project (Stage-II) (3x100 MW)<br />

ii) Teesta H.E. Project (Stage-III) (6x200 MW)<br />

iii) Kachchh Tidal <strong>Power</strong> Project (900 MW)<br />

6.16 PROJECTS UNDER<br />

INVESTIGATION:<br />

The investigation works on Kishenganga H.E. Project<br />

(330 MW) in J & K were completed and the DPR sent<br />

to CEA in May, <strong>1991</strong> for Techno Economic clearance.<br />

In respect <strong>of</strong> Goriganga H.E. Project (Stage-III) in U.P.<br />

geotechnical investigations are in progress.<br />

6.17 TRANSMISSION SYSTEMS :<br />

Work on the construction <strong>of</strong> the following transmission<br />

lines and sub stations were in progress during the year:i)<br />

400 KV Dul Hasti Transmission System & 400/<br />

220 KV Kishenpur Sub Station.<br />

ii) 132 KV S/C Bongaigaon-Gaylephug Transmission<br />

System.<br />

iii) 400 KV D/C Moga Bhiwani Transmission Line.<br />

iv) 400 KV Nathpa Jhakri Transmission System.<br />

v) Chamera (Stage-II) Transmission System.<br />

41<br />

The following Transmission Lines were also entrusted<br />

to NHPC for execution :<br />

i) Uri Transmission System.<br />

ii) 800 KV Kishenpur-Moga Transmission Line.<br />

iii) Jallundhar-Ludhiana-Dasuya Transmission<br />

System.<br />

6.18 MEMORANDUM OF<br />

UNDERSTANDING:<br />

In October, <strong>1991</strong> the Corporation signed a<br />

Memorandum <strong>of</strong> Understanding with the Department <strong>of</strong><br />

<strong>Power</strong> for the year <strong>1991</strong>-<strong>92</strong>. The MOU identifies the<br />

performance targets to be achieved by NHPC during<br />

the year with respect to <strong>Power</strong> generation, addition <strong>of</strong><br />

new capacity. It also lays down the support needed<br />

from the Govt. to achieve these targets.<br />

6.19 BONDS<br />

The Corporation has been asked to raise an amount <strong>of</strong><br />

Rs 615 crores by issue <strong>of</strong> Bonds in <strong>1991</strong>-<strong>92</strong>.<br />

6.20 RURAL ELECTRIFICATION<br />

CORPORATION<br />

Rural Electrification Corporation (REC) was set up in<br />

1969 with the primary objective <strong>of</strong> providing financial<br />

assistance for rural electrification programmes in the<br />

country. Rural electrification programmes undertaken<br />

by the REC cover electrification <strong>of</strong> villages, including<br />

tribal villages and Harijan Bastis, energisation <strong>of</strong><br />

pumpsets, provision <strong>of</strong> <strong>power</strong> for small and agro-based<br />

rural industries, lighting <strong>of</strong> rural households and street<br />

lighting. The corporation also provides assistance to the<br />

State Electricity Boards for taking up systems<br />

Improvement projects for strengthening and improving<br />

<strong>of</strong> sub-transmission and distribution system and<br />

improved reliability <strong>of</strong> supply.<br />

The authorised share capital <strong>of</strong> the Corporation is<br />

Rs. 400 crores. The paid up capital upto the year 1990-<br />

91 stood at Rs. 322.60 crores. During <strong>1991</strong>-<strong>92</strong> (upto<br />

December, 91), the Central Govt. have contributed<br />

Rs. 40 crores towards the share capital <strong>of</strong> the<br />

Corporation, thus increasing its equity capital base to<br />

Rs. 362.60 crores.<br />

Loans advanced by the REC to the State Electricity<br />

Boards (SEBs), State Governments and Rural Electric<br />

Cooperative Societies during the year 1990-91<br />

amounted to Rs. 709.09 croes. Inclusive <strong>of</strong> this, the<br />

total loan amount advanced put the end <strong>of</strong> 1990-91


Rural Electrification by REC<br />

aggregated to Rs. 5417.04 crores. During the current year,<br />

<strong>1991</strong>-<strong>92</strong> (upto December, 91) the REC has advanced<br />

Rs. 223 crores as loans.<br />

During the year 1990-91, the REC approved 1990 new<br />

projects involving a loan assistance <strong>of</strong> Rs. 961.82 crores.<br />

During the current year (upto December, 91), REC<br />

approved 38 new projects involving financial assistance<br />

<strong>of</strong> Rs. 74.60 crores. Cumulatively upto December, 91,<br />

REC sanctioned 23109 rural electrification projects,<br />

involving financial assistance <strong>of</strong> Rs. 7998.97 crores.<br />

During the year 1990-91, against the target <strong>of</strong><br />

electrification <strong>of</strong> 8,708 villages and energisation <strong>of</strong><br />

329160 pumpsets, 10,219 villages were electrified and<br />

513400 pumpsets energised. During the year <strong>1991</strong>-<strong>92</strong><br />

(upto December, <strong>1991</strong>) 2703 villages have been<br />

electrified and 2.17 lakh pumpsets have been energised.<br />

The level <strong>of</strong> rural electrification in the country has risen<br />

from mere 12.3% at the time <strong>of</strong> establishment <strong>of</strong> REC in<br />

1969 to 83.3% as <strong>of</strong> now. About one lakh villages are left<br />

for electrification, <strong>of</strong> which over 70,000 are already<br />

covered under REC sanctioned schemes. The number <strong>of</strong><br />

pumpsets energised, which stood at 10.9 lakhs at the time<br />

<strong>of</strong> setting up the Corporation, has raisen to about 91 lakhs<br />

as <strong>of</strong> now.<br />

As a result <strong>of</strong> a special drive launched by the Corporation<br />

for promoting household electrification in rural areas, a<br />

record number <strong>of</strong> 1.4 million connections were released<br />

during 1990-91. These connections included single point<br />

light connections provided to the households below the<br />

poverty line free <strong>of</strong> cost under Kutir Jyoti Programme.<br />

The corporaiton earned a net pr<strong>of</strong>it <strong>of</strong> Rs. 74.90 crores<br />

after tax during 1990-91, as against Rs. 56.48 crores in<br />

42<br />

the previous year, and declared dividend <strong>of</strong> Rs. 6.636<br />

crores for the year 1990-91.<br />

6.21 NORTH EASTERN ELECTRIC<br />

POWER CORPORATION<br />

The North Eastern Electric <strong>Power</strong> Corporation was<br />

constituted in 1976, under the Companies Act, with the<br />

aim <strong>of</strong> developing the large electric <strong>power</strong> potential <strong>of</strong> the<br />

North Eastern Region. The region has large water<br />

resources, gas oil reserves and coal deposits, all <strong>of</strong> which<br />

can be developed for <strong>power</strong> generation. The Corporation<br />

made a modest beginning with the implementation <strong>of</strong> the<br />

150 MW Kopili Hydro-electric project, which has since<br />

been commissioned fully. The Corporation has also<br />

undertaken investigation <strong>of</strong> various schemes with a view<br />

to prepare a shelf <strong>of</strong> projects to be implemented according<br />

to the demand for <strong>power</strong> and availability <strong>of</strong> resources. The<br />

various projects taken up by the Corporation are as<br />

follows:-<br />

6.22 PROJECTS COMPLETED:<br />

Kopili Hydro Electric Project.<br />

The project is located in the N.C. Hills District <strong>of</strong> Assam,<br />

and was commissioned in July, 1988. It is a twin project,<br />

consisting <strong>of</strong> two Dams and two water conductor systems<br />

leading from the Kopili reservoir to the Khandong <strong>Power</strong><br />

House (2x25 MW) and from the Umrong reservoir to the<br />

Kopili House (2x50 MW). The Khandong <strong>Power</strong> Station<br />

was commissioned in March/April, 1984. This project has<br />

already generated over 3063 million units <strong>of</strong> <strong>power</strong> till<br />

January, 19<strong>92</strong>, and has earned a revenue <strong>of</strong> over 200<br />

crores in terms <strong>of</strong> sale <strong>of</strong> <strong>power</strong>.<br />

6.23 PROJECTS UNDER EXECUTION<br />

Doyang Hydro electric Project:<br />

This project is located in the Wokha District <strong>of</strong> Nagaland<br />

and has a provision for installing 3 units <strong>of</strong> 25 MW each.<br />

Works <strong>of</strong> infrastructure development are nearing<br />

completion and the main works have also been taken up.<br />

The project is scheduled for commissioning in July, 1995.<br />

Ranganadi Hydro Electric Project:<br />

The project is located in the lower Subansiri District <strong>of</strong><br />

Arunachal Pradesh and has a provision for installing 3<br />

units <strong>of</strong> 135 MW each. Preliminary works on this project<br />

are in an advanced stage and the critical item, i.e. the main<br />

tunnel, has already been taken up. The project is<br />

scheduled for commissioning in March, 1997.


Assam Gas Based Combined Cycle <strong>Power</strong> Projects:<br />

This project envisages installation <strong>of</strong> 6 Nos. <strong>of</strong> 30-40 MW<br />

gas Turbines and 3 Nos. <strong>of</strong> 30-40 MW Waste Heat<br />

Recovery units working in combined cycle mode, at<br />

Kathalguri, Assam for utilising the natural gas from the<br />

Assam oil fields. At current prices the project is estimated<br />

to cost Rs. 816 crores.<br />

Land has been acquired and infrastructure is under<br />

development. The project is scheduled to be<br />

commissioned fully by August, 1995.<br />

Investigation Schemes:<br />

Investigation <strong>of</strong> the following schemes have been taken<br />

up by the Corporation with a view to prepare a shelf <strong>of</strong><br />

hydro electric projects. All these schemes are located in<br />

Arunachal Pradesh.<br />

1. Ranganadi HE Project (Stage-II) : 100 MW<br />

2. Damwe HE Project : 500 MW<br />

3. Dikrong HE Project : 100 MW<br />

4. Papumpam HE Project : 100 MW<br />

5. Kopili HE Project (Stage- : 25 MW<br />

II) in Assam<br />

6.24 FINANCIAL<br />

The authorised capital <strong>of</strong> the Corporation is Rs. 500 crores<br />

as on date. The pattern <strong>of</strong> investment for financing the<br />

project under execution by the Corporation is generally in<br />

the ration <strong>of</strong> 1:1 for equity and loan.<br />

6.25 POWER FINANCE<br />

CORPORATION LIMITED<br />

1. The <strong>power</strong> Finance Corporation Limited (PFC) was<br />

incroported on July 10, 1986 with the objective <strong>of</strong><br />

providing term finance for <strong>Power</strong> Generation Projects<br />

(Hydel & Thermal). Transmission and Distribution,<br />

System Improvement, Urban Distribution, Renovation &<br />

Modernisation, Survey & Investigation and Training <strong>of</strong><br />

Personnel engaged in the <strong>Power</strong> Development<br />

Programme. The Corporation commenced its business<br />

during 1987-88.<br />

2. The funds are mainly provided to the State Electricity<br />

Boards and State <strong>Power</strong> Generation Corporation. The<br />

projects are formulated and implemented by these bodies.<br />

The funds provided by the Corporation are in the nature <strong>of</strong><br />

additionality to Plan allocation, and are available for<br />

application based on merits <strong>of</strong> the individual projects.<br />

3. In the past 3 years, the Corporation adopted a strategy<br />

to maximise availability <strong>of</strong> <strong>power</strong> in the short-term and to<br />

guide the development <strong>of</strong> the <strong>Power</strong> Sector along the<br />

43<br />

optimal path in the long term. The operations <strong>of</strong> the<br />

Corporation aim at augumenting resources for the <strong>power</strong><br />

sector and bringing about improvement in efficiency–<br />

both Operational and Financial during the 8th plan.<br />

4. The authorised share Capital <strong>of</strong> the Corporation is<br />

Rs. 2000 crores. The Paid-up Capital is Rs. 975.45 crores<br />

which is subscribed entirely by the Central Government.<br />

To augument its resources, PFC has so far raised funds by<br />

the issue <strong>of</strong> Bonds <strong>of</strong> Rs. 1460 crores. It has also raised<br />

Rs. 232.14 crores <strong>of</strong> foreign currency loan.<br />

5. During the <strong>1991</strong>-<strong>92</strong>, negotiations have been completed<br />

with ADB for a direct loan <strong>of</strong> $ 250 million for the <strong>Power</strong><br />

Sector Efficiency Improvement Project and with World<br />

Bank for a loan <strong>of</strong> US $ 265 millions. The Corporation<br />

has also signed an agreement with USAID for Energy<br />

Management Consultation and Training (EMCAT)<br />

programme for a grant <strong>of</strong> US $ 14 million.<br />

6. With a view to improving the operational efficiency and<br />

financial performance <strong>of</strong> the SEBs/SGPCs, the<br />

Corporation expects them to formulate an Operational and<br />

Financial Action Plan (OFAP). The OFAPs for Andhra<br />

Pradesh, Gujarat, Madhya Pradesh, Punjab, Orissa and<br />

Karnataka Electricity Boards, and Damodar Valley<br />

Corporation have been finalised. These regulatory lending<br />

policies have shown positive response to inculcate in the<br />

borrowers a sense <strong>of</strong> the need for prudent financial<br />

management.<br />

7. The expected pr<strong>of</strong>it after tax for the year <strong>1991</strong>-<strong>92</strong> is<br />

Rs. 100 crores against Rs. 73.18 crores in 1990-91.<br />

(Rs. Cr.)<br />

Sl. Scheme Loans sanctioned/ Cumulative Loans<br />

No. disbursed in sanctioned/<br />

<strong>1991</strong>-<strong>92</strong> disbursed upto<br />

30/11/<strong>1991</strong><br />

Sanctioned Disbursed Sanctioned Disbursed<br />

1. 2. 3. 4. 5. 6.<br />

1. Renovation & 23.69 30.66 356.06 148.93<br />

Modernisation<br />

2. Transmission, 86.89 134.60 1238.30 682.91<br />

Sub-Transmission<br />

& Urban Distribution.<br />

3. Shunt 16.40 10.83 169.70 108.05<br />

Capacitors<br />

4. Generation 44.50 214.<strong>92</strong> 1790.24 1642.54<br />

Projects<br />

171.48 391.01 3554.30 2582.43


6.26 NATIONAL POWER<br />

TRANSMISSION CORPORATION LTD.<br />

The National <strong>Power</strong> Transmission Corporation Limited<br />

(NPTC) was incorporated on 23rd October, 1989 with<br />

an authorised share capital <strong>of</strong> Rs. 5000 crores, under the<br />

Companies Act, 1956 to undertake the massive<br />

programme <strong>of</strong> laying the Extra High Voltage (EHV)/<br />

High Voltage Direct Current (HVDC) transmission<br />

system and associated sub-stations as well as<br />

constructing load despatch and communication<br />

facilities in a coordinated and efficient manner with a<br />

view to move large blocks <strong>of</strong> <strong>power</strong> from various<br />

generating sources under the Central Sector to the load<br />

centres within the region as well as across the regions<br />

with reliability, security and economy. The registered<br />

<strong>of</strong>fice <strong>of</strong> the Corporation is situated at New Delhi.<br />

The setting up <strong>of</strong> the Corporation would:<br />

i) help in pooling all the expertise in this field<br />

under one Central organisation and keeping<br />

abreast <strong>of</strong> the latest technology development.<br />

ii) bring about economies <strong>of</strong> scale in the design,<br />

construction, maintenance and operation <strong>of</strong> EHV<br />

lines.<br />

iii) ensure timely and economical implementation <strong>of</strong><br />

the massive programme <strong>of</strong> transmission line<br />

construction in the 8th and 9th Plan.<br />

iv) provide the institutional mechanism for creation<br />

<strong>of</strong> a communication network in the <strong>power</strong> sector<br />

and the computer hardware and s<strong>of</strong>tware for load<br />

despatch, automatic generation control, etc. (As<br />

this involves considerable system expertise,<br />

NPTC will be able to take up such schemes in a<br />

cost effective manner which will lead to more<br />

effective manner which will lead to more<br />

efficient control <strong>of</strong> the grid operation on real<br />

time basis.<br />

v) provide missing links which will strengthen the<br />

grid and facilitate grid operations with greater<br />

security and reliability.<br />

vi) would facilitate the growth <strong>of</strong> the economic<br />

exchange <strong>of</strong> <strong>power</strong> by taking up constructions <strong>of</strong><br />

the inter-regional links. (This would ultimately<br />

lead to the formation <strong>of</strong> the National <strong>Power</strong> Grid<br />

and ensure better utilisation <strong>of</strong> the available<br />

generation resources).<br />

44<br />

vii) ensure delivery <strong>of</strong> the entitled share <strong>of</strong> <strong>power</strong><br />

from the central generation.<br />

viii) relieve central generation companies <strong>of</strong> the<br />

responsibility <strong>of</strong> construction and operation <strong>of</strong><br />

the transmission lines, enabling them to<br />

concentrate on the massive new capacity<br />

additions programme in the 8th plan and bring<br />

up the same in the prescribed time schedule.<br />

The Management <strong>of</strong> Transmission and work <strong>of</strong> NTPC.<br />

NHPC and NEEPCO has been taken over by NPTC.<br />

The man<strong>power</strong> associated with this work in these<br />

Central Public Undertakings have also been transferred<br />

and absorbed in NPTC. The NTPC, NHPC, NEEPCO<br />

and NPTC have been asked to complete the required<br />

formalities for de-jure transfer <strong>of</strong> assets.<br />

Physical Progress for <strong>1991</strong>-<strong>92</strong><br />

The following 400 KV/220 KV lines will be<br />

completed during <strong>1991</strong>-<strong>92</strong> as under :<br />

Lines kms.<br />

1. Vijayawada-Gajuwaka 332<br />

2. Gooty-Bangalore 302<br />

3. Maithon-Jamshedpur 306<br />

4. Agra-Ballabhgarh 182<br />

5. Khammam-Vijayawada 126<br />

6. Farakka-Durgapur 146<br />

7. Ramagundam-Khammam 189<br />

8. Chamera-Moga 472<br />

9. 220 KV Tanakpur-Bareilly 212<br />

Total: 2267<br />

6.27 TEHRI HYDRO DEVELOPMENT<br />

CORPORATION LIMITED<br />

The Tehri Hydro Development Corporation (THDC)<br />

was incorporated on 12th July, 1988, as a joint venture<br />

<strong>of</strong> the Govt. <strong>of</strong> India and Govt. U.P. to execute the<br />

Tehri Hydro <strong>Power</strong> Complex in Garhwal Distt. <strong>of</strong> U.P.<br />

The Tehri Hydro <strong>Power</strong> Complex, the largest<br />

multipurpose development venture in the country, will<br />

provide both irrigation and <strong>power</strong> benefits and usher in<br />

an era <strong>of</strong> rapid development in Uttar Pradesh. The<br />

project is being executed with technical and financial<br />

assistance <strong>of</strong> the Soviet Union. The Corporation has an<br />

authorised share capital <strong>of</strong> Rs. 1200 Crores.


Salient Features:<br />

A 260.5 metres high earth and rockfill dam, across<br />

the river Bhagirathi at Tehri, just after its confluence<br />

with river Bhilangana for creating a storage reservoir<br />

to generate <strong>power</strong> and provide irrigation facilities.<br />

• An underground <strong>power</strong> house <strong>of</strong> 1000 MW (4x250<br />

MW) capacity with conventional turbine-Generating<br />

sets under Stage-I at Tehri.<br />

• Second underground <strong>power</strong> house <strong>of</strong> 1000 MW<br />

(4x250 MW) capacity with reversible pump turbine<br />

sets under Stage-II at Tehri Pump Storage Plant).<br />

• A 103.5 metre high concrete dam (which will<br />

provide a balancing reservoir) with a surface <strong>power</strong><br />

house <strong>of</strong> 400 MW (4x100 MW) capacity at<br />

Koteshwar, 22 Km, downstream <strong>of</strong> Tehri dam site<br />

across the river Bhagirathi.<br />

• Transmission system for evacuation <strong>of</strong> <strong>power</strong><br />

generated Tehri at an Koteshwar projects, through<br />

two single circuits 6765 KV lines to Meerut for<br />

utilisation in Northern Region.<br />

The esimated cost <strong>of</strong> the entire Tehri Hydro <strong>Power</strong><br />

Complex is Rs. 5058 Crores at December, <strong>1991</strong><br />

price level. An expenditure <strong>of</strong> about Rs. 653 Crores<br />

has been incurred on the project till December, <strong>1991</strong>.<br />

Project Status<br />

• Infrastructure woks completed.<br />

• 4 Nos. diversion tunnels 11 M dia each completed.<br />

• 4 Nos. 8.5 M dia each Head Race Tunnel excavation<br />

completed and lining works is nearing completion.<br />

• Various approach adits to underground <strong>Power</strong> House<br />

cavern completed.<br />

• Foundation work <strong>of</strong> C<strong>of</strong>fer Dam & the Main Dam<br />

have been completed and dam raised to RL. 615<br />

metre throughout its length.<br />

45<br />

PROJECT COST AND COMMISSIONING<br />

SCHEDULE<br />

(Rs. in Crores)<br />

PROJECT ESTIMATED COST COMMISSIONING<br />

(AT DEC., <strong>1991</strong> SCHEDULE<br />

PRICE LEVEL) (PLANNED)<br />

i) Tehri Dam & HPP<br />

(4x250 MW)<br />

2618 1996-97<br />

ii) Koteshwar Dam & HPP<br />

(4x100 MW)<br />

654 1996-97<br />

iii) Tehri Pump Storage<br />

Plant (4x250 MW)<br />

1090 1996-97<br />

iv) Associated Transmission<br />

System (800 KV)<br />

696 1996-97<br />

Total 5058<br />

6.28 NATHPA JHAKRI POWER<br />

CORPORAION LTD. (1500 MW)<br />

Nathpa Jhakri <strong>Power</strong> Corporation (NJPC) was<br />

incorporated on 24th May, 1988 as a Joint Venture <strong>of</strong><br />

Govt. <strong>of</strong> India and Government <strong>of</strong> Himachal Pradesh both<br />

sharing the cost <strong>of</strong> the projects in the ratio <strong>of</strong> 3:1<br />

respectively to plan, promote, organise and execute<br />

Hydroelectric <strong>Power</strong> Projects in the Satluj river basin in<br />

Himachal Pradesh.<br />

NJPC is presently executing its first project Nathpa Jhakri<br />

Hydro-electric Project (Installed Capacity=1500 MW) in<br />

Distt. Kinnaur/Shimla (HP) for which World Bank has<br />

sanctioned a Loan <strong>of</strong> US # 437 million. Besides this<br />

project, NJPC has taken up pre-construction planning <strong>of</strong><br />

Kol Dam Project (I.C. = 800 MW).<br />

Main Features <strong>of</strong> Nathpa Jhakri Project<br />

The Nathpa Jhankri <strong>Power</strong> Project envisages the<br />

construction <strong>of</strong>:<br />

- 60.50 m high concrete dam on Satluj river at Nathpa<br />

to divert 405 cumecs <strong>of</strong> water through four intakes.<br />

- underground desilting complex, comprising four<br />

chambers, each 525 m long, 16.31 m wide and 27.5<br />

m deep, one <strong>of</strong> the largest underground complex in<br />

the World.


Managlad, Adit - Nathpa Jhakri Project<br />

- 10.15 m dia. and 27.295 Km. long head race tunnel<br />

(the longest hydro <strong>power</strong> tunnel in the World)<br />

terminating in a 21 m dia. and 301 m deep surge<br />

shaft.<br />

- three circular steel-lined pressure shafts, each 4.9 m<br />

dia. and 633 m long bifurcating near the <strong>power</strong> house<br />

to feed six units.<br />

- Underground <strong>Power</strong> House with a cavern size <strong>of</strong> 216<br />

m x 20 m x 49 m having six Francis Units <strong>of</strong> 250<br />

MW each to utilise a design discharge <strong>of</strong> 405 cumecs<br />

and a design head <strong>of</strong> 425 m.<br />

- 10.15m. dia and 1080m long tail race tunnel to<br />

discharge the water back into the river Satluj.<br />

The Project is envisaged to be commissioned by March,<br />

1997. The approved estimated cost <strong>of</strong> Generating<br />

Component <strong>of</strong> this Project at Sept., 1988 price index was<br />

Rs. 1678.02 crore including Rs. 206.02 crores as interest<br />

during construction. At December, 1990 price index the<br />

anticipated cost is Rs. 2140 crores including Rs. 275<br />

crores I.D.C. The cost estimate and commissioning<br />

schedule is under revision.<br />

The Project will generate 6700 million units in a 90%<br />

dependable year and 7447 million units in an average<br />

year, providing 1500 MW <strong>of</strong> peaking <strong>power</strong> to the<br />

Northern Region. Cost <strong>of</strong> geneation at bus bar is estimated<br />

@ 57.63 paise/Kwh and 51.85 paise/Kwh in 90%<br />

dependable year and average year respectively (on<br />

December, 1990 price level).<br />

46<br />

Progress <strong>of</strong> Infrastructure Works<br />

Preliminary surveys and discharge data observations are<br />

being carried out at site. Rocks & material tests are being<br />

conducted by CSMRS, New Delhi. Model studies for<br />

various components <strong>of</strong> the Project are being done at<br />

CWPRS, Pune and UPIRI, Roorkee.<br />

220/66/22 KV Sub-station at Jeori is under construction<br />

and will be commissioned by March, 19<strong>92</strong>. Development<br />

<strong>of</strong> infrastructure is well scheduled to meet the<br />

requirements <strong>of</strong> main civil contractor's when they arrive at<br />

site.<br />

Progress <strong>of</strong> Award <strong>of</strong> Main Works<br />

(a) Major Civil Works<br />

The major civil works will be put up to International<br />

Competitive Bidding in the following three contract<br />

packages :<br />

Contract No. 1 : Dam Intake and Desilting<br />

arrangement<br />

Contract No. 2 : Lot 2.1 HRT put STA 16042m and<br />

sholding works:<br />

Lot 2.2 HRT from STA 16042m to<br />

STA 27235m and surge shaft.<br />

Contract No. 3 : Pressure Shaft, <strong>power</strong> house and<br />

TRT including its Appurtinent<br />

works.<br />

Pre-qualification for tendering was invited on global basis<br />

for turbine, generator and associated equipment for the<br />

project. Process <strong>of</strong> pre-qualification has been finalised.<br />

Panel <strong>of</strong> Expert Meeting<br />

A panel <strong>of</strong> experts (POE) meeting was organised from 9th<br />

to 16th November, <strong>1991</strong> wherein apart from six Indian<br />

Experts, four foreign experts also participated. Technical<br />

Memos were presented to POE. POE has submitted their<br />

<strong>report</strong>. The view <strong>of</strong> POE are being studied in detail and<br />

the same would be incorporated in existing designs and<br />

construction scheme <strong>of</strong> this prestigious project <strong>of</strong> NJPC.


Kol Dam Hydro-Electric Project<br />

(I.C. = 800 MW)<br />

The Kol Dam Hydro-Electric Project which is located on<br />

Satluj river in Bilaspur district <strong>of</strong> Himachal Pradesh<br />

envisages utilisation <strong>of</strong> a drop about 140 mtrs. by<br />

constructing a 163 mt. high rockfill Dam and a <strong>Power</strong><br />

Station, with an installed capacity <strong>of</strong> 800 MW, at the toe<br />

<strong>of</strong> Dam. It is expected to provide an <strong>annual</strong> energy<br />

generation <strong>of</strong> 3089 million units in a 90% dependable<br />

year. The Project is estimated to cost Rs. 1354 crores at<br />

December, 90 price level, with a generation cost <strong>of</strong> 74.06<br />

Paise/unit.<br />

The Project is proposed to be completed in a period <strong>of</strong><br />

61 / years including 1 2 1 / years for infrastructural<br />

2<br />

development. M/s. Technopromexport, USSR has already<br />

submitted their Final Appraisal Report <strong>of</strong> the Kol Dam<br />

Project indicating its technical feasibility. Financial<br />

proposal <strong>of</strong> USSR's participation in execution <strong>of</strong> the<br />

project is awaited. The Project has been approved by PIB<br />

in July, <strong>1991</strong> and the approval <strong>of</strong> CCEA is under active<br />

consideration.<br />

6.29 DAMODAR VALLEY<br />

CORPORAITON<br />

The Damodar Valley Corporation was established in July,<br />

1948 under the Damodar Valley Corporation Act. The<br />

Corporation has a fulltime chairman and two part-time<br />

members. The part-time Members represent the States <strong>of</strong><br />

Bihar and West Bengal.<br />

The Functions <strong>of</strong> the Corporation include :<br />

• the promotion and operation <strong>of</strong> schemes for irrigation,<br />

water supply and drainage;<br />

• the promotion and operation <strong>of</strong> schemes for the<br />

generation, transmission and distribution <strong>of</strong> energy,<br />

both hydro-electric and thermal;<br />

• the promotion and operation <strong>of</strong> schemes for flood<br />

control in the Damodar river and its tributaries and the<br />

channels excavated by the Corporation for the<br />

improvement <strong>of</strong> flow conditions in the Hooghly river;<br />

• the promotion and control <strong>of</strong> Navigation in the<br />

Damodar river and its tributaries and channels, if any;<br />

• the promotion <strong>of</strong> afforestation and control <strong>of</strong> soil<br />

erosion in the Damodar Valley; and<br />

• the promotion <strong>of</strong> public health and the agricultural,<br />

industrial, economic and general well-being in the<br />

Damodar Valley and its areas <strong>of</strong> operation.<br />

47<br />

The Corporation has so far constructed four multi-purpose<br />

dams at Tilaiya, Konar, Maithon and Panchet. The<br />

irrigation system comprises a barrage over river Damodar<br />

at Durgapur and the canal system <strong>of</strong> 2495 Kms which<br />

includes 137 kms long irrigation-cum-navigation canal on<br />

the left bank <strong>of</strong> the river Damodar. The management <strong>of</strong><br />

irrigation system excluding the navigation canal was<br />

transferred to the Government <strong>of</strong> West Bengal in 1964.<br />

The installed capacity (derated) and geneation <strong>of</strong> <strong>power</strong><br />

during the year <strong>1991</strong>-<strong>92</strong> upto November, <strong>1991</strong>, are as<br />

follow :-<br />

Name <strong>of</strong> Installed capcity Generation MU upto<br />

Station (MW) 30th November, <strong>1991</strong>.<br />

1) Bokaro 3x50 - 150<br />

1x40 - 40<br />

190 363.77<br />

2) Bokaro 'B' 1x210 210 662.22<br />

3) C.T.P.S. 3x14 - 420<br />

3x120 - 360<br />

780 1173.89<br />

4) D.T.P.S. 1x140 - 140<br />

1x210 - 210<br />

350 717.01<br />

3268.89<br />

Gas Turbine 3x27.5 - 82.5<br />

at Maithon<br />

Hydel<br />

82.5 40.00<br />

Tilaiya 2x2 4 10.99<br />

Panchet 1x40 40 164.24<br />

Maithon 3x20 60 136.<strong>92</strong><br />

312.15<br />

Total Generation : 3621.04<br />

• BTPS 'A' Unit 4 derated to 40 MW from Janaury, 1990.<br />

•• Panchet unit 2 synchronised on 5.3.91 and generated<br />

80.46 MU upto 30.11.91.<br />

The position relating to the on-going generation and<br />

transmission projects <strong>of</strong> the Corporation is given in the<br />

table on the following page.


Work under Capacity Target date for<br />

Progress<br />

Generation Project<br />

completion.<br />

1) Bokaro 'B' 2x210 MW 420 MW Unit II Synchronised<br />

Stage-II<br />

2) Panchet Unit<br />

on 7.11.90,<br />

Unit III, June, 19<strong>92</strong><br />

Reversible pump 1x40 MW 40 MW First synchronised<br />

turbine on 5.3.91.<br />

3) Mejia Thermal 3x210 MW 630 MW Unit-I Dec, 1993<br />

<strong>Power</strong> Station Unit-II June, 1994.<br />

Unit-III Dec. '94.<br />

4) Maithon Right 4x210 MW 840 MW This Soviet assisted<br />

Bank project has been taken<br />

Thermal <strong>Power</strong> up for implementation<br />

Station and the agreement sign<br />

on 16.1.89, Unit-I<br />

Feb '95.<br />

5) Maithon Gas 3x27.5 82.5 MW After successful<br />

Turbine synchronisation and<br />

completion <strong>of</strong> trial run<br />

and performance test<br />

<strong>of</strong> all the units, the<br />

DVC has since taken<br />

over and put to<br />

commercial operation.<br />

b) Transmission Projects<br />

1) 220 KV Bokaro "B" 85% work completed<br />

Jamshedpur line Target March, 19<strong>92</strong><br />

2) 220 KV Kalyaneswari - Kolipahori Target December,<br />

Majia line <strong>1991</strong>.<br />

3) 220 KV CTPS-DTPS - Mejia line Target march, 19<strong>92</strong>.<br />

4) 132 KV Sindri-Prodhan Khanta<br />

line<br />

Completed.<br />

5) 33 KV Ramgarh-West Bokaro line Forest clearance still<br />

awaited.<br />

6) 33 KV West Bokaro-Kalda line Work completed.<br />

Awaited<br />

commissioning, Line<br />

checking and precommissioning<br />

going<br />

on.<br />

7) 33 KV line for supply <strong>of</strong> <strong>power</strong> Receiving point not<br />

to Karo special (CCL) yet finalised by CCL.<br />

8) 220 KV CTPS switchyard (3rd 80% work complected.<br />

150 MVA Auto transformer)<br />

9) 220 KV Jamshedpur sub-stn.<br />

Target March, 19<strong>92</strong>.<br />

(Phase-II) Completed.<br />

10) 220 KV DTPS switchyard (3rd 90% work completed.<br />

150 MVA Auto transformer) Target March, 19<strong>92</strong>.<br />

48<br />

Tail Pool Dam Panchet<br />

Work <strong>of</strong> Tail Pool Dam on the left bank side has not yet<br />

started. On the right bank side earth work is in progress<br />

for the approach road and the position <strong>of</strong> Earth Dam<br />

extending to that side. Pending completion <strong>of</strong> the Tail<br />

Pool Dam, Panchet Hill Unit-2 (reversible pump turbine<br />

type), which is presently under advanced stage <strong>of</strong><br />

construction, will run as conventional unit during the<br />

monsoon period only.<br />

Training<br />

DVC introduced modern training methods in collaboration<br />

with PETS and a Training Institute has been set up a<br />

Chandrapura Thermal <strong>Power</strong> Station to Impart training to<br />

Graduate Engineers (Trainee) <strong>of</strong> all disciplines and<br />

operatives. In addition, <strong>of</strong>ficers <strong>of</strong> different disciplines are<br />

sponsored for training in different institutions under<br />

Executive Development Scheme from time to time. DVC<br />

has also scheme to sponsor <strong>of</strong>ficers for foreign training<br />

under Colombo Plan etc. on need basis.<br />

The Capital Expenditure <strong>of</strong> DVC is met from its internal<br />

resources and is supplemented by Market Borrowing.<br />

The Damodar Valley Corporation constituted the major<br />

<strong>power</strong> infra-structure in the <strong>power</strong> sector for the Coal<br />

Mines, Steel Plants, Railways and Copper Mines located<br />

in the Eastern Region. The other beneficiaries are the<br />

West Bengal and Bihar State Electricity Boards and<br />

Calcutta Electric Supply Corporation. <strong>Power</strong> generation in<br />

the DVC system is shared between Bihar and West<br />

Bengal regions approximately in the proportion <strong>of</strong> 65%<br />

and 35% respectively.<br />

Damodar Valley Corporation – 630 MW.<br />

Mejia Thermal <strong>Power</strong> Station under Construction


During the year 1990-91 the net deficit on <strong>power</strong> system<br />

amounted to Rs. (-) 19.89 crores. The return on Capital<br />

and resources employed was 1.22%.<br />

6.30 BHAKRA BEAS MANAGEMENT<br />

BOARD AND B.C.B.<br />

The administration, operation and maintenance <strong>of</strong> Bhakra<br />

Nangal & Beas projects has been entrusted to the Bhakra<br />

Beas Management Board, under the Punjab<br />

Reorganisation Act, 1966. The works on Bhakra Nangal<br />

project consist <strong>of</strong> the Bhakra Dam, two <strong>power</strong> Houses i.e.<br />

Left Bank and Right Bank <strong>power</strong> plants, Nangal Dam,<br />

Nangal Hydel Channel (NHC), two <strong>power</strong> plants namely<br />

Ganguwal and Kotle on NHC. The Beas project consists<br />

<strong>of</strong> two units namely Unit No. I and Unit No. II. Unit No. I<br />

comprises the Pandeh Dam, Pandeh Baggi Tunnel,<br />

Sundernagar Hydel Channel, Balancing Reservoir,<br />

Sundernagar Sutlej Tunnel, Dohar <strong>Power</strong> Plant including<br />

Surge Shaft and bye Pass Chute. Unit No. II comprises<br />

the Pong Dam, the Pong <strong>Power</strong> plant, two Irrigation<br />

Tunnels and the Spillway.<br />

The installed capacity <strong>of</strong> the <strong>power</strong> plants is as under:-<br />

<strong>Power</strong> House Installed capacity (MW)<br />

1. Bhakra (Right Bank) 5x132 = 660<br />

2. Bhakra (Left Bank) 5x108 = 540<br />

3. Ganguwal 2x24+1x29 = 77<br />

4. Kotla 2x24+1x29 = 77<br />

5. Dehar 6x165 = 990<br />

6. Pong 6x60 = 360<br />

Total 2704<br />

The BBMB also manages the Operation and Maintenance<br />

<strong>of</strong> large transmission system comprising 574.30 circuit<br />

Kms <strong>of</strong> 400 KV lines and 2975.00 circuit Kms <strong>of</strong> 220<br />

lines extending from Bhakra, Pong and Dehar to Delhi<br />

passing through Himachal Pradesh, Punjab and Haryana<br />

and having three Nos. 400 KV Sub-Stations at Dehar,<br />

Panipat & Bhiwani and eighteen 220 KV Sub-station at<br />

various other places.<br />

Inflows into the Reservoirs:<br />

(A) Bhakra Reservoir<br />

The maximum reservoir level attained was (512.237<br />

mtrs.) on 15-9-<strong>1991</strong> against the maximum permissible<br />

level <strong>of</strong> 1685.00 (513.588 mtrs.). The total quanity <strong>of</strong><br />

49<br />

water received in the Bhakra Reservoir during the period<br />

April to December, <strong>1991</strong> was 15.6854 MAF (19347.627<br />

MOM, comprising 12.2167 MAF (15069.06 cm) <strong>of</strong> Sutlej<br />

water and 3.4687 MAF (4278.57 MOM) <strong>of</strong> Beas diverted<br />

water through BSL System. It is anticipated that during<br />

the period Ist January to 31st March, 19<strong>92</strong>, the Sutlej<br />

inflows into Bhakra Reservoir would be approximately<br />

0.6302 MAF (777.34 MOM) and Beas diverted water<br />

0.3531 MAF (435.542 MOM) based on dry year pattern<br />

<strong>of</strong> inflows. The total inflow ensuing the previous year<br />

were 18.0528 MAF (22268 MOM).<br />

(B) Pong Reservoir:<br />

The maximum reservoir level attained was 1390.28'<br />

(423.757 mtrs.) on 24.9.91 against the maximum<br />

permissible level <strong>of</strong> 1400.00' (426.72 mtrs.). The total<br />

quantity <strong>of</strong> water received during the period April to<br />

December, 91 is 5.7509 MAF (7093.62 MOM). It is<br />

expected that 0.2237 MAF (276 MOM) would be received<br />

in Pong Reservoir during the period Ist January to 31st<br />

March, 19<strong>92</strong> based on dry year pattern <strong>of</strong> inflows. The<br />

total inflows during the previous year were 9.3060 MAF<br />

(11479 MOM).<br />

Generation<br />

The actual generation from BBMB <strong>Power</strong> Houses during<br />

the period Ist April 91 to December <strong>1991</strong> was 10120<br />

MUs. The estimated generation during the period January,<br />

19<strong>92</strong> to March, <strong>92</strong> would be about 2120 MUs. Thus the<br />

total estimated generation from BBMB <strong>Power</strong> Houses<br />

during the year <strong>1991</strong>-<strong>92</strong> would be about 12240 MUs<br />

against the Generation target <strong>of</strong> 11010 MUs for the year.<br />

<strong>1991</strong>-<strong>92</strong> fixed by CEA.<br />

B.C.B. Works<br />

400 KV Dehra-Bhiwani Line and allied works have been<br />

handed over to BBMB on 23-10-90. During the year<br />

under <strong>report</strong>, disposal <strong>of</strong> surplus stores, machinery &<br />

other spares etc. for an amount <strong>of</strong> Rs. 456.64 lacs (upto<br />

31/12/91) has been done & further for an amount <strong>of</strong><br />

Rs. 100.00 lacs approx. is expected upto 31/3/<strong>92</strong>.<br />

6.31 POWER ENGINEERS TRAINING<br />

SOCIETY (PETS)<br />

The <strong>Power</strong> Engineers Training Society (PETS) was<br />

established by the Government <strong>of</strong> India in 1980 to<br />

function as national apex body for meeting the training<br />

need <strong>of</strong> the <strong>power</strong> sector. The existing four Thermal<br />

<strong>Power</strong> Stations Personnel Training Institutes at Neyveli,<br />

Durgapur, Badarpur and Nagpur were set up by the Govt.<br />

<strong>of</strong> India in 1965, 1968, 1974 and 1975,


espectively under the overall control <strong>of</strong> the Central<br />

Electricity Authority (CEA). These Institutions were<br />

engaged in the training <strong>of</strong> engineers and operators <strong>of</strong><br />

thermal <strong>power</strong> stations. To achieve better coordination<br />

<strong>of</strong> training activities, PETS was formed in 1980 as an<br />

autonomous body and all the four Institutes were<br />

transferred to PETS. The <strong>Power</strong> Engineers Training<br />

Society has since been organising training programmes<br />

for <strong>power</strong> engineers, operators and technicians in its<br />

Institutes.<br />

2. The training courses conducted at the Regional<br />

Institutes <strong>of</strong> PETS include the following:-<br />

- Induction Level Courses for Graduate Engineers.<br />

- Induction Level Courses for Operators in Thermal.<br />

- Induction Level Courses for Technicians.<br />

- Courses on <strong>Power</strong> Station Chemistry for Chemists.<br />

- Short-term courses for Engineers (General)<br />

(Mechanical) (Electrical) (Control & Instrumentation).<br />

- Short-term courses for Supervisors/Technicians<br />

(Mechancial)/Electrical)/Control & Instrumentation).<br />

- Simulator courses for Graduate Engineers/Shift Changer<br />

Engineers, unit controller/Desk Controllers etc.<br />

3. PETS has been organising, training programmes for<br />

<strong>Power</strong> Sector and have trained about 30,141 personnel<br />

upto March, <strong>1991</strong>. The number <strong>of</strong> persons trained in the<br />

different courses at the Institutes during <strong>1991</strong>-<strong>92</strong> (upto<br />

November, <strong>1991</strong>) is as follows :-<br />

Sl. No. Courses No. <strong>of</strong> trainees<br />

(1) Regular courses for Engineers 101<br />

(2) Condensed course for Engineers 97<br />

(3) Operator courses 108<br />

(4) Short-term courses for Engineers 484<br />

(5) Maintenance courses for Technicians 504<br />

(6) On Plant/On-site courses 1169<br />

(7) PETS-BHEL courses on 210 MW TPS 50<br />

Operations<br />

(8) Simulator course 202<br />

Total: 2715<br />

4. The Simulator for 210 MW Units installed with<br />

UNDP assistance at Badarpur Institute in 1983, has<br />

provided training to more than 2300 engineers by 30th<br />

November, <strong>1991</strong>.<br />

50<br />

5. The following short-term courses/workshops have<br />

been organised or are planned to be organised by PETS in<br />

collaboration with BEI, U.K.:-<br />

(i) National Seminar on <strong>Power</strong> Plant Rehabilitation and<br />

Modernisation from 25-27th November, <strong>1991</strong> at New<br />

Delhi.<br />

(ii) Three-day Residential programme on Environmental<br />

Management conducted at Goa from 11-13th February,<br />

19<strong>92</strong>.<br />

6. For the current financial year <strong>1991</strong>-<strong>92</strong>, the<br />

Department <strong>of</strong> <strong>Power</strong> has released Rs. 100 lakhs as Plan<br />

and Rs. 191 lakhs as Non-plan grants-in-aid to PETS. The<br />

training fee during <strong>1991</strong>-<strong>92</strong> is targetted to fetch a revenue<br />

<strong>of</strong> Rs. 72.36 lakhs.<br />

7. During 1990-91, the Government has sanctioned<br />

schemes for installation <strong>of</strong> one 500 MW Simulator at<br />

Badarpur and one 210 MW Simulator at Nagpur Insititute.<br />

Action has already been taken for supply and installation<br />

<strong>of</strong> 500/210 MW Simulators. The schemes are targetted to<br />

be completed by July, 1994. The other Regional <strong>Power</strong><br />

Training Institutes are proposed to be augumented during<br />

the Ninth Plan Period.<br />

8. The scheme for Housing Complex for Badarpur<br />

Institute Sanctioned on 26.12.88 at an estimated cost <strong>of</strong><br />

Rs. 345.68 lakhs is in an advanced stage <strong>of</strong> completion.<br />

9. The scheme for conversion <strong>of</strong> existing <strong>Power</strong><br />

Engineers Training Society (PETS) into National <strong>Power</strong><br />

Training Institute (NPTI) was sanctioned, in Februrary,<br />

<strong>1991</strong> at an estimated cost <strong>of</strong> Rs. 1273.14 lakhs. The<br />

scheme envisaged - (a) Upgrading the present PETS into<br />

NPTI; and (b) Setting up <strong>of</strong> an Institute for Advanced<br />

Learning and Management Studies (INALMAS) at<br />

Faridabad, Haryana. Action has already been taken to<br />

introduce different courses as required under NTPI. A<br />

number <strong>of</strong> long-term courses as per statutory requirement<br />

and specialised short-term courses are also being<br />

conducted in Hydro and <strong>Power</strong> System areas. As input to<br />

the <strong>power</strong> system courses, orders have been placed for<br />

computer based <strong>power</strong> system study packages for<br />

development <strong>of</strong> s<strong>of</strong>tware with 1000 buses and 20 HVDC<br />

lines. Computer based hardware required for the same is<br />

also being procured. A Desk Top publishing system is<br />

under installation at PETS HQ for development <strong>of</strong> training<br />

material.


6.32 CENTRAL POWER RESEARCH<br />

INSTITUTE (CPRI)<br />

The Central <strong>Power</strong> Research Institute (CPRI) was<br />

established in 1960 by the Government <strong>of</strong> India, to serve<br />

as a national laboratory for applied research in electrical<br />

<strong>Power</strong> engineering and also to function as an independent<br />

authority for testing and certification <strong>of</strong> electrical<br />

equipments manufactured in the country. CPRI was reorganized<br />

into an autonomous society in 1978 under the<br />

<strong>Ministry</strong> <strong>of</strong> Energy (Department <strong>of</strong> <strong>Power</strong>), Government<br />

<strong>of</strong> India.<br />

2. The Institute has its main laboratories and<br />

corporate <strong>of</strong>fice at Bangalore and a unit at Bhopal for<br />

testing and development <strong>of</strong> switchgears. A research<br />

facility in UHV AC transmission technology is coming up<br />

near Hyderabad. The work has just started at the Thermal<br />

<strong>Power</strong> Research Centre at Koradi near Nagpur, Regional<br />

Testing Laboratory at Muradnagar and the one Energy<br />

Research Centre at Thiruananthapuram. A Flyash<br />

Utilization Demonstration Centre has been commissiond<br />

at Raichur Thermal <strong>Power</strong> Station, Karnataka.<br />

3. The Institute has identified many R&D problems<br />

for investigation which are <strong>of</strong> importance and relevance to<br />

the electric <strong>power</strong> sector. A number <strong>of</strong> technical problems<br />

faced by <strong>power</strong> utilities and manufacturing industries are<br />

also referred to the Institute for investigation and finding<br />

solutions in the form <strong>of</strong> sponsored research projects.<br />

Central <strong>Power</strong> Research Institute –<br />

Testing <strong>of</strong> 220 KV Transmisssion Tower<br />

51<br />

4. As a result <strong>of</strong> its R&D efforts, the Institute has<br />

been able to develop a number <strong>of</strong> new proudcts and<br />

processes useful in the <strong>power</strong> sector. They are found to be<br />

<strong>of</strong> great improtance in energy saving, <strong>power</strong> system<br />

improvement, pr<strong>of</strong>itable utilization <strong>of</strong> waste products,<br />

curtailing distribution lossess, etc. Many <strong>of</strong> these products<br />

and processes are transferred to entrepreneurs for<br />

commercial exploitation.<br />

5. With a view to expose the engineers & scientists<br />

to the latest developments in the pr<strong>of</strong>essional field, the<br />

Institute organises seminars/workshops on different<br />

subjects. During the year Institute has organized four<br />

national seminars/workships. A large number <strong>of</strong> technical<br />

papers were presented and discussed at these seminars/<br />

workshops.<br />

6. Forty six technical <strong>report</strong>s were issued upto 31<br />

December <strong>1991</strong> bringing out the results <strong>of</strong> R&D<br />

investigations carried out. The engineers and scientists <strong>of</strong><br />

the Institute presented/published a large number <strong>of</strong><br />

research papers during the year in various symposia/<br />

technical journals in India and abroad.<br />

7. The CPRI provides testing and consultancy<br />

services to electricity supply utilities, manufacturing<br />

industries and other organisations for new product<br />

development and quality assurance. It has also helped<br />

towards import substitution.<br />

8. The Institute is fully equipped for development<br />

testing <strong>of</strong> switchgear and fusegear, transformers,<br />

<strong>power</strong>cables, capacitors solid insulating materials,<br />

insulation oils and varnishes, transmission linetowers etc.<br />

For effective quality control, facilities are available for<br />

testing impulse and <strong>power</strong> frequency <strong>of</strong> <strong>power</strong> equipment,<br />

short circuit testing <strong>of</strong> switchgear and fusegear,<br />

transformers, CTs and other <strong>power</strong> system apparatus and<br />

evaluation testing <strong>of</strong> <strong>power</strong> cables, capacitors solid<br />

insulating materials, insulating oils and varnishes etc., in<br />

accordance with various standards. New testing facilities<br />

are being set-up by the Institute to cater to the increasing<br />

testing needs from time to time.<br />

9. Upto 31 December, <strong>1991</strong>, the Institute has tested<br />

3223 samples and 1229 organizations have availed<br />

themselves <strong>of</strong> the testing and certification facilities during<br />

the year.<br />

10. The revenue realised by the Institute during the<br />

last three years is as follows:<br />

1989-90 1990-91 <strong>1991</strong>-<strong>92</strong> (upto 31 Dec <strong>1991</strong>)<br />

Rs. 477 Lakhs Rs. 502 Lakhs Rs. 436 Lakhs


11. During 1989-90 the Institute had earned adequate<br />

revenue to meet its non-plan expenditure. No grant-in-aid<br />

was therefore released from the Government during these<br />

years to meet the non-plan expenditure.<br />

The Institute was self-sufficient during <strong>1991</strong>-<strong>92</strong> also in so<br />

far as non-plan expenditure is concerned.<br />

12. The following major capital projects continued to<br />

be under various stages <strong>of</strong> execution by the Institute<br />

during the year.<br />

(1) 2500 MVA High <strong>Power</strong> Testing station Rs. 9744.00 Lakhs<br />

(2) UHV/AC Research Laboratory, Hyderabad Rs. 1705.53 Lakhs<br />

(3) Thermal <strong>Power</strong> Research Centre, Koradi<br />

(Nagpur) Rs. 1718.17 Lakhs<br />

(4) Regional Testing Laboratory, Murandnagar Rs. 636.00 Lakhs<br />

(U.P.)<br />

13. Under Phase I <strong>of</strong> the long term R&D co-operation<br />

programme with CESI, Italy, engineers and scientists <strong>of</strong><br />

CPRI and CESI have jointly worked on many projects<br />

concerning topics and problems <strong>of</strong> current interest.<br />

14. CPRI received one award each from Institute <strong>of</strong><br />

Electrical Engineers, Japan, National Design Award by<br />

Instititution <strong>of</strong> Engineers (India) and 3 awards from<br />

CBI &P during the year <strong>1991</strong>.<br />

15. Training programme for middle level <strong>of</strong>ficers to<br />

give exposure to Research and Development work as well<br />

as testing facilities at CPRI were conducted.<br />

16. Several s<strong>of</strong>tware packages developed by CPRI in<br />

the field <strong>of</strong> distribution planning, transmission tower<br />

design analysis, load forecasting, load scheduling etc.,<br />

have found favour with utilities who are approaching<br />

CRPI for using the s<strong>of</strong>tware.<br />

6.33 ENERGY MANAGEMENT<br />

CENTRE<br />

Energy Management Centre was established by the<br />

Government <strong>of</strong> India in April 1989 to act as a focal point<br />

for exchange <strong>of</strong> experience among energy institutes within<br />

India and has a Centre for information, research and<br />

training activities in the energy field based on cooperation<br />

between India and the European Communities.<br />

The institutional structure for determing and directing<br />

energy policies is a two-tired one. The Energy<br />

Conservation Cell in the Department <strong>of</strong> <strong>Power</strong>, <strong>Ministry</strong><br />

<strong>of</strong> <strong>Power</strong> & NES, formulates policy, designs the energy<br />

management programme and ensures effective<br />

52<br />

co-ordination between interested Ministries and other<br />

entities. The Energy Mangement Centre is the executive<br />

agency under this policy function, designed to implement<br />

and monitor the Energy Conservation programme.<br />

Role as Coordinator:<br />

There are a number <strong>of</strong> institutions in the field <strong>of</strong> energy<br />

management today which are doing highly competent and<br />

effective works in this field. It has been felt that there has<br />

to be an organisation for taking over overall strategic<br />

vision supported by quantitiative analysis <strong>of</strong> work being<br />

done in the field <strong>of</strong> energy management so far in the<br />

country and also steps to be taken to improve energy<br />

efficiency further. Energy Management Centre has<br />

therefore been set up as a Centre <strong>of</strong> excellence for<br />

research, training and information in energy policy and<br />

management. The Centre is a focal point <strong>of</strong> institutional<br />

network between India and the European Communities.<br />

Organisation <strong>of</strong> the Centre:<br />

EMC has been registered as a Society under the<br />

Registration <strong>of</strong> Societies Act 1860, so that it functions as<br />

an independent and autonomous body. This gives it the<br />

responsibility and required flexibility to make its<br />

operations more dynamic.<br />

Its Operational Headquater is in Delhi while the Training<br />

Headquarter is at Nagpur.<br />

Activities <strong>of</strong> the Centre:<br />

The activities <strong>of</strong> EMC are as follows:<br />

- develop a National Energy database by collecting and<br />

analysing data on energy supply, demand and<br />

information on prices;<br />

- identify barriers for improving energy efficiency and<br />

propose appropriate incentives and other measures to<br />

overcome them. These would include<br />

recommendations for assistance with capital<br />

investment, taxes, duties and other financial<br />

incentives;<br />

- review laws and regulations that have an impact on<br />

energy consumption and propose modifications and<br />

formulate suitable policies and actions;<br />

- suggest introduction <strong>of</strong> standards and lables and<br />

setting <strong>of</strong> consumption targets, - provide planning<br />

assistance to government agencies, organise public<br />

information and promotional campaigns on an ongoing<br />

basis;<br />

- organise sector specific promotional campaigns for<br />

the main energy consuming sectors (industry,<br />

transport, agriculture, commercial and government<br />

buildings). Also provide technical assistance in the<br />

field <strong>of</strong> energy efficiency to these sectors;<br />

- promote energy audits in enterprises and provide<br />

recommendations to improve energy efficiency


and fuel substitution;<br />

- monitor progress made in energy conservation and<br />

fuel substitution and initiate follow-up actions where<br />

needed;<br />

- organise training for energy managers and equipment<br />

operators;<br />

- implement multilateral and bilateral aided<br />

conservation projects;<br />

International Cooperation Projects:<br />

At present the EMC is implementing the following<br />

projects:<br />

(i) UNDP-Energy Bus Project<br />

(ii) EEC-India Energy Bus Programme<br />

(iii) ESCAP Regional TCDC Working<br />

Group on Energy Conservation<br />

(iv) World Bank Industrial Efficiency<br />

Project<br />

Expenditure during the year 1990-91 and budget<br />

estimates for the year <strong>1991</strong>-<strong>92</strong><br />

The total expenditure <strong>of</strong> the EMC during the year 1990-91<br />

was Rs. 157.24 lakhs. The budget estimates for the year<br />

<strong>1991</strong>-<strong>92</strong> is Rs. 122.68 lakhs against which an expenditure<br />

<strong>of</strong> Rs. 58.28 lakhs has been incurred till November, <strong>1991</strong>.<br />

6.34 ACC BABCOCK LIMITED<br />

By a decision <strong>of</strong> Government, March 1989, ACC<br />

Babcock Limited (ABL), the premier boiler<br />

manufacturing company, was placed under the<br />

administrative control <strong>of</strong> Department <strong>of</strong> <strong>Power</strong>. The<br />

manufacturing range <strong>of</strong> ABL, apart from <strong>power</strong> and<br />

industrial boilers, includes Cement manufacturing<br />

machinery, Pressure vessels, Electro-static precipitators<br />

(ESPs) air quality control system, machinery for<br />

chemical, metallurgical, sugar, defence and mineral ore<br />

processing industry, miscellaneous Engg. equipment and<br />

foundry products. ABl's manufacturing units are in<br />

Durgapur, in West Bengal and Shahabad in Karnataka.<br />

ABL has a subsidiary, namely Babcock & Wilcox India<br />

Limited (B&WI), located in Clacutta, which specialises in<br />

erection and commissioning.<br />

With over a quarter <strong>of</strong> century <strong>of</strong> proven experience, ABL<br />

is one <strong>of</strong> the largest heavy engineering companies in India<br />

with a wealth <strong>of</strong> expertise garnered from the renowed<br />

promoters and other well known organisations through<br />

technical collaboration. ABL which started functioning in<br />

1962, ceased functioning following filing <strong>of</strong> a winding-up<br />

petition before Bombay High Court by its previous<br />

management in October, 1986. Under an IDBI/BIFR<br />

package, which was approved by Government, ABL<br />

53<br />

resumed operations in June, 1988, under the<br />

administrative control <strong>of</strong> Department <strong>of</strong> <strong>Power</strong><br />

(Government <strong>of</strong> India). The Department <strong>of</strong> Atomic<br />

Energy and Department <strong>of</strong> <strong>Power</strong> <strong>of</strong> Government <strong>of</strong><br />

India have extended a long term interest free loan to the<br />

extent <strong>of</strong> Rs. 13 crores each, totalling to Rs. 26 crores.<br />

Financial institutions led by IDBI have extended<br />

assistance for the revival <strong>of</strong> the company. The State<br />

Governments <strong>of</strong> Karnataka and West Bengal have<br />

extended concessions regarding collection <strong>of</strong> Central<br />

sales tax from ABL's units located in these States.<br />

Department <strong>of</strong> <strong>Power</strong> had submitted a proposal to Govt.<br />

on future course <strong>of</strong> action for rehabilitation <strong>of</strong> ACC<br />

Babcock Limited. The proposal was approved on 7th<br />

February, 19<strong>92</strong>. The basic thrust <strong>of</strong> Department <strong>of</strong><br />

<strong>Power</strong>'s proposal was to furnish gurantees/counter<br />

guarantees to ABL for financial assistance from the SBI<br />

and other financial institutions amounting to Rs. 180.54<br />

crores.<br />

Major Orders booked during the period under review<br />

includes:<br />

Order Value<br />

(Rs. Crores)<br />

1. 2x250 MW Budge-Budge TPs <strong>of</strong> CESC 190.00<br />

2. Retr<strong>of</strong>it <strong>of</strong> ESPs for BALCO Managed 23.00<br />

by NTPC<br />

3. Retr<strong>of</strong>it <strong>of</strong> ESPs for Nasik TPS <strong>of</strong> MSEB 16.00<br />

4. Conversion boilers for HPC-30% advance 12.00<br />

for supply<br />

5. Recovery boiler for Bhadrachalam 6.00<br />

paper Board<br />

6. Boilers <strong>of</strong> Madras Refinery 19.00<br />

The company after revival has Successfuly commissioned<br />

the following projects:<br />

1. Kolaghat <strong>of</strong> (WBPDCL) (1x210 MW)<br />

2. Bokaro <strong>of</strong> (DVC) (1x210 MW)<br />

3. Khammam Heavy Water (3x265 TPH)<br />

plant <strong>of</strong> (DAE)<br />

4. Boilers for Manadya Paper Mills<br />

5. Boilers for Bhadrachalam paper Boards<br />

6. Boilers for Ballarpur Industries<br />

Working on the revival plan, an improved order book<br />

position and identification <strong>of</strong> new opportunities for<br />

diversification, ABL is expected to contribute its mite<br />

in the <strong>power</strong> sector as a reputed manufacturer <strong>of</strong><br />

boilers.


ELECTRICITY STATISTICS AT A GLANCE<br />

ELECTRICITY-INSTALLED CAPACITY, GENERATION & CONSUMPTION<br />

Unit 1970-71 71-75 79-80 80-81 81-82 82-83 83-84 84-85 85-86 86-87 87-88 88-89* 89-90* 90-91*<br />

Installed Capacity<br />

Utilities+Non-Utilities MW 16271 20345 31307 33316 35781 3<strong>92</strong>35 43706 47705 52273 54980 60500 65560 70501 74456<br />

Utilities MW 14709 18317 28148 30214 32345 35363 39339 42585 46769 4<strong>92</strong>66 54155 59040 63627 66055<br />

Hydro MW 6383 7529 11384 11791 12173 13056 13856 14460 15472 16196 17265 17798 18308 18753<br />

Nuclear MW 420 640 640 860 860 860 1095 1095 1330 1330 1330 1565 1565 1565<br />

Thermal (Coal) MW 7508 9753 15991 17128 18695 20712 23648 26311 28809 30394 34237 37943 41510 43379<br />

Oil & Gas MW 398 395 433 440 617 735 740 719 1158 1346 1323 1734 2244 2358<br />

Non-Utilities MW 1562 2028 2859 3102 3436 3872 4367 5120 5504 5714 6345 6520 6874 8402<br />

Generation (U+NU) BU 61.21 76.68 112.82 119.26 131.12 140.30 150.99 169.21 183.39 201.28 218.98 240.35 266.20 288.71<br />

Utilities BU 55.83 70.20 104.63 110.84 122.10 130.26 140.18 156.86 170.35 187.71 202.09 221.38 245.40 264.61<br />

Hydro BU 25.25 27.88 45.48 46.54 49.56 48.37 49.95 53.95 51.02 53.84 47.44 57.87 62.05 71.68<br />

Nuclear BU 2.42 2.21 2.88 3.00 3.02 2.02 3.55 4.07 4.98 5.02 5.04 5.82 4.63 6.14<br />

Thermal (Coal) BU 27.80 39.50 55.72 60.71 68.75 77.91 84.44 96.96 112.54 125.45 145.81 154.87 172.68 179.70<br />

Oil & Gas BU 0.36 0.57 0.55 0.59 0.77 1.96 2.24 1.88 1.81 3.40 3.80 2.82 6.04 7.09<br />

Non-Utilities BU 5.38 6.48 8.19 8.42 9.02 10.04 10.81 12.35 13.04 13.57 16.89 18.97 20.80 24.10<br />

Auxiliary<br />

Consumption (U+NU) BU 3.44 4.86 7.35 8.20 9.38 10.21 11.41 13.28 14.84 15.96 18.20 19.46 22.66 22.57<br />

T&D Losses BU 9.31 13.56 20.06 21.32 23.59 25.64 27.69 31.21 34.19 37.78 42.23 44.51 52.21 56.52<br />

Consumption (U+NU) BU 43.46 58.26 85.39 89.74 98.15 104.45 111.89 124.72 134.36 147.84 158.55 176.38 191.33 209.62<br />

Industrial BU 34.33 38.31 53.24 55.40 60.89 61.75 66.55 73.56 79.44 81.95 82.94 <strong>92</strong>.68 98.19 106.21<br />

Transport BU 1.37 1.53 2.30 2.27 2.50 2.83 2.71 2.88 3.08 3.26 3.65 4.07 4.18 4.15<br />

Agriculture BU 4.47 7.76 13.45 14.49 15.0 17.82 18.23 20.96 23.42 29.44 35.27 38.85 43.64 49.47<br />

Domestic, Commercial<br />

and Services BU 8.29 10.66 16.40 17.58 19.56 22.25 24.40 27.32 28.42 32.89 36.69 40.78 45.32 49.79<br />

Includes not energy exported to neighbouring countries.<br />

* Provisional<br />

54


Tehri Project—View <strong>of</strong> Bhagirathi River Diversion


INSTALLED GENERATING CAPACITY AS ON 31.3.<strong>92</strong> (UTILITIES)*<br />

REGION/STATE/UT HYDRO THERMAL NUCLEAR TOTAL<br />

(MW) (%) (MW) (%) (MW) (%) (MW)<br />

HARYANA 883.90 49.6 896.42 50.4 0.00 0.0 1780.32<br />

HIMACHAL PRADESH 272.07 99.5 1.50 0.5 0.00 0.0 273.57<br />

JAMMU & KASHMIR 180.31 68.8 81.76 31.2 0.00 0.0 262.07<br />

PUNJAB 1798.94 54.7 1490.00 45.3 0.00 0.0 3288.94<br />

RAJASTHAN 962.93 55.7 765.00 44.3 0.00 0.0 1727.93<br />

UTTAR PRADESH 1504.55 26.4 4204.69 73.6 0.00 0.0 5709.24<br />

CHANDIGARH 0.00 0.0 2.00 100.0 0.00 0.0 2.00<br />

DELHI 0.00 0.0 551.60 100.0 0.00 0.0 551.60<br />

CENTRAL SECTOR 645.00 9.4 5307.00 77.3 910.00 13.3 6862.00<br />

TOTAL (NR) 6247.70 30.5 13299.97 65.0 910.00 4.4 20457.67<br />

GUJARAT 425.00 9.0 4314.33 91.0 0.00 0.0 4739.33<br />

MADHYA PRADESH 725.09 21.4 2657.50 78.6 0.00 0.0 3382.59<br />

MAHARASHTRA 1570.22 17.1 7634.50 82.9 0.00 0.0 <strong>92</strong>04.72<br />

GOA 0.00 ERR 0.00 ERR 0.00 ERR 0.00<br />

D&N HAVELI 0.00 ERR 0.00 ERR 0.00 ERR 0.00<br />

CENTRAL SECTOR 0.00 0.0 3496.00 84.2 655.00 15.8 4151.00<br />

TOTAL (WR) 2720.31 12.7 18102.33 84.3 655.00 3.0 21477.64<br />

ANDHRA PRADESH 2511.94 59.5 1711.50 40.5 0.00 0.0 4223.44<br />

KARNATAKA 2372.20 79.0 630.00 21.0 0.00 0.0 3002.20<br />

KERALA 1491.50 100.0 0.00 0.0 0.00 0.0 1491.50<br />

TAMIL NADU 1944.95 45.3 2350.00 54.7 0.00 0.0 4294.95<br />

PONDICHERRY 0.00 ERR 0.00 ERR 0.00 ERR 0.00<br />

CENTRAL SECTOR 0.00 0.0 3750.00 88.9 470.00 11.1 4220.00<br />

TOTAL (SR) 8320.59 48.3 8441.50 49.0 470.00 2.7 17232.09<br />

BIHAR 153.30 9.9 1399.43 90.1 0.00 0.0 1552.73<br />

ORISSA 1221.<strong>92</strong> 72.2 470.00 27.8 0.00 0.0 1691.<strong>92</strong><br />

WEST BENGAL 46.91 1.5 30<strong>92</strong>.47 98.5 0.00 0.0 3139.38<br />

DVC 144.00 7.1 1887.50 <strong>92</strong>.9 0.00 0.0 2031.50<br />

SIKKIM 26.59 90.8 2.70 9.2 0.00 0.0 29.29<br />

CENTRAL SECTOR 0.00 0.0 840.00 100.0 0.00 0.0 840.00<br />

TOTAL (ER) 15<strong>92</strong>.72 17.2 76<strong>92</strong>.10 82.8 0.00 0.0 <strong>92</strong>84.82<br />

ASSAM 2.00 0.4 55.19 99.6 0.00 0.0 557.19<br />

MANIPUR 2.60 21.6 9.41 78.4 0.00 0.0 12.01<br />

MEGHALAYA 186.71 96.4 7.05 3.6 0.00 0.0 193.76<br />

NAGALAND 2.50 40.8 3.62 59.2 0.00 0.0 6.12<br />

TRIPURA 16.01 29.3 38.64 70.7 0.00 0.0 54.65<br />

ARUNACHAL PRADESH 19.26 68.2 8.99 31.8 0.00 0.0 28.25<br />

MIZORAM 2.37 9.2 23.35 90.8 0.00 0.0 25.72<br />

CENTRAL SECTOR 255.01 100.0 0.00 0.0 0.00 0.0 255.01<br />

TOTAL (NER) 486.46 42.9 646.25 57.1 0.00 0.0 1132.71<br />

A & N ISLANDS 0.00 0.0 27.69 100.0 0.00 0.0 27.69<br />

LAKSHADWEEP 0.00 0.0 5.08 100.0 0.00 0.0 5.08<br />

ALL INDIA 19367.78 27.8 48214.<strong>92</strong> 69.3 2035.00 2.9 69617.70<br />

STATE SECTOR 18047.77 37.3 30362.<strong>92</strong> 62.7 0.00 0.0 48410.69<br />

PVT. SECTOR 276.00 9.7 2571.50 90.3 0.00 0.0 2847.50<br />

CENTRAL SECTOR<br />

* Anticipated<br />

1044.01 5.7 15280.50 83.2 2035.00 11.1 18359.51<br />

56